QTS Data Centers, Eagle Mountain
QTS Data Centers News · Apr 17, 2026 · Updated Nov 23, 2026, 13:58 ETWhat the release says
Project · Reskill Report summary
QTS Data Centers and contractor Layton Construction said they topped out the third building at QTS's SLC1 data center campus in Eagle Mountain, Utah. The companies said work began in September 2025 and the campus will have more than 2,000 construction jobs and more than 100 permanent roles.
From the release: “Layton Construction and QTS Data Centers (QTS) reached a major construction milestone with the topping out of the third building at the QTS data center campus in Eagle Mountain, Utah (SLC1).”
Release headline: Layton Construction and QTS Data Centers Celebrate Topping Out of Data Center Campus in Eagle Mountain
This is the issuer's own account. Figures are what it announced, not what has been built, and nothing here is independently verified.
What has been announced since
| Date | Release | From |
|---|---|---|
| Jul 23, 2026 | QTS Statement on Responsible Data Center Growth and Ratepayer Protection | QTS Data Centers News |
These are other releases that name QTS Data Centers and Eagle Mountain, or are announcements about QTS Data Centers in Utah on this tracker. We follow press releases from governors, state agencies, attorneys general and the companies' own newsrooms. Permits, local decisions and construction progress are not covered unless one of those reports them, so the absence of an update here does not mean nothing has happened.
Source
- The summary is ours, written from the release linked above and checked against it. The quoted passage and each stated figure are copied from the release.
- A project can appear in more than one announcement on this tracker.