The Public Service Commission of Wisconsin modified Alliant Energy's Electric Service Agreement for a Beaver Dam data center at its May 7, 2026 open meeting.
- Alliant Energy submitted the application in April 2025 under its Individual Contract Rate Tariff, which the commission said has been in place since 2000.
- The commission ordered Alliant to file a stand-alone large load tariff for future data center customers.
- The commission said it required the data center customer to contribute to the statewide energy efficiency and renewable energy program.
- The case is Docket 6680-TE-115, and the commission said its Final Order will be posted in the coming weeks.
The Public Service Commission of Wisconsin modified Alliant Energy's Electric Service Agreement for a data center in Beaver Dam on May 7, 2026, according to a notice from the commission.
Alliant submitted the application in April 2025. The commission said its decision protects existing customers. It said it strengthened the proposed termination charge, which applies if the data center customer leaves, and ordered added reporting requirements and financial safeguards.
The commission also said it required the data center customer to contribute to the statewide energy efficiency and renewable energy program. It approved Renewable Energy Procurement Agreements for the customer.
The commission ordered Alliant to file a stand-alone large load tariff, a set of rates and terms for very big electricity users, that future data center customers would have to take service under.
The commission said the case is Docket 6680-TE-115. It said the notice gives an overview of a preliminary decision made verbally at the meeting, and that its Final Order will be posted in the coming weeks.