HF2928: Preapplication filings for large water appropriation projects required, permit application information for large water appropriation projects added, level of environmental review for data centers specified, data centers exempted from making financial contributions to an energy conservation and optimization plan, and other data center provisions modified.
Minnesota · 2025-2026 Regular Session · Bill · Updated Nov 23, 2026, 21:34 ETWhat it does
Regulates · Reskill Report summary
Would require an environmental impact statement for new data centers, or expansions of 100 megawatts or more, and require large data centers to use carbon-free energy: 65 percent before December 31, 2030, and 100 percent after. It would add reporting on energy, water and metals, require prevailing wages for construction, and impose a per-megawatt fee. Data centers that break the rules would lose state financial incentives.
From the bill: “A data center must, prior to December 31, 2030, arrange to generate or procure carbon-free energy equal to at least 65 percent of its electricity consumption, measured on an hourly basis.”
Topics: Data centers, Energy and utilities
Sponsors: Patty Acomb (D), Kristi Pursell (D), Katie Jones (D).
History
| Date | Chamber | Action |
|---|---|---|
| Apr 9, 2026 | House | Author added Jones |
| Feb 17, 2026 | House | Author added Pursell |
| Mar 27, 2025 | House | Introduction and first reading, referred to Energy Finance and Policy |
Source
- The "What it does" summary and its label are ours, written from the bill's latest text and checked against it. The quoted clause is copied from that text.
- This bill is tracked because its title or summary uses the term "data centers".