U.S. Congress · 2025-2026 Regular Session · Bill · Updated Nov 22, 2026, 21:38 ETWhat it does
Regulates · Reskill Report summary
Would require the Bureau of Land Management to treat any permit or lease for a hyperscale data center on public lands as a major federal action needing a full environmental impact statement. It would require a public comment period of at least 45 days and a public hearing, and analysis of water and energy use. Categorical exclusions could not be used. Applicants for rights-of-way would have to submit workforce plans covering job numbers and wages.
From the bill: “The Director of the Bureau of Land Management may not apply a categorical exclusion with respect to”
The legislature's summary
To clarify the requirements for authorizing the use, occupancy, and development of public lands for hyperscale data centers, and for other purposes.
Topics: Data centers
Sponsors: Dina Titus (D), Val Hoyle (D), Raul Ruiz (D), Jared Huffman (D).
History
| Date | Chamber | Action |
|---|---|---|
| Sep 16, 2026 | House | Referred to the Committee on Natural Resources, and in addition to the Committee on Agriculture, for a period to be subsequently determined by the Speaker, in each case for consideration of such provisions as fall within the jurisdiction of the committee concerned. |
| Sep 16, 2026 | House | Introduced in House |
Source
- The "What it does" summary and its label are ours, written from the bill's latest text and checked against it. The quoted clause is copied from that text.
- This bill is tracked because its title or summary uses the term "data centers".
- Status, sponsors and history are from LegiScan's record of this bill, used under the Creative Commons Attribution 4.0 license. The legislature's own record is linked at the top of this page.