A5294: "Responsible Data Center Development and Resource Protection Act"; establishes Statewide framework concerning siting, land use approval, energy sourcing, water use, and environmental impacts of large load data center development.
New Jersey · 2026-2027 Regular Session · Bill · Updated Nov 22, 2026, 21:45 ETWhat it does
Regulates · Reskill Report summary
Would require developers of large data centers (25 megawatts or more) to get State approval of a resource impact statement before a town can approve their site plan. It would require water diversion permits above 100,000 gallons per day, public reporting of power and water use, and a ban on charging utility customers for data center infrastructure costs. A voluntary certification program would offer faster reviews. If the State does not act within 60 days, the statement is deemed approved.
From the bill: “A planning board shall not grant preliminary site plan approval of a site plan for the development of a large load data center unless the State Planning Commission has granted approval of the data center resource impact statement”
Topics: Data centers, Energy and utilities
Sponsors: William Moen (D), Eliana Marin (D), Balvir Singh (D), William Sampson (D).
History
| Date | Chamber | Action |
|---|---|---|
| Jun 18, 2026 | Assembly | Introduced, Referred to Assembly Science, Innovation and Technology Committee |
Source
- The "What it does" summary and its label are ours, written from the bill's latest text and checked against it. The quoted clause is copied from that text.
- This bill is tracked because its title or summary uses the term "Data Center".
- Status, sponsors and history are from LegiScan's record of this bill, used under the Creative Commons Attribution 4.0 license. The legislature's own record is linked at the top of this page.