Reskill ReportTracking AI's effect on jobs, power and the law

Data Center Tracker

How fast data centers are being built in the United States, where they are, what grid operators expect, and what officials are announcing: federal construction figures, a map, and a log of project and policy announcements.

Last updated Nov 23, 2026, 19:46 ET
Data center construction, annual rate, September 2026$96.5 billion
A year earlier$50.7 billion
Change in a year+90.3%
Five years earlier$10.8 billion

Spending on data center construction

$24B$48B$72B$96B2014201620182020202220242026
Private construction spending on data centers, seasonally adjusted annual rate, January 2014 to September 2026 (latest month preliminary). It counts the value of building work put in place each month, not the computers that go inside. Source: U.S. Census Bureau, Construction Spending · CSV

Figures to cite

Project announcements in 2026Official releases on our log47
Investment those releases state23 of them give a figure$225.2 billion
Power those releases state22 of them give a figure19,684 MW
PJM's forecast of large new loads in 2030PJM 2026 load forecast38,815 MW
Large loads approved to connect in TexasERCOT, October 20269,456 MW
Jobs in data processing and hostingBLS; 2019: 344,059488,955
Data center buildings mappedOpenStreetMap1,862
Each figure is explained, with its source, in the section it links to.

Largest projects announced in 2026

ProjectStateAnnouncedStatusInvestmentMWJobs
Meta, Richland ParishLA07/13/26Expansion$50 billion5,0001,000
Lambda, Lowndes CountyAL11/04/26Announced$33.1 billion225
xAI, SouthavenMS01/08/26Under construction$20 billion
Google, Montgomery CountyMO05/20/26Announced$15 billion
Starwood Digital Ventures, Mason CountyWV09/03/26Approved$12 billion2,160
Amazon, Madison CountyMS04/09/26Expansion$11 billion700
Meta, El PasoTX10/15/26Announced$10 billion1,000300
QTS Data Centers, Hall CountyTX07/13/26Announced$10 billion350
Amazon, Montgomery CityMO06/15/26Announced$10 billion400
QTS Data Centers, Van WertOH05/29/26Announced$10 billion200
Meta, LebanonIN02/11/26Under construction$10 billion300
CoreWeave, LancasterPA10/22/26Announced$6 billion30075
Microsoft, Village of Mount PleasantWI06/23/26Opened$4.7 billion550
TeraWulf, Hancock CountyKY08/24/26Approved$4.5 billion482
Sabey Data Centers, Decatur TownshipIN08/27/26Announced$4.3 billion75

Ranked by the investment each official release states, then by stated power. These are announced figures, not what has been built, and a blank means the release gave none. Projects no followed office announced are not here. All 47 project announcements in 2026

Grid forecast: Mid-Atlantic and Midwest

PJM, which runs the grid from New Jersey to Illinois, forecasts how much power large new customers will need in each utility's zone. It says most of that is data centers. Figures are megawatts added to the summer peak.

Zone20262030203520402045
All of PJM11,47938,81568,97782,65686,511
Dominion (Virginia, N.C.)7,06613,89622,42631,35035,010
AEP (Ohio, Ind., Va., W.Va. and others)2,6998,66516,27620,72520,725
ComEd (northern Illinois)8855,17610,78910,86610,870
PPL (Pennsylvania)1894,9966,2826,2816,283
Allegheny Power (Pa., W.Va., Md.)1651,2132,6262,6242,776
PSE&G (New Jersey)3081,4462,6022,6772,709
AES Ohio (Dayton)09542,2422,2412,243
FirstEnergy (Ohio, western Pa.)1321,1292,1692,2102,210
PECO (Philadelphia)178241,6981,6981,701
Pepco (D.C., Md.)01429461,0641,064
BGE (Baltimore)18176355354354
Jersey Central (N.J.)077245245245
Met-Ed (Pa.)075234234234
Duquesne Light (Pittsburgh)046878787

From PJM's 2026 long-term load forecast, Table B-9b. This is a grid operator's forecast, built from utilities' requests, not connected load. Zones with no adjustment are left out. PJM's table · CSV

Texas: large loads approved to connect

ERCOT, which runs most of the Texas grid, reports each month how much large-customer load it has cleared to connect and how much of that it has seen drawing power.

MonthApproved to connect, MWSeen drawing power, MWSource
October 20269,4565,115ERCOT report
September 20269,4564,132ERCOT report
August 20269,4564,316ERCOT report
July 20269,4564,370ERCOT report
June 20268,9263,966ERCOT report
May 20269,0624,145ERCOT report
April 20269,0124,006ERCOT report
March 20269,0424,008ERCOT report

From ERCOT's monthly operational overview. "Approved to connect" is ERCOT's running total of large loads with approval to energize. "Seen drawing power" is the sum of each such load's highest draw in the month, which ERCOT uses as its measure of how much is operating. Large loads include data centers, cryptocurrency mines and industrial sites. CSV

By state

StateProjects announced, all yearsStated investmentMapped sitesJobs, 2019Jobs nowChange in jobsRules and policy
Virginia8$18.5 billion41213,44024,831+84.8%23
Texas9$22.6 billion22235,96447,535+32.2%56
Oregon11345,5477,681+38.5%0
California011651,85384,174+62.3%1
Ohio1$10 billion928,43513,630+61.6%0
Washington27213,89221,552+55.1%0
Arizona4$1.9 billion6410,20310,748+5.3%7
Illinois16410,97716,887+53.8%0
New Jersey06110,51815,701+49.3%4
Iowa0603,7653,670-2.5%0
Georgia25713,40126,003+94.0%0
Pennsylvania3$6 billion4710,01013,670+36.6%1
Nevada2$254 million392,5533,244+27.1%0
New York03619,60130,042+53.3%1
Tennessee0286,0317,533+24.9%1
Colorado02713,84612,924-6.7%0
North Carolina0269,97912,109+21.3%1
Nebraska0254,1422,315-44.1%1
Missouri5$26.5 billion2410,84314,277+31.7%1
Wyoming123193532+175.6%0
Utah2$3 billion225,7457,656+33.3%1
Florida01819,57327,560+40.8%0
New Mexico0174911,038+111.4%0
Minnesota0165,3547,381+37.9%0
South Carolina0153,7144,180+12.5%0
Indiana2$14.3 billion142,6404,799+81.8%2
Maryland0143,6105,487+52.0%6
Alabama1$33.1 billion132,1063,875+84.0%0
North Dakota4$6.6 billion13521n/an/a1
Michigan1127,4709,738+30.4%0
Wisconsin3$4.7 billion128,1887,793-4.8%2
Oklahoma1$444 million111,4371,709+18.9%0
Mississippi5$47.1 billion108611,025+19.0%0
Kansas071,9612,241+14.3%0
Kentucky5$4.5 billion63,7293,499-6.2%0
Connecticut051,9964,641+132.5%0
Idaho046871,253+82.4%0
Louisiana2$50 billion42,4002,875+19.8%0
Massachusetts038,12210,101+24.4%0
Maine03611787+28.8%0
Montana13510473-7.3%1
New Hampshire031,3241,875+41.6%0
Arkansas021,6733,772+125.5%0
South Dakota02168n/an/a0
West Virginia4$16 billion21,0521,248+18.6%4
District of Columbia011,1891,982+66.7%1
Vermont01373480+28.7%0
Alaska0081n/an/a0
Delaware00375447+19.2%0
Hawaii00339514+51.6%0
Rhode Island00569641+12.7%0

Sorted by mapped sites. Announcements are official releases on our log; investment is the sum of what those releases state. Jobs are private employers in the industry the government calls computing infrastructure providers, data processing and web hosting, which is wider than data centers; "now" is 2026, quarter 1 and 2019 is that year's average. Nationally the industry had 344,059 jobs in 2019 and 488,955 now (+42.1%). "n/a" means the bureau withholds the figure. Source for jobs: Bureau of Labor Statistics, Quarterly Census of Employment and Wages · CSV

Where data centers are

1,862 buildings and sites tagged as data centers in OpenStreetMap. Darker areas have more. The map is made by volunteers: it is not complete, it shows what exists rather than what is planned, and it counts buildings, so one campus can be many dots. © OpenStreetMap contributors · CSV

Who operates the mapped sites

OperatorMapped sites
Amazon Web Services253
Digital Realty83
Google75
Microsoft68
Meta59
Quality Technology Services55
Equinix46
CyrusOne43
Flexential43
NTT25
Sites in OpenStreetMap that name an operator. Many name none, and a campus can be several buildings.

All announcements

DateStateAnnouncementKindInvestmentJobsMW
11/23/26NYAssembly Announces the Passage of Legislation Placing a One-Year Moratorium on Development of Data Centers Jun 5, 2026 Speaker Carl Heastie and Energy Committee Chair Didi Barrett today announced the Assembly has passed legislation that would pause the development of data centers in New York for oneRules and policy
11/23/26WIPSC Overhauls We Energies’ Data Center Tariff, Makes Improvements to Protect Existing CustomersRules and policy
11/23/26WIPSC Ensures Stronger Public Transparency, Customer Protections in Review of Alliant Energy's Data Center Service AgreementRules and policy
11/23/26TXPUCT Approves New ERCOT Process to Manage Electricity Requests from Data Centers, Large Power UsersRules and policy
11/23/26USWhat the new Congress needs to do now on AI data centersRules and policy
11/23/26TXData center surge powering questions of who pays electricity billsRules and policy
11/23/26LAApplied Digital · Applied Digital Press ReleasesUnder construction
11/23/26US8.13.2026 EdgeCore Digital Infrastructure Formally Pledges Commitment to Data Center CommunitiesRules and policy
11/23/26USSTACK Infrastructure Proudly Supports Governor Abbott in Advancing Responsible Data Center Growth in TexasRules and policy
11/23/26TXCyrusOne, Freestone County · CyrusOne Press ReleasesAnnounced380
11/20/26USConsumer Reports applauds Senate passage of bipartisan permitting packageRules and policy
11/19/26USCongress Should Not Equate Broadband Infrastructure With Multi-Megawatt Data Centers, Says ITIFRules and policy
11/19/26USDoes the Federal Tax Code Single Out AI for Special Treatment?Rules and policy
11/19/26MOHyperscalers’ Financing of the AI Investment BoomRules and policy
11/19/26NEGov. Pillen Shares Resolution and Recommendations from Data Center Task ForceRules and policy
11/19/26AZAttorney General Mayes Urges Cochise County to Delay Vote on Proposed SpaceX Data Center, Schedules Town Hall to Hear from ResidentsRules and policy
11/18/26TXMarisol Saenz-Zambrano: Public Comments regarding Docket #60410 - Mesquite H2 Data Center Project in Jim Hogg County (PUC docket 60410)Rules and policy
11/18/26TXJuan O Flores Norma L Flores: Public comments on Mesquite H2 Data Center project in Jim Hogg County (PUC docket 60410)Rules and policy
11/18/26UTNovember 17, 2026 Meeting RecapRules and policy
11/18/26USData Centers and Electricity Costs: Bad Assessment Leads to Bad PolicyRules and policy
11/18/26USFederal Data Centers: Congress Has an Opportunity to Improve Agencies' Acquisition and OperationsRules and policy
11/16/26TXDATA CENTER COALITION: DCC Proposed List of Issues (PUC docket 60332)Rules and policy
11/16/26USPJM Proposes New Rules to Protect Grid Reliability as Data Center Demand GrowsRules and policy
11/16/26USPJM Plan Would Cut Interconnection Process Time in HalfRules and policy
11/16/26USAMD, Oak Ridge · AMD's investor-relations press releasesOpened
11/13/26TNCity of Memphis Directs $3.26 Million in Data Center Revenue Back to South Memphis NeighborhoodsRules and policy
11/13/26USISO-NE files proposal with FERC to address ‘large loads’Rules and policy
11/13/26USEPIC Joins Group Urging New Jersey Court to Reject Data Center Developer’s First Amendment ClaimRules and policy
11/12/26USFEDS Paper: Artificial Intelligence and the U.S. Economy: Current EvidenceRules and policy
11/11/26DCEspionage, AI, and the Risks of Strategic OverreactionRules and policy
11/10/26WVGovernor Morrisey Names Chris Morris to Lead Advisory Council on Responsible Digital Manufacturing DevelopmentRules and policy
11/09/26TXDATA CENTER COALITION: Motion to Intervene of the Data Center Coalition (PUC docket 60332)Rules and policy
11/09/26AZArizona Corporation Commission: Document Filed in docket E-00000A-25-0069. In the Matter of the Commission’s Inquiry and Review of the Existing Rate Classifications and other Potential Issues relating to Data Centers.Rules and policy
11/05/26AZArizona Corporation Commission: Document Filed in docket E-00000A-25-0069. In the Matter of the Commission’s Inquiry and Review of the Existing Rate Classifications and other Potential Issues relating to Data Centers.Rules and policy
11/05/26USConsumer Reports urges Congress to advance key ratepayer safeguards in bipartisan permitting packageRules and policy
11/05/26TXTexas Data Center Site Selection: Why Operators Choose TexasRules and policy
11/04/26TXERCOT: ERCOT UPDATES: BATCH ZERO VERIFICATION AND AUDIT PROCESS, DATA CENTER STATE AND COMMUNITY IMPACT RFI, AND MEDIUM LOAD RFI (PUC docket 59142)Rules and policy
11/04/26KYTeraWulf, Hawesville · TeraWulf Press ReleasesUnder construction
11/04/26ALLambda, Lowndes County · Lambda BlogAnnounced$33.1 billion225
11/03/26AZArizona Corporation Commission: Document Filed in docket E-00000A-25-0069. In the Matter of the Commission’s Inquiry and Review of the Existing Rate Classifications and other Potential Issues relating to Data Centers.Rules and policy
11/02/26AZArizona Corporation Commission: Document Filed in docket E-00000A-25-0069. In the Matter of the Commission’s Inquiry and Review of the Existing Rate Classifications and other Potential Issues relating to Data Centers.Rules and policy
11/02/26USIntroducing the Grid Protectors ProgramRules and policy
10/30/26INGovernor Braun Directs IURC to Speed Up Utility Rate Reduction Approvals for HoosiersRules and policy
10/29/26USOn Facebook and Instagram, Political Ads Are Increasingly Critical of Data CentersRules and policy
10/28/26USEstablish a Common Framework for Evaluating Data-Center ProjectsRules and policy
10/27/26TXSKYBOX DATACENTERS, LLC: HSPM Exhibit to Complaint of Skybox Data Centers LLC Regarding ERCOTS Reclassification of BZ-465 from Base Load (PUC docket 60431)Rules and policy
10/27/26AZArizona Corporation Commission: Document Filed in docket E-00000A-25-0069. In the Matter of the Commission’s Inquiry and Review of the Existing Rate Classifications and other Potential Issues relating to Data Centers.Rules and policy
10/26/26TXSKYBOX DATACENTERS, LLC: REDACTED HSPM Exhibits to Complaint of Skybox Data Centers LLC Regarding ERCOTS Reclassification of BZ-465 from Base Load (PUC docket 60431)Rules and policy
10/26/26TXSKYBOX DATACENTERS, LLC: CONFIDENTIAL - Complaint of Skybox Data Centers LLC Regarding ERCOTS Reclassification of BZ-465 from Base Load (PUC docket 60431)Rules and policy
10/26/26TXSKYBOX DATACENTERS, LLC: Revised Confidential Filing Memorandum to the Complaint of Skybox Data Centers LLC (PUC docket 60431)Rules and policy
Showing 1–50 of 237 announcements
Next 50

How we count

  • Construction spending is the Census Bureau's monthly estimate of the value of private building work on data centers, at a seasonally adjusted annual rate. The map shows what volunteers have recorded in OpenStreetMap. Job counts are for a wider industry. Grid operators' figures are their own forecasts and approvals. None of these measures the same thing, and none is a count of projects.
  • In the announcement log, each row is one press release, from a governor, a state economic development agency, an attorney general, a federal office or a data center company's own newsroom, that is about a data center project or about rules, taxes or plans for data centers. We read the release and record what it says.
  • Investment, jobs and power are the figures the release states, in its own words on each announcement's page. They are what a company or office announced, not what was built, and nothing here is independently verified.
  • The log lists announcements. When two offices announce the same project within days of each other, both are listed but counts and totals take it once. A project announced and later expanded, or announced again months on, is counted each time. Projects that were never announced by an office or company we follow are not here.
  • We follow the press pages of most governors and state economic development agencies and of about three dozen companies that build or run data centers. For 2026 we have read back through the archives of the offices whose archives can be read by a program; offices that block such reading, or keep no archive, are covered only from November 2026.
Full methodology