SB1297: In Computer Data Center Equipment Incentive Program, further providing for application for certification and for separation of facilities, providing for additional eligibility requirements, further providing for notification, for revocation of certification, for application for certification and for separation of facilities, providing for additional eligibility requirements and further providing for notification and records and for revocation of certification.
Pennsylvania · 2025-2026 Regular Session · Bill · Updated Nov 22, 2026, 21:50 ETWhat it does
Regulates · Reskill Report summary
Starting January 1, 2030, data centers in Pennsylvania's equipment tax incentive program would have to buy 100% of their yearly electricity from Tier I alternative energy sources. They would also have to show enough investment in environmental and energy-efficiency measures, such as holding ISO 14001 certification plus two or more listed green building standards. Owners would sign an affirmation of compliance, and the Department of Revenue could revoke certification if the requirements are not met.
From the bill: “The computer data center shall purchase 100% of the computer data center's annual electric load from a Tier I alternative energy source”
The legislature's summary
An Act amending the act of March 4, 1971 (P.L.6, No.2), known as the Tax Reform Code of 1971, in Computer Data Center Equipment Incentive Program, further providing for application for certification and for separation of facilities, providing for additional eligibility requirements, further providing for notification, for revocation of certification, for application for certification and for separation of facilities, providing for additional eligibility requirements and further providing for notification and records and for revocation of certification.
Topics: Data centers, Taxes and incentives
Sponsors: Timothy Kearney (D), Maria Collett (D), Wayne Fontana (D), Jay Costa (D), Amanda Cappelletti (D), Judy Schwank (D), Sharif Street (D).
History
| Date | Chamber | Action |
|---|---|---|
| Apr 23, 2026 | Senate | Referred to Finance |
Source
- The "What it does" summary and its label are ours, written from the bill's latest text and checked against it. The quoted clause is copied from that text.
- This bill is tracked because its title or summary uses the term "Data Center".
- Status, sponsors and history are from LegiScan's record of this bill, used under the Creative Commons Attribution 4.0 license. The legislature's own record is linked at the top of this page.