xAI, Southaven

the Mississippi Development Authority · Jan 9, 2026 · Updated Nov 23, 2026, 13:04 ET
StatusUnder construction
Investment, as stated$20 billion
Jobs, as statedNot stated
Power, as statednearly 2 gigawatts

What the release says

Project · Reskill Report summary

The Mississippi Development Authority said xAI is locating a data center, called MACROHARDRR, in Southaven in a retrofitted building. The agency says the investment exceeds $20 billion and will create hundreds of permanent jobs. It said the agency approved a sales and use tax exemption, and xAI expects operations to begin in February 2026.

From the release: “xAI has purchased and is retrofitting a building to house the new data center operations.”

Release headline: Tech leader xAI investing more than $20 billion in Southaven

This is the issuer's own account. Figures are what it announced, not what has been built, and nothing here is independently verified.

What has been announced since

DateReleaseFrom
Jan 8, 2026Tech leader xAI investing more than $20 billion in Southaven · on this trackerthe office of the governor of Mississippi

These are other releases that name xAI and Southaven, or are announcements about xAI in Mississippi on this tracker. We follow press releases from governors, state agencies, attorneys general and the companies' own newsrooms. Permits, local decisions and construction progress are not covered unless one of those reports them, so the absence of an update here does not mean nothing has happened.xAI is a party in 12 lawsuits on our court tracker.

Source

  • The summary is ours, written from the release linked above and checked against it. The quoted passage and each stated figure are copied from the release.
  • A project can appear in more than one announcement on this tracker. This one repeats an earlier release about the same project, so our counts take the project once.