Alabama PSC sets process for reviewing Alabama Power contracts with large data center customers
Alabama Public Service Commission · No. 33709 · Updated Nov 23, 2026, 18:37 ETWhat the case is
Reskill Report summary · the commission lists the case as decided
The Alabama Public Service Commission opened a generic proceeding on how it reviews electric service contracts between Alabama Power and large load data center customers under Act 2026-610. After 19 sets of initial comments and 10 sets of reply comments, it adopted a review process, with a vote and 90-day deemed-approval limit.
From the docket: “DOCKET 33709, Generic Proceeding to Establish a Process for”
Official title: Generic Proceeding to Establish a Process for Consideration of Contracts for Electric Service Between Alabama Power Company and Large Load Data Center Customers
What the commission decided
The Commission unanimously accepted the recommended review procedures as amended: contracts are approved or disapproved by Commission vote, deemed approved if no vote within 90 days of filing, and Alabama Power must file a compliant tariff within ten calendar days. · Oct 6, 2026
Terms for large users, as approved
| Term | What it says | The document's words |
|---|---|---|
| Counts as a large user at | 150 MW | “an expected total peak demand of 150 megawatts or greater at” Source |
| Also | Petition deemed approved if the Commission does not vote within 90 days; no hearing or intervention. | “vote; however, if the Commission fails to vote within 90 days” Source |
Who is taking part
Attorney General of Alabama; Southern Environmental Law Center; Data Center Coalition; Alabama Industrial Energy Consumers; Business Council of Alabama; Energy Alabama; Sierra Club; Southeast Energy Efficiency Alliance.
Source
- This case was compiled from the Alabama Public Service Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Commission order: “DOCKET 33709, Generic Proceeding to Establish a Process for”
- Commission order: “vote; however, if the Commission fails to vote within 90 days”
- Commission order: “Initiating a generic proceeding to develop procedures for the”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.