SB1000: Certificates of Public Convenience and Necessity and Construction of Data Centers
Maryland · 2026 Regular Session · Bill · Updated Nov 22, 2026, 21:55 ETWhat it does
Regulates · Reskill Report summary
Would bar anyone from building a data center in a Baltimore City development district that is repaying tax increment bonds. The one exception is the city-wide affordable housing development district. The bill would also widen state approval rules for high-voltage power lines to cover all transmission lines, not just overhead ones. It would require the Public Service Commission to write specific criteria for waiving the approval requirement.
From the bill: “A PERSON MAY NOT CONSTRUCT A DATA CENTER IN A DEVELOPMENT DISTRICT THAT IS SUBJECT TO TAX INCREMENT REPAYMENT ON OUTSTANDING BONDS.”
The legislature's summary
Expanding the application of certain requirements for the construction of certain overhead transmission lines to include certain other transmission lines; requiring the Public Service Commission to adopt regulations to establish specific criteria for making the determination to waive, for good cause, the requirement to obtain a certificate of public convenience and necessity in certain circumstances; prohibiting the construction of a data center in certain development districts in Baltimore City; etc.
Topics: Data centers, Studies and task forces
Sponsors: William Ferguson (D).
History
| Date | Chamber | Action |
|---|---|---|
| Feb 23, 2026 | Senate | First Reading Senate Rules |
Source
- The "What it does" summary and its label are ours, written from the bill's latest text and checked against it. The quoted clause is copied from that text.
- This bill is tracked because its title or summary uses the term "Data Centers".
- Status, sponsors and history are from LegiScan's record of this bill, used under the Creative Commons Attribution 4.0 license. The legislature's own record is linked at the top of this page.