Applied Digital, Harwood
Applied Digital Press Releases · Nov 24, 2026 · Updated Nov 24, 2026, 08:07 ETWhat the release says
Project · Reskill Report summary
Applied Digital said it finished base-build commissioning of the first 75 MW of a 150 MW building at Polaris Forge 2 in Harwood, North Dakota. The company said the first 25 MW data hall is Ready for Service for a hyperscaler customer, on schedule. It said the remaining 50 MW can now move to fit-out.
From the release: “Within this phase, the Company has completed the integrated fit-out of the first 25 MW data hall and achieved Ready for Service on schedule.”
Release headline: Applied Digital Achieves Initial 25 MW Ready for Service in Harwood, North Dakota, for Hyperscaler, Completes Base-Build Commissioning of First 75 MW
This is the issuer's own account. Figures are what it announced, not what has been built, and nothing here is independently verified.
What has been announced since
| Date | Release | From |
|---|---|---|
| Oct 7, 2026 | Applied Digital Reports Fiscal First Quarter 2027 Results | Applied Digital Press Releases |
| Oct 2, 2026 | Applied Digital Brings an Additional 75 MW of AI Infrastructure Online at Polaris Forge 1 · on this tracker | Applied Digital Press Releases |
| Jul 27, 2026 | Applied Digital Reports Fiscal Fourth Quarter and Full Year 2026 Results | Applied Digital Press Releases |
| Jul 1, 2026 | Applied Digital Delivers Second Building at Polaris Forge 1 · on this tracker | Applied Digital Press Releases |
| Jun 9, 2026 | Applied Digital Announces Pricing of $1.59 Billion of Senior Secured Notes to fund the Fourth Building at Polaris Forge 1 · on this tracker | Applied Digital Press Releases |
| Mar 19, 2025 | Armstrong inspects Applied Digital expansion, housing project in Ellendale, signs backup power supply bill · on this tracker | the office of the governor of North Dakota |
These are other releases that name Applied Digital and Harwood, or are announcements about Applied Digital in North Dakota on this tracker. We follow press releases from governors, state agencies, attorneys general and the companies' own newsrooms. Permits, local decisions and construction progress are not covered unless one of those reports them, so the absence of an update here does not mean nothing has happened.
Source
- The summary is ours, written from the release linked above and checked against it. The quoted passage and each stated figure are copied from the release.
- A project can appear in more than one announcement on this tracker.