H5215: Data Center Utility Costs
South Carolina · 2025-2026 Regular Session · Bill · Updated Nov 22, 2026, 21:55 ETWhat it does
Regulates · Reskill Report summary
Would bar electric utilities from passing the extra costs of serving very large power users, such as data centers, onto other customer classes. Customers with projected peak demand of at least 50MW would need a state-approved contract, a minimum service period of no less than twenty years, and financial security. They would file annual energy and water reports, hold public hearings before permits or incentives, and repay incentives if they miss conditions.
From the bill: “An electrical utility shall not recover any incremental costs incurred to serve a large load customer from customers in another customer class.”
The legislature's summary
Amend The South Carolina Code Of Laws So As To Enact The "south Carolina Ratepayer Protection And Large Load Customer Infrastructure Accountability Act" By Adding Chapter 44 To Title 58 So As To Provide Definitions, Prohibit Incremental Costs Resulting From Large Load Customers To Be Recovered From Customers In Another Customer Class; To Establish Contract Requirements Between Large Load Customers And Electrical Utilities; To Establish Review Standards For The Public Service Commission; And To Require Annual Reports From Large Load Customers; By Adding Section 13-1-80 So As To Establish Requirements Regarding Incentives That May Be Offered To Potential Large Load Customers; By Adding Section 6-29-550 So As To Establish Requirements Regarding Public Notice, Public Hearings, And Local Governmental Certifications Concerning Planning And Zoning Prior To The Receipt Of Certain Permits Or Incentives; And By Adding Section 49-1-100 So As To Require Potential Large Load Customers To Provide Plans Regarding Water Resources And Annual Reporting Requirements To The Department Of Environmental Services, And To Require The Department Of Environmental Services To Verify Water Usage Contingency Plan Adherence In The Event Of A Drought.
Topics: Government use, Data centers, Studies and task forces, Energy and utilities, Taxes and incentives
Sponsors: Wendell Jones (D).
History
| Date | Chamber | Action |
|---|---|---|
| Feb 24, 2026 | Scrivener's error corrected | |
| Feb 19, 2026 | House | Referred to Committee on Labor, Commerce and Industry |
| Feb 19, 2026 | House | Introduced and read first time |
Source
- The "What it does" summary and its label are ours, written from the bill's latest text and checked against it. The quoted clause is copied from that text.
- This bill is tracked because its title or summary uses the term "Data Center".
- Status, sponsors and history are from LegiScan's record of this bill, used under the Creative Commons Attribution 4.0 license. The legislature's own record is linked at the top of this page.