Florida PSC denies Duke Energy Florida's large load tariff for customers of 50 MW or more

The commission ordered the utility to file new provisions covering all large load customers under state law, plus a rate schedule with adequate cost support.

By Reskill Report staffPublished

Key facts

The Florida Public Service Commission denied Duke Energy Florida's large load tariff petition on November 16, 2026, in docket 20260064-EI.

  • The commission found the petition and associated tariffs did not comply with Section 366.043, Florida Statutes.
  • The proposal covered customers of 50 megawatts or more, and those terms are proposed, not approved.
  • The commission ordered Duke to file tariff provisions for all statutory large load customers and a large load rate schedule with adequate cost support.

The Florida Public Service Commission denied Duke Energy Florida's large load tariff on November 16, 2026, according to docket 20260064-EI. The commission found the petition and its tariffs did not comply with Section 366.043, Florida Statutes.

Duke had asked the commission to approve a Large Load Customer Policy, a Large Load Customer Agreement and revised contribution in aid of construction tariffs. They would apply to customers of 50 megawatts or more. A megawatt measures how much power a customer can draw at one moment.

The commission ordered Duke to file tariff provisions covering all statutory large load customers. It also ordered a large load rate schedule with adequate cost support. The 50-megawatt threshold remains a proposed term, not an approved one.

Reskill Report's tracker lists 8 cases in Florida, among 124 cases across 40 states.

Sources and method