Virginia Electric and Power Co: VA Electric & Power Company - Exhibit 27 – Telos Data Center Flexibility Study. (case PUR-2025-00037)

filings at the Virginia State Corporation Commission · Sep 25, 2025 · Updated Nov 23, 2026, 21:25 ET

What the release says

Rules and policy · Reskill Report summary

A fact sheet from Telos Energy and GridLab was filed as Exhibit 27 by the Community Interveners in Virginia State Corporation Commission case PUR-2025-00037. Its authors say utility plans should count data center flexibility, and their NV Energy case study found it could cut new capacity needs.

From the release: “For example, 1 GW of data center flexibility was able to defer 600-850 MW of new firm capacity needs.”

Release headline: Virginia Electric and Power Co: VA Electric & Power Company - Exhibit 27 – Telos Data Center Flexibility Study. (case PUR-2025-00037)

This is the issuer's own account. Figures are what it announced, not what has been built, and nothing here is independently verified.