Reskill ReportTracking AI's effect on jobs, power and the law

Data Center Tracker

How fast data centers are being built in the United States, where they are, what grid operators expect, and what officials are announcing: federal construction figures, a map, and a log of project and policy announcements.

Last updated Nov 23, 2026, 21:06 ET
Data center construction, annual rate, September 2026$96.5 billion
A year earlier$50.7 billion
Change in a year+90.3%
Five years earlier$10.8 billion

Spending on data center construction

$24B$48B$72B$96B2014201620182020202220242026
Private construction spending on data centers, seasonally adjusted annual rate, January 2014 to September 2026 (latest month preliminary). It counts the value of building work put in place each month, not the computers that go inside. Source: U.S. Census Bureau, Construction Spending · CSV

Figures to cite

Project announcements in 2026Official releases on our log47
Investment those releases state23 of them give a figure$225.2 billion
Power those releases state22 of them give a figure19,684 MW
PJM's forecast of large new loads in 2030PJM 2026 load forecast38,815 MW
Large loads approved to connect in TexasERCOT, October 20269,456 MW
Jobs in data processing and hostingBLS; 2019: 344,059488,955
Data center buildings mappedOpenStreetMap1,862
Each figure is explained, with its source, in the section it links to.

Largest projects announced in 2026

ProjectStateAnnouncedStatusInvestmentMWJobs
Meta, Richland ParishLA07/13/26Expansion$50 billion5,0001,000
Lambda, Lowndes CountyAL11/04/26Announced$33.1 billion225
xAI, SouthavenMS01/08/26Under construction$20 billion
Google, Montgomery CountyMO05/20/26Announced$15 billion
Starwood Digital Ventures, Mason CountyWV09/03/26Approved$12 billion2,160
Amazon, Madison CountyMS04/09/26Expansion$11 billion700
Meta, El PasoTX10/15/26Announced$10 billion1,000300
QTS Data Centers, Hall CountyTX07/13/26Announced$10 billion350
Amazon, Montgomery CityMO06/15/26Announced$10 billion400
QTS Data Centers, Van WertOH05/29/26Announced$10 billion200
Meta, LebanonIN02/11/26Under construction$10 billion300
CoreWeave, LancasterPA10/22/26Announced$6 billion30075
Microsoft, Village of Mount PleasantWI06/23/26Opened$4.7 billion550
TeraWulf, Hancock CountyKY08/24/26Approved$4.5 billion482
Sabey Data Centers, Decatur TownshipIN08/27/26Announced$4.3 billion75

Ranked by the investment each official release states, then by stated power. These are announced figures, not what has been built, and a blank means the release gave none. Projects no followed office announced are not here. All 47 project announcements in 2026

Grid forecast: Mid-Atlantic and Midwest

PJM, which runs the grid from New Jersey to Illinois, forecasts how much power large new customers will need in each utility's zone. It says most of that is data centers. Figures are megawatts added to the summer peak.

Zone20262030203520402045
All of PJM11,47938,81568,97782,65686,511
Dominion (Virginia, N.C.)7,06613,89622,42631,35035,010
AEP (Ohio, Ind., Va., W.Va. and others)2,6998,66516,27620,72520,725
ComEd (northern Illinois)8855,17610,78910,86610,870
PPL (Pennsylvania)1894,9966,2826,2816,283
Allegheny Power (Pa., W.Va., Md.)1651,2132,6262,6242,776
PSE&G (New Jersey)3081,4462,6022,6772,709
AES Ohio (Dayton)09542,2422,2412,243
FirstEnergy (Ohio, western Pa.)1321,1292,1692,2102,210
PECO (Philadelphia)178241,6981,6981,701
Pepco (D.C., Md.)01429461,0641,064
BGE (Baltimore)18176355354354
Jersey Central (N.J.)077245245245
Met-Ed (Pa.)075234234234
Duquesne Light (Pittsburgh)046878787

From PJM's 2026 long-term load forecast, Table B-9b. This is a grid operator's forecast, built from utilities' requests, not connected load. Zones with no adjustment are left out. PJM's table · CSV

Texas: large loads approved to connect

ERCOT, which runs most of the Texas grid, reports each month how much large-customer load it has cleared to connect and how much of that it has seen drawing power.

MonthApproved to connect, MWSeen drawing power, MWSource
October 20269,4565,115ERCOT report
September 20269,4564,132ERCOT report
August 20269,4564,316ERCOT report
July 20269,4564,370ERCOT report
June 20268,9263,966ERCOT report
May 20269,0624,145ERCOT report
April 20269,0124,006ERCOT report
March 20269,0424,008ERCOT report

From ERCOT's monthly operational overview. "Approved to connect" is ERCOT's running total of large loads with approval to energize. "Seen drawing power" is the sum of each such load's highest draw in the month, which ERCOT uses as its measure of how much is operating. Large loads include data centers, cryptocurrency mines and industrial sites. CSV

By state

StateProjects announced, all yearsStated investmentMapped sitesJobs, 2019Jobs nowChange in jobsRules and policy
Virginia8$18.5 billion41213,44024,831+84.8%29
Texas9$22.6 billion22235,96447,535+32.2%62
Oregon11345,5477,681+38.5%0
California011651,85384,174+62.3%1
Ohio1$10 billion928,43513,630+61.6%0
Washington27213,89221,552+55.1%0
Arizona4$1.9 billion6410,20310,748+5.3%7
Illinois16410,97716,887+53.8%0
New Jersey06110,51815,701+49.3%4
Iowa0603,7653,670-2.5%0
Georgia25713,40126,003+94.0%0
Pennsylvania3$6 billion4710,01013,670+36.6%1
Nevada2$254 million392,5533,244+27.1%0
New York03619,60130,042+53.3%1
Tennessee0286,0317,533+24.9%1
Colorado02713,84612,924-6.7%0
North Carolina0269,97912,109+21.3%1
Nebraska0254,1422,315-44.1%1
Missouri5$26.5 billion2410,84314,277+31.7%1
Wyoming123193532+175.6%0
Utah2$3 billion225,7457,656+33.3%1
Florida01819,57327,560+40.8%0
New Mexico0174911,038+111.4%0
Minnesota0165,3547,381+37.9%0
South Carolina0153,7144,180+12.5%0
Indiana2$14.3 billion142,6404,799+81.8%2
Maryland0143,6105,487+52.0%6
Alabama1$33.1 billion132,1063,875+84.0%0
North Dakota4$6.6 billion13521n/an/a1
Michigan1127,4709,738+30.4%0
Wisconsin3$4.7 billion128,1887,793-4.8%2
Oklahoma1$444 million111,4371,709+18.9%0
Mississippi5$47.1 billion108611,025+19.0%0
Kansas071,9612,241+14.3%0
Kentucky5$4.5 billion63,7293,499-6.2%0
Connecticut051,9964,641+132.5%0
Idaho046871,253+82.4%0
Louisiana2$50 billion42,4002,875+19.8%0
Massachusetts038,12210,101+24.4%0
Maine03611787+28.8%0
Montana13510473-7.3%1
New Hampshire031,3241,875+41.6%0
Arkansas021,6733,772+125.5%0
South Dakota02168n/an/a0
West Virginia4$16 billion21,0521,248+18.6%4
District of Columbia011,1891,982+66.7%1
Vermont01373480+28.7%0
Alaska0081n/an/a0
Delaware00375447+19.2%0
Hawaii00339514+51.6%0
Rhode Island00569641+12.7%0

Sorted by mapped sites. Announcements are official releases on our log; investment is the sum of what those releases state. Jobs are private employers in the industry the government calls computing infrastructure providers, data processing and web hosting, which is wider than data centers; "now" is 2026, quarter 1 and 2019 is that year's average. Nationally the industry had 344,059 jobs in 2019 and 488,955 now (+42.1%). "n/a" means the bureau withholds the figure. Source for jobs: Bureau of Labor Statistics, Quarterly Census of Employment and Wages · CSV

Where data centers are

1,862 buildings and sites tagged as data centers in OpenStreetMap. Darker areas have more. The map is made by volunteers: it is not complete, it shows what exists rather than what is planned, and it counts buildings, so one campus can be many dots. © OpenStreetMap contributors · CSV

Who operates the mapped sites

OperatorMapped sites
Amazon Web Services253
Digital Realty83
Google75
Microsoft68
Meta59
Quality Technology Services55
Equinix46
CyrusOne43
Flexential43
NTT25
Sites in OpenStreetMap that name an operator. Many name none, and a campus can be several buildings.

All announcements

DateStateAnnouncementKindInvestmentJobsMW
08/11/26WVGovernor Morrisey, Legislative Leaders Announce Unified Plan for Responsible Data Center Development in West VirginiaRules and policy
08/10/26USCore Scientific Supports Governor Abbott’s Focus on Responsible Data Center Infrastructure in TexasRules and policy
08/10/26USCompass Datacenters to Gov. Abbott: We Agree. Raise the Standards.Rules and policy
08/10/26VAGovernor Spanberger Discusses Intervention in NextEra-Dominion Merger, Highlights Focus on Energy Affordability & Protecting Jobs on FOX 5 DCRules and policy
08/07/26USStream Data Centers Affirms New Auditing Measures for Texas Grid, Supports Policies That Preserve Responsible, Rational GrowthRules and policy
08/06/26USQTS Applauds Texas Governor Greg Abbott’s Efforts to Support Responsible Data Center GrowthRules and policy
08/05/26VANEW: Following Governor Spanberger’s Urging, SCC Requires Data Centers to Pay for New Transmission InfrastructureRules and policy
08/03/26VAYondr Group, Manassas · Yondr Press ReleasesAnnounced72
07/29/26USThe Truth About Data Centers: What’s Really Behind Your Electricity BillRules and policy
07/27/26VARappahannock Electric: Rappahannock Electric Cooperative, Hyperscale Energy Services, LLC, and Hyperscale Energy [y], LLC - Application for Approval of Affiliate Arrangements pursuant to Chapter 4 of Title 56 of the Code of Virginia. (case PUR-2026-00119)Rules and policy
07/23/26USDuke Energy: Data center growth will deliver billions of dollars in customer savingsRules and policy
07/23/26USQTS Statement on Responsible Data Center Growth and Ratepayer ProtectionRules and policy
07/23/26USVantage Data Centers Signs Ratepayer Protection Pledge, Reinforcing Commitment to Pay Our Own WayRules and policy
07/22/26ORSabey Data Centers, Umatilla · Sabey Data Centers Press ReleasesUnder construction
07/22/26GAOpenAI, Effingham County · OpenAI NewsAnnounced3,200
07/15/26VAVirginia Electric and Power Co: Virginia Electric and Power Company - Exhibit 23 – Comparison of "But For" Data Center Projects. (case PUR-2026-00056)Rules and policy
07/14/26TXJIM SCOGGINS: Waterfront property owner on Cedar Creek Lake in Trinidad, Texas. I'm writing in strong support of the petition in Project No. 59824, which would require large data centers to disclose their water demand before connecting to the grid. (PUC docket 59824)Rules and policy
07/13/26TXRillera: I strongly support the petition in Project 59824. ECROT needs approval from the TWBD before a data center in Texas is established. A temporary infrastructure moratorium is needed in Texas counties until mandatory standards are law. Protect Texas. (PUC docket 59824)Rules and policy
07/13/26TXQTS Data Centers, Hall County · QTS Data Centers NewsAnnounced$10 billion350
07/13/26LAMeta, Richland Parish · Meta Data CentersExpansion$50 billion1,0005,000
07/09/26TXRikki Weaver: support the petition in Project No. 59824 requiring large data centers to file a Water-Reliability Impact Statement before grid connection (PUC docket 59824)Rules and policy
07/08/26TXRachel Streater: I strongly support the petition in Project No. 59824. Revealed in the June 23rd House hearing, over 80% of data centers operate in secrecy, refusing to report water metrics. Protect TX resources by requiring ERCOT to work with TWDB before approvals. (PUC docket 59824)Rules and policy
07/08/26MTGov. Gianforte Signs Ratepayer Protection Pledge to Protect Montana ConsumersRules and policy
07/07/26NJGovernor Sherrill Announces Ratepayer Relief, Signs Major Legislation on Energy, Saving New Jerseyans $1B AnnuallyRules and policy
07/06/26KYTeraWulf, Hawesville · TeraWulf Press ReleasesAnnounced401
07/06/26VANEW: Governor Spanberger Highlights First-of-Its-Kind Data Center Energy Consumption Tax in Politico InterviewRules and policy
07/01/26TXEL PASO ELECTRIC COMPANY: APPLICATION OF EL PASO ELECTRIC COMPANY FOR APPROVAL OF AN UPDATE TO ITS RATE SCHEDULES 33A AND 33B ECONOMIC DEVELOPMENT RATE RIDER FOR A NEW DATA CENTER HSPM (PUC docket 59948)Rules and policy
07/01/26TXEL PASO ELECTRIC COMAPNY: APPLICATION OF EL PASO ELECTRIC COMPANY FOR APPROVAL OF AN UPDATE TO ITS RATE SCHEDULES 33A AND 33B ECONOMIC DEVELOPMENT RATE RIDER FOR A NEW DATA CENTER (PUC docket 59948)Rules and policy
07/01/26NDApplied Digital, Ellendale · Applied Digital Press ReleasesExpansion75
06/30/26VAGovernor Spanberger Signs Legislation to Address High Energy Costs & Rejoin RGGIRules and policy
06/29/26VAGovernor Spanberger Celebrates Record Education, Healthcare, & Housing Investments in Final BudgetRules and policy
06/28/26TXHamlet Peguero: Require Water Accountability Before Approving Data Center Growth (PUC docket 59824)Rules and policy
06/26/26TXGeorgina Hidalgo: I strongly support petition Project No. 59824. As revealed in the June 23rd House hearing, 80%+ of data centers operate in total secrecy, refusing to report water metrics. The PUCT must stop letting ERCOT approve massive grid connections in isolation. (PUC docket 59824)Rules and policy
06/26/26TXCONCERNED CITIZEN: Regarding data centers be required to report all water usage (PUC docket 59824)Rules and policy
06/26/26TXJlawless: Need to regulate data centers and require water reporting to protect citizens and resources of Texas. (PUC docket 59824)Rules and policy
06/25/26TXRoger Frazier: Comments regarding water usage and data centers (PUC docket 59824)Rules and policy
06/25/26NDArmstrong statement on North Dakota legislators establishing interim committee on AI and data centersRules and policy
06/23/26WIMicrosoft, Village of Mount Pleasant · Microsoft SourceOpened$4.7 billion550
06/16/26TXData Center Coalition (DCC): Data Center Coalition's Comments Regarding PGRR 145 (PUC docket 54445)Rules and policy
06/15/26TXDataBank, Red Oak · DataBank NewsUnder construction$2.6 billion60
06/15/26MOAmazon, Montgomery City · the Missouri Department of Economic DevelopmentAnnounced$10 billion400
06/15/26MOAmazon, Montgomery City · the office of the governor of Missouri · a second announcement of the same project, not counted againAnnounced$10 billion400
06/12/26TXDATA CENTER COALITION: DCC Comments on NOGRR282 Large Computational Load Ride-Through Requirements (PUC docket 54445)Rules and policy
06/09/26NDApplied Digital, Ellendale · Applied Digital Press ReleasesAnnounced$1.6 billion150
06/01/26MIOpenAI, Saline · OpenAI NewsUnder construction4501,000
05/29/26OHQTS Data Centers, Van Wert · QTS Data Centers NewsAnnounced$10 billion200
05/27/26PAGovernor Shapiro Releases Full Governor’s Responsible Infrastructure Development (GRID) Standards to Protect Pennsylvanians and Establish Strict Guardrails to Hold Data Center Developers AccountableRules and policy
05/27/26NJGovernor Sherrill Announces Comprehensive Plan on Data CentersRules and policy
05/26/26KYTeraWulf, EastPark Industrial Park · TeraWulf Press ReleasesAnnounced1,000
05/20/26MOGoogle, Montgomery County · the Missouri Department of Economic DevelopmentAnnounced$15 billion
Showing 101–150 of 249 announcements
PreviousNext 50

How we count

  • Construction spending is the Census Bureau's monthly estimate of the value of private building work on data centers, at a seasonally adjusted annual rate. The map shows what volunteers have recorded in OpenStreetMap. Job counts are for a wider industry. Grid operators' figures are their own forecasts and approvals. None of these measures the same thing, and none is a count of projects.
  • In the announcement log, each row is one press release, from a governor, a state economic development agency, an attorney general, a federal office or a data center company's own newsroom, that is about a data center project or about rules, taxes or plans for data centers. We read the release and record what it says.
  • Investment, jobs and power are the figures the release states, in its own words on each announcement's page. They are what a company or office announced, not what was built, and nothing here is independently verified.
  • The log lists announcements. When two offices announce the same project within days of each other, both are listed but counts and totals take it once. A project announced and later expanded, or announced again months on, is counted each time. Projects that were never announced by an office or company we follow are not here.
  • We follow the press pages of most governors and state economic development agencies and of about three dozen companies that build or run data centers. For 2026 we have read back through the archives of the offices whose archives can be read by a program; offices that block such reading, or keep no archive, are covered only from November 2026.
Full methodology