Rappahannock Electric: Rappahannock Electric Cooperative, Hyperscale Energy Services, LLC, et al. - Public Version - Staff Report - Prepared by: Carol B. Myers - Division of Utility Accounting and Finance. (case PUR-2025-00178)
filings at the Virginia State Corporation Commission · Oct 31, 2025 · Updated Nov 23, 2026, 21:25 ETWhat the release says
Rules and policy · Reskill Report summary
Virginia State Corporation Commission staff recommended denying a request by Rappahannock Electric Cooperative and its Hyperscale Energy affiliates. The request would let the cooperative guarantee or fund collateral that PJM requires for a large load customer. Staff said the applicants had not shown this was in the public interest.
From the release: “Staff believes that burdening the Cooperative’s general body of members, primarily composed of residential consumers, with the responsibility of providing cash collateral to support a large load customer is unreasonable and unnecessarily risky.”
This is the issuer's own account. Figures are what it announced, not what has been built, and nothing here is independently verified.
Source
- The summary is ours, written from the release linked above and checked against it. The quoted passage and each stated figure are copied from the release.