Rappahannock Electric: Rappahannock Electric Cooperative, Hyperscale Energy Services, LLC and Hyperscale Energy [y], LLC - Public Version - Action Brief - 10/23/2026 (case PUR-2026-00119)

filings at the Virginia State Corporation Commission · Oct 23, 2026 · Updated Nov 23, 2026, 17:38 ET

What the release says

Rules and policy · Reskill Report summary

Virginia State Corporation Commission staff filed an action brief on Rappahannock Electric Cooperative's request to approve an affiliate agreement for a retail power model serving large-load customers. Staff said it recommends denying the application without prejudice because of uncertainty over the cooperative's tax-exempt status. It offered conditions in case the Commission approves.

From the release: “Staff recommends that the Commission deny the Application without prejudice at this time.”

Release headline: Rappahannock Electric: Rappahannock Electric Cooperative, Hyperscale Energy Services, LLC and Hyperscale Energy [y], LLC - Public Version - Action Brief - 10/23/2026 (case PUR-2026-00119)

This is the issuer's own account. Figures are what it announced, not what has been built, and nothing here is independently verified.