HB1834: Providing for the regulation of commercial data centers; imposing duties on the Pennsylvania Public Utility Commission, the Department of Human Services and the Pennsylvania Energy Development Authority; establishing the Data Center Low-Income Home Energy Assistance Program Enhancement Account and the Pennsylvania Energy Independence Account; providing for clean firm energy requirements, contract filing, commission review, disclosure requirements, backup generation standards, curtailment standar
Pennsylvania · 2025-2026 Regular Session · Bill · Updated Nov 22, 2026, 21:52 ETWhat it does
Regulates · Reskill Report summary
Would set rules for commercial data centers, meaning facilities drawing 25 megawatts or more. Data centers would pay their own grid costs, make yearly payments per megawatt to fund home energy aid and a clean energy account, and buy rising shares of new clean firm power starting at 10% in 2027, or pay a fee instead. Electric companies would have to file their data center contracts with the state utility commission for review.
From the bill: “AN ELECTRIC DISTRIBUTION COMPANY MAY NOT RECOVER FROM RATEPAYERS OTHER THAN COMMERCIAL DATA CENTERS, WHETHER THROUGH BASE RATES, RIDERS, SURCHARGES OR ANOTHER RATEMAKING MECHANISM, A COST CAUSED IN WHOLE OR IN PART BY THE INTERCONNECTION, SERVICE OR LOAD OF A COMMERCIAL DA”
The legislature's summary
An Act providing for the regulation of commercial data centers; imposing duties on the Pennsylvania Public Utility Commission, the Department of Human Services and the Pennsylvania Energy Development Authority; establishing the Data Center Low-Income Home Energy Assistance Program Enhancement Account and the Pennsylvania Energy Independence Account; providing for clean firm energy requirements, contract filing, commission review, disclosure requirements, backup generation standards, curtailment standards and certification and expedited interconnection for commercial data centers bringing incremental clean firm energy resources; and imposing penalties.
Topics: Data centers, Studies and task forces, Energy and utilities
Sponsors: Robert Matzie (D), John Inglis (D), Daniel Deasy (D), Ed Neilson (D), Kyle Mullins (D), James Haddock (D), Kyle Donahue (D), Tarah Probst (D), Carol Hill-Evans (D), Jose Giral (D), Ben Sanchez (D), Gina Curry (D), Dan Williams (D), Nathan Davidson (D), Kristine Howard (D), Dan Frankel (D), Steven Malagari (D), Lisa Borowski (D), Heather Boyd (D), James Prokopiak (D), Gregory Scott (D), Brandon Markosek (D), Mandy Steele (D), Ismail Smith-Wade-El (D), Joseph Ciresi (D), Robert Freeman (D), Paul Friel (D), Joseph Webster (D), Jeanne McNeill (D), Benjamin Waxman (D), Paul Takac (D), Jennifer O'Mara (D), Tarik Khan (D), Rick Krajewski (D), Nancy Guenst (D), Liz Hanbidge (D), Sean Dougherty (D), Nikki Rivera (D), Roni Green (D), Timothy Brennan (D), Malcolm Kenyatta (D), Tina Davis (D), Stephen Samuelson (D), Abigail Salisbury (D), Christopher Pielli (D).
History
| Date | Chamber | Action |
|---|---|---|
| Mar 31, 2026 | Senate | Referred to Consumer Protection & Professional Licensure |
| Mar 24, 2026 | Senate | In the Senate |
| Mar 24, 2026 | House | Third consideration and final passage (104-95) |
| Mar 24, 2026 | House | Re-reported as committed |
| Mar 23, 2026 | House | Re-committed to Appropriations |
| Mar 23, 2026 | House | Second consideration, with amendments |
| Feb 4, 2026 | House | Removed from table |
| Feb 2, 2026 | House | Laid on the table |
| Feb 2, 2026 | House | First consideration |
| Feb 2, 2026 | House | Reported as amended |
| Sep 4, 2025 | House | Referred to Energy |
Source
- The "What it does" summary and its label are ours, written from the bill's latest text and checked against it. The quoted clause is copied from that text.
- This bill is tracked because its title or summary uses the term "data centers".
- Status, sponsors and history are from LegiScan's record of this bill, used under the Creative Commons Attribution 4.0 license. The legislature's own record is linked at the top of this page.