Reskill ReportTracking AI's effect on jobs, power and the law

Who Pays for the Power

The utility-commission cases that decide how data centers and other very large electricity users get power, what they pay, and what lands on everyone else. Each case links to its docket and its latest filings.

Last updated Nov 23, 2026, 18:37 ET
Cases on file124
States40
Large users approved to connect in Texas, October 20269,456 MW
Large new loads the PJM grid forecasts by 203038,815 MW

A megawatt is a rate of use; a large data center campus can draw several hundred. The Texas figure is ERCOT's own count of large loads it has approved to connect (source). The PJM figure is the grid operator's 2026 forecast for its 13-state region (source). More on both is on the data center tracker.

What the fights are about

Rates and terms for large usersWhat a large user pays and on what terms47
Commission rules or inquiryA commission setting rules for all utilities24
Contract with a large customerA commission reviewing one deal15
Connecting to the gridWho gets plugged in, and in what order9
General rate caseLarge-load terms argued inside a general rate case8
New plants, lines or power purchasesPlants and lines proposed to serve the new demand5
DisputeA developer or customer against a utility or grid operator4
Other12

Each case has one label, for its main subject, chosen from the docket's title and filings.

Cases by year opened

20223
20231
202410
202535
202643

32 more have no opening date on file.

Who shows up most

Google22 cases
Data Center Coalition21 cases
Sierra Club21 cases
ERCOT11 cases
Amazon Data Services10 cases
Office of Public Utility Counsel (Texas)10 cases
Texas Industrial Energy Consumers9 cases
Walmart8 cases
Oncor Electric Delivery Company7 cases
Microsoft Corporation6 cases

Named on filings, or listed as a participant, in two or more cases here. Commission staff are left out.

What each state asks of a large user

The terms a utility or commission has proposed, approved or enacted, in the document's own numbers. Each figure links to the document it comes from.

StateUtility or bodyCounts as large atMust pay for at leastMinimum contractDeposit or exit termsStanding
AlabamaAlabama Legislature150 MWIn law
AlabamaAlabama Power Company150 MWApproved
ArizonaArizona Public Service Company25 yearsRisk-based collateral (cash, surety bonds or letters of credit) covering three years of fixed capacity paymentsProposed
ArizonaArizona Public Service Company5 MWProposed
ArizonaTucson Electric Power CompanyAgreement carries termination fees and minimum billing payments protecting other TEP customersApproved
ArkansasArkansas Electric Cooperative Corporation50 MWContribution in aid of construction equal to 100 percent of the line cost and other related facilities.Approved
ArkansasArkansas Electric Cooperative Corporation50 MWProposed
ArkansasEntergy Arkansas, LLCSecurity deposit of three months of an average estimated bill, in cash, bond or letter of credit.Approved
CaliforniaPacific Gas and Electric CompanyCustomer prefunds 100 percent of Type 4 transmission network upgrade cost; repayment not guaranteed.Proposed
ColoradoPublic Service Company of Colorado (Xcel Energy)50 MW80% of contracted demand15 yearsCustomer unable to give a guaranty must post credit support of 60 times the minimum monthly bill.Proposed
ColoradoPublic Service Company of Colorado (Xcel Energy)100 MW15 yearsCommission raised required security from three months to six months of anticipated bills.Approved
DelawareDelmarva Power & Light Company25 MWProposed
FloridaDuke Energy Florida, LLC50 MWProposed
FloridaFlorida Legislature50 MWIn law
FloridaFlorida Power & Light Company50 MW70% of contracted demand20 yearsUp-front performance security equal to 100 percent of the incremental generation charge over the 20-year term.Approved
IdahoIdaho Power Company20 MWApproved
IdahoIdaho Public Utilities Commission50 MWApproval conditioned on financial security in a form and amount approved by the commission.In law
IndianaIndiana Michigan Power Company70 MW80% of contracted demand12 yearsCollateral of 24 times the maximum expected monthly non-fuel bill, with credit-rating exemptions.Approved
IndianaNorthern Indiana Public Service Company LLC and NIPSCO Generation LLC15 yearsApproved
KansasEvergy Kansas Central and Evergy Metro75 MW80% of contracted demand12 yearsCollateral equal to two years of minimum monthly bills.Approved
KentuckyEast Kentucky Power Cooperative, Inc.15 MWPrepayment deposit equal to a rolling two months of expected maximum monthly bills.Approved
KentuckyKentucky Power Company150 MW90% of contracted demand20 yearsCollateral equal to 24 times the customer's monthly bill.Approved
LouisianaEntergy Louisiana, LLCParent guaranty agreements and other collateral security, including credit insurance, must be obtained and enforced.Approved
LouisianaLouisiana Public Service Commission15 yearsApproved
MarylandMaryland Public Service Commission100 MWIn law
MichiganConsumers Energy Company100 MW80% of contracted demand15 yearsApproved
MichiganDTE Electric Company80% of contracted demand20 yearsApproved
MichiganDTE Electric Company80% of contracted demand19 yearsApproved
MichiganIndiana Michigan Power Company50 MW90% of contracted demand15 yearsApproved
MinnesotaNorthern States Power Company (Xcel Energy)100 MW80% of contracted demand15 yearsApproved
MissouriEvergy Missouri Metro and Evergy Missouri West75 MW80% of contracted demand12 yearsCollateral equal to two years of minimum monthly bills.Approved
MissouriUnion Electric Company d/b/a Ameren Missouri80% of contracted demandCollateral equal to two years of minimum monthly bills, with credit-based discounts.Approved
NebraskaNebraska Legislature (no state commission regulates Nebraska's public power utilities' retail rates)Financial commitment requirements for transmission and generation built to serve the customer.In law
NevadaNevada Power Company and Sierra Pacific Power Company (d/b/a NV Energy)25 MW72% of contracted demandProposed
New JerseyNew Jersey Board of Public Utilities50 MW85% of contracted demand10 yearsDeposits, financial security or, for highly rated customers, financial commitments, plus a class-only stranded cost mechanism.Proposed
New MexicoPublic Service Company of New Mexico10 MWApproved
North CarolinaDuke Energy Carolinas, LLC50 MW75% of contracted demand10 yearsSecurity equal to liquidated damages for early termination, in cash, letter of credit or parent guaranteeProposed
North CarolinaDuke Energy Progress, LLC50 MW75% of contracted demand10 yearsSecurity equal to liquidated damages for early termination, in cash, letter of credit or parent guaranteeProposed
North DakotaOtter Tail Power Company75 MWProposed
OhioOhio Power Company (AEP Ohio)25 MW85% of contracted demandGuarantee or collateral equal to 50% of total minimum charges for the full contract term.Approved
OklahomaOklahoma Gas and Electric Company75 MW85% of contracted demand15 yearsProposed
OklahomaPublic Service Company of Oklahoma75 MW10 yearsProposed
OregonPacifiCorp dba Pacific Power10 yearsApproved
OregonPortland General Electric Company20 MW90% of contracted demand10 yearsApproved
OregonPublic Utility Commission of Oregon20 MW10 yearsIn law
PennsylvaniaPennsylvania Public Utility Commission50 MW80% of contracted demand5 yearsCollateral must fully cover network improvement and interconnection facility costs, released as milestones are met.Approved
South CarolinaDominion Energy South Carolina, Inc.50 MWApproved
South CarolinaDuke Energy Carolinas, LLC50 MWApproved
South CarolinaDuke Energy Carolinas, LLC; Duke Energy Progress, LLC50 MWProposed
South CarolinaDuke Energy Progress, LLC50 MWApproved
South CarolinaSouth Carolina Public Service Authority (Santee Cooper)20 MW90% of contracted demandCollateral equal to 180 months of minimum bills; at least 12 months as a cash deposit.Approved
South CarolinaSouth Carolina Public Service Authority (Santee Cooper)50 MWCollateral equal to 180 months of minimum bills; at least 12 months as a cash deposit.Approved
South DakotaOtter Tail Power Company75 MWProposed
TexasEl Paso Electric Company75 MWProposed
TexasTexas Legislature75 MWIn law
UtahPublic Service Commission of Utah100 MWLarge load contract must require the customer to maintain financial security covering its obligations.In law
UtahRocky Mountain Power (PacifiCorp)100 MWApproved
VirginiaAppalachian Power Company100 MW80% of contracted demand14 yearsStipulated collateral requirements approved, but the parties may not negotiate different amounts; cash collateral earns interest.Approved
VirginiaRappahannock Electric Cooperative25 MWCollateral left to the cooperative to determine and set out in the electric service agreement.Approved
WashingtonWashington Utilities and Transportation Commission50 MWProposed
West VirginiaAppalachian Power Company and Wheeling Power Company100 MW80% of contracted demand12 yearsApproved
WisconsinWisconsin Electric Power Company (We Energies)15 yearsApproved
WyomingCheyenne Light, Fuel and Power Company (d/b/a Black Hills Energy)5 MWProposed

A blank cell means we found no such term stated in the documents we read, not that there is none. "Proposed" terms are a request and may change.

What commissions have decided

DecidedStateCaseWhat was ordered
Nov 16, 2026FloridaFlorida PSC denies Duke Energy Florida's large load tariff for customers of 50 MW or moreThe Commission denied Duke Energy Florida's petition and associated tariffs as non-compliant with Section 366.043, and ordered it to file tariff provisions covering all statutory large load customers plus a large load rate schedule with adequate cost support.
Oct 30, 2026South CarolinaSantee Cooper adopts standard High Impact Load rate for data centers and other large loadsOn Oct. 30, 2026, the Santee Cooper board approved rates including a High Impact Load Rate that transitions the 2025 Experimental Large Load Rate into a standard offering, effective for bills rendered on and after February 1, 2027.
Oct 6, 2026AlabamaAlabama PSC sets process for reviewing Alabama Power contracts with large data center customersThe Commission unanimously accepted the recommended review procedures as amended: contracts are approved or disapproved by Commission vote, deemed approved if no vote within 90 days of filing, and Alabama Power must file a compliant tariff within ten calendar days.
Oct 1, 2026TexasTexas PUC: Green Recursive petition for rule on large computational loads, deniedThe commission issued an order denying the petition for rulemaking, filed October 1, 2026.
Oct 1, 2026MichiganDTE Electric's special contracts with Google for a Wayne County data center, approved with conditionsOn October 1, 2026, the commission approved the Primary Supply Agreement and the Clean Capacity Accelerator Agreement, conditioned on protections so other DTE Electric customers bear none of the project's costs.
Aug 27, 2026MichiganMichigan approves Indiana Michigan Power's amended large load tariff for data centersThe commission approved the Tariff LP amendments and required I&M to propose a standalone large load rate, modeling six cost allocation and rate design models, in its next general rate case, plus an ex parte compliance filing before each new customer.
Aug 11, 2026IdahoIdaho Power annual update of marginal energy prices for large-load Schedules 20 and 34In Order No. 37125 the Commission acknowledged the marginal cost calculations as correctly quantified, found the Company complied with Order No. 36619, authorized keeping the current Schedule 20 and 34 marginal energy price components, and directed a separate docket to reevaluate the methodology.
Aug 5, 2026OhioPUCO orders AEP Ohio to procure separate default-service energy for data centers returning to SSOPUCO issued an order on Aug. 5, 2026 directing AEP Ohio to require 180-day notice from data centers returning to the SSO and to procure their energy through separate auctions or spot-market purchases, with the entire cost assigned to them.
Jul 2, 2026South CarolinaDominion Energy South Carolina rate case: commission approves large load (50 MW+) stipulationOrder No. 2026-374 (July 2, 2026) approved the Large Load Stipulation in its entirety, finding it just and reasonable, in the public interest, and in accordance with law and regulatory policy.
Jun 1, 2026VirginiaAppalachian Power large-load terms for Schedule L.P.S.: Virginia SCC order adopting examiner's reportOn June 1, 2026, the Commission adopted the Hearing Examiner's findings and recommendations, which approve the revisions as set out in the Partial Stipulation's Attachment 1 with changes to collateral, Exit Fee dispute resolution and Exit Fee mitigation, ordered revised tariff sheets, and dismissed the case.
May 12, 2026PennsylvaniaPennsylvania PUC adopts model tariff for customers with large loads of 50 MW or moreIn its Final Order, adopted April 30, 2026 and entered May 12, 2026, the Commission adopted the Model Tariff for customers with load at or over 50 MW individually or 100 MW in the aggregate.
May 8, 2026IdahoIdaho Power seeks approval of special contract and Schedule 28 to serve Micron's memory fabThe Commission approved the Micron Energy Service Agreement and Schedule 28 rates, directing the Company to revise Sections 5.5(b) and 7.2 on the marginal cost-based Energy Charges and Minimum Monthly Billing Demand per Micron Exhibits 304 and 305.
May 7, 2026WisconsinAlliant Energy data center service agreement in Beaver Dam; PSC modifies it, orders large load tariffThe Commission modified the Electric Service Agreement, strengthening the termination charge and adding reporting and financial safeguards, and ordered Alliant to file a stand-alone large load tariff for future data center customers.
May 7, 2026OregonOregon PUC sets PGE data center rate class (Schedule 96) under the POWER ActOrder No. 26-154 adopted Schedule 96 with modifications, ordered revisions to Schedules 89 and 90 and to Rules C and I, and adopted the first partial stipulation.
Apr 24, 2026WisconsinWe Energies' very large customer tariff for data centers: Wisconsin PSC modifies and decidesThe Commission made major modifications to the tariff, extending the minimum initial term to 15 years, lowering the eligibility threshold from 500 MW to 100 MW, and removing a capacity-only option that covered 75% of generating costs.
Apr 17, 2026AlabamaAlabama law on Public Service Commission review of large data center electric contracts (SB270)SB270 was enacted as Act No. 2026-610, adding Section 37-4-22.1 to the Code of Alabama, effective October 1, 2026.
Apr 14, 2026NebraskaNebraska law limits eminent domain over private power plants serving huge industrial customersThe Governor approved LB 1261 on April 14, 2026, enacting the ban on eminent domain by consumer-owned utilities against qualifying privately owned generation facilities serving a single large industrial customer.
Apr 14, 2026NebraskaNebraska enacts Large Load Customer Regulation Act (LB 1010) for new loads over 20 MWLB 1010, approved by the Governor April 14, 2026, adopts the Large Load Customer Regulation Act, requiring public power suppliers to set interconnection standards and a curtailment procedure for large load customers.
Apr 10, 2026UtahRocky Mountain Power large-load service contract with unnamed customer approved by Utah PSCThe PSC approved the Application, the large-load service contract and the Settlement, finding the Customer will bear all just and reasonable incremental costs, and denied UAE's motion for access to "regulator access only" materials.
Apr 10, 2026IdahoIdaho law requiring commission approval of contracts for new large electricity loads (HB 911)Idaho enacted Idaho Code 61-335 (added 2026, ch. 335), requiring commission-approved service contracts, with a no harm test and financial security, for new large loads of 50 megawatts or more.
Mar 20, 2026VirginiaVirginia SCC approves Rappahannock Electric Cooperative's large-load rate schedule LP-DFThe Commission approved Schedule LP-DF effective April 15, 2026, subject to modifications, ended the interim authority, and ordered refunds with interest where interim rates exceeded the approved rates.
Mar 11, 2026ColoradoXcel's Public Service Co. of Colorado asks for more time to file its large load tariff; approvedThe Commission granted Public Service's Verified Petition for a Variance from Ordering Paragraph 81 of Decision No. C25-0747 and acknowledged the Colorado Energy Office's notice of intervention.
Jan 22, 2026FloridaFPL rate case: large load (data center) tariffs LLCS-1 and LLCS-2 approved through 2025 settlementA later commission order states the Commission previously approved FPL's LLCS tariffs and service agreement in FPL's 2025 Settlement Agreement, issued January 22, 2026, in this docket.
Jan 15, 2026CaliforniaPG&E asks CPUC to approve transmission agreements for Microsoft's 90 MW San Jose data centerThe Commission approved, with modification, the four agreements, limiting refunds to 75 percent of net revenues received from Microsoft plus an ITCC adjustment and extending the refund period for energization-related costs to fifteen years.
Dec 31, 2025South CarolinaDuke Energy Carolinas rate case: SC commission approves large load stipulation for 50 MW+ customersOrder No. 2025-769, dated December 31, 2025, found the Large Load Stipulation just and reasonable, in the public interest and in accordance with law, and approved it in its entirety.
Dec 18, 2025New MexicoPNM seeks approval of amended data center power contract with Greater Kudu, plus three power dealsA Commission final order in Case No. 25-00048-UT made PNM's 3rd Revised Rider No. 47 (Green Energy Rider) effective December 18, 2025; the passages do not state the ruling on the contract itself.
Dec 18, 2025MichiganDTE Electric special contracts for 1,383-MW Washtenaw County data center, approved with conditionsThe Commission conditionally approved the special contracts, requiring DTE Electric to bear any costs to serve the data center that it cannot recover from Green Chile Ventures LLC, and to update its emergency procedures to cut the data center's load first.
Dec 17, 2025LouisianaLouisiana PSC "Lightning" directive waiving General Order rules for capacity serving new large loadsThe Commission passed Commissioner Coussan's directive 4:1, so General Order requirements are considered waived for qualifying capacity additions that serve new or expanding load and meet the listed factors.
Dec 12, 2025South CarolinaDuke Energy Progress SC rate case: large load stipulation on new 50 MW+ customers approvedOrder No. 2025-757 (December 12, 2025) found the Large Load Stipulation just and reasonable, in the public interest and lawful, and approved it in its entirety.
Dec 4, 2025ArkansasEntergy Arkansas special rate contract with Attitude Capital (Google), approved by commissionThe Commission approved, without modification, the Agreement for Electric Service between Entergy Arkansas and Attitude Capital, LLC (Google) as consistent with the public interest.
Nov 24, 2025MissouriAmeren Missouri large load tariff: required rate for new or expanded customers of 75 MW or moreThe commission's November 24, 2025 order, in Ordering Paragraph 3, authorized Ameren Missouri's Large Load Customer Service tariff sheets, which were issued December 5, 2025 and took effect January 4, 2026.
Nov 13, 2025MissouriEvergy Missouri Metro and West large load tariff (Schedule LLPS) for customers of 75 MW or moreThe commission issued a Report and Order on November 13, 2025, finding the stipulation's LLPS proposal, with its 75 MW threshold, definite and clear; Evergy Missouri West's Schedule LLPS tariff was issued February 5, 2026, effective March 9, 2026.
Nov 6, 2025ColoradoXcel Colorado 2024 Just Transition Solicitation: large load customer contract principles and tariffDecision C25-0747 granted the 2024 Just Transition Solicitation application with modifications, generally adopted the commercial principles with changes, and directed Public Service to make a large load tariff filing no later than January 31, 2026.
Nov 6, 2025KansasEvergy Kansas large load (75 MW+) power service tariff approved by KCC via settlementOn November 6, 2025, the Kansas Corporation Commission approved a unanimous settlement agreement creating the Large Load Power Service rate plan for customers requiring greater than 75 megawatts of peak power.
Aug 29, 2025LouisianaEntergy Louisiana power plants and lines for Meta data center in Richland ParishThe Commission accepted the settlement among Entergy Louisiana, Staff, Sierra Club, Walmart and the Southern Renewable Energy Association, approving the proposed generation and transmission resources for the North Louisiana customer project, subject to certain conditions.
Aug 26, 2025ArkansasArkansas Electric Cooperative's tariff for users over 50 MW to pay for transmission extensionsThe administrative law judge found the Transmission Extension of Facilities Tariff just and reasonable and in the public interest, and approved the tariff AECC filed on May 28, 2025.
Jul 31, 2025TexasEl Paso Electric economic development rates for a new El Paso data centerThe Commission approved El Paso Electric's Rate Schedule No. 33A (large economic development rate) and No. 33B (medium economic development rate), as attached to the parties' agreement, effective the first billing cycle after the Order.
Jul 9, 2025OhioPUCO orders AEP Ohio to file a data center tariff, adopting the utility's settlementOn July 9, 2025, the commission adopted the settlement agreement reached by AEP Ohio, PUCO staff, Ohio Consumers' Counsel and others, and ordered AEP Ohio to file updated data center tariffs and lift its moratorium on new data center connections.
Jun 5, 2025OregonOregon HB 3546 (POWER Act): separate rate class and long contracts for large data-center usersThe Legislature enacted HB 3546, requiring the PUC to create a separate large energy use facility classification with its own tariff and to require contracts of 10 years or longer with a minimum payment obligation.
May 29, 2025TexasTexas Senate Bill 6: rules for large electricity users (large loads) in ERCOTThe Legislature passed S.B. 6 in 2025, and the Public Utility Commission adopted new 16 TAC §25.194 in Project No. 58481, implementing the large load interconnection standards of PURA §37.0561.
Apr 25, 2025South CarolinaSantee Cooper experimental Large Load rate schedule L-25-LL for data centers and other big usersSantee Cooper adopted Schedule L-25-LL on April 25, 2025, effective for bills rendered on and after that date, and available through no later than April 24, 2029.
Nov 4, 2022ArkansasEntergy Arkansas large power high-load density (crypto mining) tariff, Rate Schedule 69Order No. 7 found EAL's proposed LPHLDS tariff just and reasonable and approved it, allowed a three-month deposit, and ordered EAL to include LPHLDS customers in its annual report to the Commission.
n/aNorth CarolinaDuke Energy Carolinas rate case: large load tariff for data centers over 50 MW approvedAccording to Duke's press release, the Commission approved new rates for Duke Energy Carolinas and Duke Energy Progress and established a new rate schedule for data center customers with loads above 50 megawatts, adding upfront payment and security requirements.
n/aNorth CarolinaDuke Energy Progress rate case: new large-load tariff for data centers over 50 MW approvedThe Commission approved rate increases for Duke Energy Progress and Duke Energy Carolinas and established a new rate schedule for data center customers with loads above 50 megawatts, adding upfront facility payments and security requirements.
n/aIndianaNIPSCO and GenCo special contract to serve Amazon data centers, approved by Indiana regulatorsThe commission approved the Settlement, the Customer Contract, the Power Purchase Agreement, the alternative regulatory plans, and the depreciation accrual rates for the generation and transmission assets to be built.
n/aOregonPacific Power Schedule 401 tariff for large data centers under Oregon's POWER ActThe Commission adopted the stipulation among Pacific Power, Staff, CUB and others, finding it in the public interest and resulting in just and reasonable rates, with a direct contracting and direct assignment approach and a 1-cent per kilowatt-hour surcharge.
n/aMarylandMaryland PSC opens PC 72 work group on large load customer regulations and tariffsThe Commission initiated Public Conference 72, established a work group led by Drew McAuliffe, and directed it to file proposed regulations and recommendations by December 6, 2025.
n/aUtahUtah PSC rulemaking on large-load electric service rules under S.B. 132, Rule R746-318The PSC made new rule R746-318 effective January 1, 2026, and continued the rulemaking to consider potential amendments, consolidating it with the line extension investigation (Docket No. 24-035-43) that will cover a large load flexible tariff.
n/aKentuckyEast Kentucky Power Cooperative's Rate DCP data center tariff approved with changesThe Commission approved EKPC's Rate DCP tariff as modified in the order, effective for service on and after the order date, required revised tariff sheets within 20 days, and closed the case.
n/aKentuckyKentucky Power tariff: long-term terms and safeguards for new customers of 150 MW or moreThe Commission approved Kentucky Power's proposed Tariff I.G.S. revisions with modifications, so they apply only to large-load customers adding 150 MW or more of incremental load on or after the date of the Order.
n/aUtahUtah PSC consolidates Rocky Mountain Power large-load line extension probe with S.B. 132 rulemakingOn January 15, 2026, the PSC consolidated the investigation with the rulemaking, continued the rulemaking to consider amendments to the Rule, and set a January 28, 2026 scheduling conference.
n/aIndianaIndiana Michigan Power large-load terms added to Industrial Power tariff, approved by IURCThe commission approved the Settlement Agreement as modified and approved I&M's proposed Tariff I.P. as modified by the settlement, requiring commission review of contract capacity reductions beyond 20% and semi-annual Large Load Customer reports.
n/aWest VirginiaAppalachian Power and Wheeling Power large-load tariff terms for 100 MW+ customers approvedOn March 25, 2025, the Commission accepted the Joint Stipulation and Agreement for Settlement and required revised tariff Schedules LCP and IP to be filed within ten days of the Order.
n/aGeorgiaGeorgia Power 2023 resource plan update: added grid capacity; docket holds large-load reportsThe commission unanimously approved Georgia Power's interim Integrated Resource Plan in April 2024, which added extra capacity to Georgia's power grid.
n/aMinnesotaMinnesota law on electric service to very large customers (Minn. Stat. 216B.1622)The Legislature enacted section 216B.1622 in 2025 (1Sp2025 c 12 s 9) and amended subdivision 2 in 2026 (c 88 art 1 s 91), requiring the commission to establish very large customer class definitions by order by December 15, 2026.
n/aMinnesotaMinnesota PUC approves Xcel's very large customer tariff, with stronger cost protectionsThe Commission adopted Xcel's proposed tariff framework for very large customers (new loads of 100 MW or more) but strengthened it, including a standalone customer class and an 80% minimum bill and exit fee.
n/aFloridaFlorida law sets large load tariff rules for electric utilities (s. 366.043)The Legislature enacted section 366.043 (s. 3, ch. 2026-65), requiring large load tariffs that make each large customer bear its full cost of service, with utilities filing compliant tariffs for commission approval by October 1, 2026.
n/aArizonaArizona law on reports, service terms and cost studies for extra high load factor electricity customersThe act was approved by the Governor on June 4, 2026 and filed with the Secretary of State on June 5, 2026, adding section 40-207 and requiring cost-of-service studies on request.
n/aArizonaTucson Electric Power special agreement to serve Project Blue data center (Humphrey's Peak Power)The Commission approved the Tucson Electric Power Energy Supply Agreement with Humphreys Peak Power, LLC in Decision No. 81587, without guaranteeing any future ratemaking treatment of the Special Contract; the press release reports a 4-1 vote.
n/aNebraskaOPPD Rate 261M: market-priced power rate for very large high-voltage customersOPPD's Board of Directors unanimously approved Rate 261M in 2017.
n/aMichiganMichigan PSC approves Consumers Energy terms of service for data centers and other very large customersThe Commission approved Consumers Energy's application, with a 15-year minimum contract term, 80% minimum billing demand, an exit fee and collateral, applying to customers of 100 MW or more, and left cost allocation and rate design to later cases.

Texas

CaseWhat it isKindOpenedLatest filingFilings
Skybox Datacenters complaint against ERCOT over reclassification of its large-load project BZ-465 No. 60431Skybox Datacenters filed a complaint against ERCOT over ERCOT's reclassification of BZ-465 from base load. It is one of the "Batch Zero" complaint dockets. Joint Large Loads, ERCOT and PUC Staff have filed lists of issues. The case is abated, and Order No. 3 set a deadline for a proposed schedule and scheduled a prehearing conference.DisputeOct 26, 2026Nov 23, 202629
Rowan Stampede LLC complaint against ERCOT, one of the "Batch Zero" large-load complaints No. 60396Rowan Stampede LLC filed a complaint against ERCOT on 2026-10-14, asking for immediate suspension of conduct and expedited relief. ERCOT, Commission Staff, a group called Joint Large Loads and Skybox Datacenters, LLC have filed in the case. The case has been abated, and lists of issues were filed in November. An order on 2026-11-23 sets a deadline for a proposed schedule and a prehearing conference.DisputeOct 14, 2026Nov 23, 202635
Medina County Power appeals ERCOT decisions in "Batch Zero" large-load complaint cases No. 60356Medina County Power NR I, LLC filed a complaint and appeal of decisions by ERCOT, the Texas grid operator. The case is one of the "Batch Zero" complaint dockets. Joint Large Loads, Skybox Datacenters, South Texas Electric Cooperative and PUC staff are taking part. The case is paused while parties file lists of issues, and a prehearing conference and procedural schedule are being set.Connecting to the gridSep 30, 2026Nov 23, 202645
Southwestern Public Service Co. asks Texas PUC to approve large load customer tariff provisions No. 60332Southwestern Public Service Company filed this application on 2026-09-25 asking the Public Utility Commission of Texas to approve large load customer tariff provisions. Texas Industrial Energy Consumers, the Data Center Coalition, the Office of Public Utility Counsel, Golden Spread Electric Cooperative, Targa Resources and AXM have joined. The case is in the discovery and issues-list stage, with Commission Staff recommending a procedural schedule on 2026-11-23.Rates and terms for large usersSep 24, 2026Nov 23, 202644
Mesquite H2 appeals ERCOT decisions; one of the "Batch Zero" large-load complaint dockets No. 60410Mesquite H2, LLC filed a complaint appealing unspecified ERCOT decisions and asked for expedited handling. South Texas Electric Cooperative moved to intervene, and Skybox Datacenters and a group called Joint Large Loads also filed. The commission paused the schedule; ERCOT and Joint Large Loads then filed lists of issues for the "Batch Zero" complaints.DisputeOct 20, 2026Nov 19, 202634
PUCT review of ERCOT's process for connecting large loads such as data centers to the grid No. 59142The Public Utility Commission of Texas is reviewing how ERCOT connects large electricity users to the grid. Filings concern ERCOT's "Batch Zero" eligibility verification and audit process. Synergen Green Energy asked for a good cause exception to the Batch Zero deadlines, and residents filed comments opposing it. Residents also requested audits of Project Raptor, a 1000 MW request. The commission granted other good cause exceptions on 2026-08-20.Connecting to the gridDec 17, 2025Nov 18, 202685
Texas PUC rulemaking on a standard interconnection agreement for large electricity users No. 59999Texas PUC staff recommended a draft Standardized Large Load Interconnection Agreement, and the commission published it with a request for comments. The Office of Public Utility Counsel filed a notice of participation. Green Recursive Utility Service LLC filed comments and a separate petition proposing its own rule, with a request for a public hearing.Connecting to the gridJul 15, 2026Nov 11, 202610
Texas PUC review of ERCOT rule changes, including large-load interconnection and ride-through rules No. 54445The Texas commission reviews and approves rule changes (revision requests) that ERCOT's board recommends. Part of the docket covers PGRR 145, the Batch Zero process for large load interconnections, and NOGRR 282, ride-through requirements for large computational loads. Data center, crypto, industrial and utility groups filed comments in June 2026. The commission issued orders approving ERCOT revision requests on 2026-06-18 and 2026-11-05.Connecting to the gridDec 7, 2022Nov 5, 2026167
SWEPCO asks Texas PUC to add a large-load standard electric service contract to its tariffs No. 58796Southwestern Electric Power Company applied to amend its retail tariffs to include a new standard form contract for large-load electric service. Texas Industrial Energy Consumers, Eastman Chemical, the Office of Public Utility Counsel, CARD and Commission Staff took part. The utility filed a unanimous settlement agreement and the case was sent back from SOAH to the Commission. A proposed order was filed October 28, 2026.Rates and terms for large usersOct 3, 2025Oct 28, 2026109
El Paso Electric asks Texas PUC to update economic development rate rider for a new data center No. 59948El Paso Electric Company filed an application on 2026-07-01 asking the Public Utility Commission of Texas to approve an update to its Rate Schedules 33A and 33B, the economic development rate rider, for a new data center. The City of El Paso intervened. Commission Staff gave its recommendation on final disposition, and the parties filed a joint motion to admit evidence with proposed findings. Evidence was admitted on 2026-10-14.Rates and terms for large usersJul 1, 2026Oct 14, 202617
Texas PUC: Green Recursive petition for rule on large computational loads, denied No. 60084 · DecidedGreen Recursive Utility Service LLC petitioned the Public Utility Commission of Texas to adopt a measurement standard and regulatory framework for large computational loads. Oncor Electric Delivery filed comments opposing the petition if it affects Oncor's rights or obligations. The commission issued an order denying the petition for rulemaking.Commission rules or inquiryAug 6, 2026n/a0
Texas PUC rulemaking on how large loads like data centers connect to the grid (new rule 25.194) No. 58481The Public Utility Commission of Texas is writing a new rule, 16 TAC §25.194, setting large load interconnection standards under PURA §37.0561. Data center groups, power companies, Oncor, cities and other parties filed comments on the proposal. On 2026-09-18 the commission issued an order adopting the rule, with a Texas Register effective date of 10.08.2026.Commission rules or inquiryJul 31, 2025Sep 18, 2026219
Texas PUC rulemaking on a demand management service for large electricity users (new §25.521) No. 58482Commission staff published a proposed new rule, 16 TAC §25.521, for a Large Load Demand Management Service. Comments on the proposal were due September 4, 2026. Filers include ERCOT, the Data Center Coalition, Google, utilities such as Oncor and CenterPoint, the Office of Public Utility Counsel, the market monitor, and Sierra Club.Commission rules or inquiryAug 1, 2025Sep 6, 202664
Texas PUC petition to require data centers to report water use before grid connection (denied) No. 59824Margaret Elizabeth Hill and the Texas Residents and Ratepayers petitioned the Texas commission to change a rule so large data centers disclose water demand before connecting to the grid. Many members of the public filed comments in support, and Oncor filed comments opposing a proposed 50-megawatt large load threshold. On July 30, 2026, the commission issued an order denying the petition.Commission rules or inquiryMay 29, 2026Jul 30, 202666
El Paso Electric asks Texas PUC to approve new high load factor tariff for data centers No. 59611 · OpenEl Paso Electric asked the Public Utility Commission of Texas to approve Schedule No. 27, a new rate for very large data center or advanced manufacturing customers with peak demand of 75 MW or larger and load factor of at least 85%. The filing says the Wurldwide data center under construction would qualify.Rates and terms for large usersApr 7, 2026n/a0
Texas PUC rule on large loads net metering with existing power plants (new 16 TAC §25.205) No. 58479The Public Utility Commission of Texas is writing a rule on net metering arrangements where a large load, such as a data center, is co-located with an existing power plant. Utilities, ERCOT, the Data Center Coalition, CyrusOne, Crusoe, Vistra, Calpine, Sierra Club and the Office of Public Utility Counsel filed comments. On 2026-03-26 the commission issued an order adopting new 16 TAC §25.205.Commission rules or inquiryJul 31, 2025Mar 26, 202667
Texas PUC rule on how ERCOT counts large loads like data centers in its demand forecast No. 58480The Public Utility Commission of Texas is setting criteria for including large electricity users in ERCOT's load forecasts under a new rule, 16 TAC § 25.370. Utilities, the Data Center Coalition, Crusoe, consumer advocates and others filed comments and reply comments. On 2026-02-06 the commission issued an order adopting the new rule, and ERCOT filed a compliance plan.Commission rules or inquiryJul 31, 2025Feb 9, 202659
Pacifico Spunky LLC registers a new power plant for an AI data center in Hood County, Texas No. 58854Pacifico Spunky LLC applied to the Public Utility Commission of Texas for a power generation company registration. Its filing describes a new power generation facility for AI data center development in Hood County. Consumer Protection staff made a recommendation on 2025-11-06, and the commission's office issued a notice of approval on 2025-11-14.New plants, lines or power purchasesOct 17, 2025Nov 14, 20253
El Paso Electric economic development rates for a new El Paso data center No. 56903 · DecidedEl Paso Electric applied on August 1, 2024 for two new rates under its economic development tariff, Rate Schedule No. 33, for a new data center in El Paso. The data center is expected to have a peak demand of over 100 megawatts (MW). The commission approved the rates after the parties filed an agreement.Rates and terms for large usersAug 1, 2024n/a0
Texas PUC project to implement SB 6 on large electricity loads such as data centers No. 58317 · OpenThe Public Utility Commission of Texas runs Project 58317 to implement Senate Bill 6. Staff have filed roadmaps and memos, and companies, officials and residents have filed comments, including on Governor Abbott's June 10, 2026 letter about data center infrastructure costs.Commission rules or inquiryJun 30, 2025n/a0
Texas Senate Bill 6: rules for large electricity users (large loads) in ERCOT No. S.B. No. 6 (89th Legislature, Regular Session, 2025) · DecidedTexas Senate Bill 6 directs the Public Utility Commission to set interconnection standards for large load customers in ERCOT, with a 75 megawatt demand threshold, and to make them contribute to interconnection costs. The bill passed both houses, and the commission has adopted a rule under it, 16 TAC §25.194.Othern/an/a0
PUC of Texas rulemaking on ERCOT transmission cost allocation and large load minimum billing demand No. 58000 · OpenCommission staff proposed replacing the four coincident peak (4CP) method for assigning transmission costs with a 12 coincident peak (12CP) method, and requiring a minimum billing demand for large load customers. The commission approved the proposal for publication on July 9, 2026, and comments were due August 11, 2026.Commission rules or inquiryApr 23, 2025n/a0

Florida

CaseWhat it isKindOpenedLatest filingFilings
Florida PSC denies Duke Energy Florida's large load tariff for customers of 50 MW or more No. 20260064-EI · DecidedDuke Energy Florida asked the Florida Public Service Commission to approve a Large Load Customer Policy, a Large Load Customer Agreement and revised contribution in aid of construction tariffs for customers of 50 megawatts or more. The Commission found the proposal did not comply with Section 366.043, Florida Statutes, and denied it.Rates and terms for large usersApr 22, 2026n/a0
Green Recursive Utility Service asks Florida PSC to adopt a large-load measurement rule No. 20260158-EU · OpenGreen Recursive Utility Service LLC petitioned the Florida Public Service Commission to start rulemaking on a measurement and reporting methodology for large load service under § 366.043. It proposes designating its own standard, GRUS-STD-60084 v2.0-U, for data center and large-load water and energy consumption.Commission rules or inquiryOct 30, 2026n/a0
FPL seeks approval of tariff revisions and a finding its large load tariffs meet Florida law No. 20260149-EI · OpenFlorida Power & Light asked the Florida PSC to approve minor tariff revisions on foreign entities and to find its existing Large Load Contract Service tariffs comply with Section 366.043. The Commission issued an order suspending the tariff while staff needs more time to analyze the petition.Rates and terms for large usersOct 1, 2026n/a0
Florida Public Utilities Co. asks Florida PSC to approve a Large Load Service tariff No. 20260148-EI · OpenFlorida Public Utilities Company petitioned the Florida Public Service Commission on October 1, 2026 for approval to institute a Large Load Service tariff, filing new and revised electric tariff sheets. The passages show only the petition, not a ruling.Rates and terms for large usersOct 1, 2026n/a0
Tampa Electric asks Florida PSC to approve large load customer rate schedules and contract No. 20260146-EI · OpenTampa Electric asked the Florida Public Service Commission to approve two Large Load Customer rate schedules (LLCS-1 and LLCS-2), a standard contract and related tariff changes to comply with section 366.043. The commission issued an order suspending the tariff; the passages do not show a final approval decision.Rates and terms for large usersSep 30, 2026n/a0
FPL rate case: large load (data center) tariffs LLCS-1 and LLCS-2 approved through 2025 settlement No. 20250011-EI · DecidedIn its base rate case, Florida Power & Light proposed Large Load Contract Service tariffs for customers with very large new loads. The settlement would apply them at 50 MW or more of new load, down from the 25 MW first proposed, with a 70% minimum take-or-pay demand charge, down from 90%.General rate casen/an/a0
Duke Energy Florida's withdrawn petition for a large load tariff and rate schedule No. 20250113-EIDuke Energy Florida petitioned on September 5, 2025 for a new large load tariff with an associated rate schedule. The schedule was abated on March 19, 2026 for pending legislation (SB 484), Duke withdrew the petition, and the docket was closed April 27, 2026.Rates and terms for large usersSep 5, 2025n/a0
Florida law sets large load tariff rules for electric utilities (s. 366.043) No. SB 484 (2026), ch. 2026-65; s. 366.043, F.S. · DecidedFlorida's statute 366.043 sets minimum tariff and service requirements for customers with a peak load of 50 megawatts or more, so their costs are not shifted to other ratepayers. It bars service to foreign entities of concern and requires each public utility to file a compliant tariff by October 1, 2026.Othern/an/a0

Virginia

CaseWhat it isKindOpenedLatest filingFilings
Dominion Virginia asks approval of Rider T1 rate adjustment clause; data center issues argued No. PUR-2026-00056 · Under AppealDominion asked the Virginia SCC to approve a rate adjustment clause, Rider T1. Microsoft, Amazon Data Services, Google, Commission Staff and others took part, and exhibits address data center projects. After a July hearing, the Commission issued a final order on 07/31/2026 and Dominion filed a revised tariff. Microsoft appealed, then withdrew the appeal on 11/17/2026.Rates and terms for large usersJul 9, 2026Nov 17, 2026146
Virginia SCC docket on how transmission costs are allocated to large-load customers No. PUR-2026-00131 · ActiveThe Virginia State Corporation Commission established this docket by an order dated 2026-08-25 to look at allocating transmission costs to large-load customers. The filings show a comment from Nathan Barasa Wangusi, PhD, M.ASCE, submitted for the Commission's consideration. A Virginia Electric and Power Company application to amend its Line Extension Policy was also filed on 2026-10-29.Commission rules or inquiryAug 25, 2026Oct 29, 20263
Dominion Energy Virginia seeks approval of its queue process for connecting large loads No. PUR-2026-00011 · PendingVirginia Electric and Power Company (Dominion) asked the State Corporation Commission to approve its large-load connection queue process. Data center and tech companies, including Amazon, Google, Microsoft, STACK and Verrus, the Data Center Coalition and the Piedmont Environmental Council took part. Hearings were held April 28–30, 2026, post-hearing briefs were filed June 30, and the Commission issued an order on October 23, 2026.Connecting to the gridFeb 4, 2026Oct 23, 2026128
Dominion Virginia 2025 rate review, including special terms for high-load customers (GS-5) No. PUR-2025-00058 · Under AppealVirginia Electric and Power Company (Dominion) filed a biennial review of its rates, terms and conditions. The filings show a final order dated 11/25/2025 and a notice of appeal by the Retail Energy Advancement League. Data Center Coalition, Amazon, Microsoft, Google and others filed briefs. In October 2026 the company filed revised terms for High Load Customers and a Rate Schedule GS-5, which Staff accepted.General rate caseAug 22, 2025Oct 14, 2026646
Appalachian Power large-load terms for Schedule L.P.S.: Virginia SCC order adopting examiner's report No. PUR-2025-00057 · DecidedAppalachian Power asked to add terms for new customers of 150 MW aggregated or 100 MW at one site, including a twelve-year contract, five-year notice, 80 percent minimum billing demand and more collateral. The Commission adopted its Hearing Examiner's report, which found a 14-year initial term, including a ramp period of up to four years, reasonable.Rates and terms for large usersMar 24, 2025n/a0
Virginia SCC approves Rappahannock Electric Cooperative's large-load rate schedule LP-DF No. PUR-2025-00048 · DecidedRappahannock Electric Cooperative asked the Virginia State Corporation Commission to approve Schedule LP-DF, a new rate for customers served through dedicated facilities with contracted demand above 25 MW and a 75 percent load factor. The Commission approved it, with modifications, effective April 15, 2026.Rates and terms for large usersn/an/a0
Virginia SCC inquiry on utilities and data center load growth: technical conference on large load flexibility No. PUR-2024-00144 · OpenThe Virginia State Corporation Commission is examining rate impacts and challenges from large-load customers, particularly data centers. Its October 23, 2025 scheduling order set a technical conference on large load flexibility and continued the case.Commission rules or inquiryn/an/a0

Arizona

CaseWhat it isKindOpenedLatest filingFilings
Six Arizona co-ops seek streamlined process for large-load electric service agreements No. E-01461A-26-0123Six electric cooperatives jointly applied to the Arizona Corporation Commission for a streamlined process for multiparty agreements to serve large-load customers. The applicants are Arizona Electric Power Cooperative, Duncan Valley, Graham County, Mohave, Sulphur Springs Valley and Trico. The filings listed are only generic "Document Filed" entries from the co-ops in November 2026, so their content and the case's stage are not shown.Rates and terms for large usersApr 17, 2026Nov 20, 202624
Arizona Corporation Commission inquiry into electric rate classes and issues for data centers No. E-00000A-25-0069The Arizona Corporation Commission is reviewing the existing rate classifications and other potential issues relating to data centers. The filings shown are six entries marked "Document Filed" by the commission, dated October 26 to November 9, 2026. They don't describe what the documents say, who else is taking part, or what stage the case is at.OtherApr 2, 2025Nov 9, 20266
APS asks Arizona regulators to approve 25-year direct pricing contract for TSMC Arizona No. E-01345A-26-0454 · OpenArizona Public Service asked the Arizona Corporation Commission to approve a 25-year Direct Pricing Contract with TSMC Arizona Corporation, plus related accounting orders and resource findings. The contract contemplates ramping to approximately 1.88 GW and includes fixed capacity charges, exit fees and collateral obligations.Contract with a large customerNov 6, 2026n/a0
APS rate case: changes to Extra High Load Factor rate, requiring data centers to use it No. E-01345A-25-0105 · OpenIn its general rate case, Arizona Public Service proposes changing its cost allocation and XHLF rate schedule so data centers must take XHLF service, with revised minimum bill and eligibility terms. The hearing ran May 18 to July 7, 2026; the judge's recommended order was expected by late November 2026.General rate caseMay 15, 2025n/a0
Arizona law on reports, service terms and cost studies for extra high load factor electricity customers No. HB 2756 (2026), Laws 2026, Chapter 111 · DecidedArizona's legislature enacted a law requiring electric utilities to file semiannual reports on interconnection requests and completed interconnections for new extra high load factor customers. It lets the Corporation Commission set service terms for those customers and requires cost-of-service studies on request within one hundred eighty days.Othern/an/a0
Tucson Electric Power special agreement to serve Project Blue data center (Humphrey's Peak Power) No. E-01933A-25-0187 · DecidedTucson Electric Power asked the Arizona Corporation Commission to approve a special agreement for electric service to the planned Project Blue data center, developed by Beal Infrastructure Group and its affiliate Humphrey's Peak Power, LLC. The Commission approved it at its December 3, 2025 meeting.Contract with a large customern/an/a0

South Carolina

CaseWhat it isKindOpenedLatest filingFilings
Santee Cooper adopts standard High Impact Load rate for data centers and other large loads No. Schedule L-27-HIL · DecidedSantee Cooper's board approved a High Impact Load Rate, Schedule L-27-HIL, that turns the 2025 experimental large load rate into a standard offering. Customers must sign service agreements of at least 180 months, pay upgrade costs up front, post collateral, and carry a 90% minimum firm billing demand factor.Rates and terms for large usersOct 30, 2026n/a0
Dominion Energy South Carolina rate case: commission approves large load (50 MW+) stipulation No. 2025-325-E · DecidedDominion Energy South Carolina's rate case included a Large Load Stipulation, filed May 8, 2026, in which the company agreed to join a generic docket on new large load (50 MW or greater) additions. The Commission's July 2, 2026 order approved the stipulation.General rate caseDec 1, 2025n/a0
Duke Energy asks SC regulators to open a comment docket on large load additions of 50 MW or more No. 2026-138-E · OpenDuke Energy Carolinas and Duke Energy Progress petitioned the South Carolina commission to open a generic docket for comments on new large loads (50 megawatts or greater), including rate schedules, line extension policies and interconnection rules. The docket is open, and Order No. 2026-362 clarified the procedural schedule.Commission rules or inquiryMay 27, 2026n/a0
Duke Energy Carolinas rate case: SC commission approves large load stipulation for 50 MW+ customers No. 2025-172-E · DecidedIn Duke Energy Carolinas' South Carolina rate case, the parties to a Large Load Stipulation agreed to petition the Commission to open a generic docket on new large load (50 MW or greater) additions, by June 1, 2026. The Commission's order approved that stipulation in its entirety.General rate caseMay 30, 2025n/a0
Duke Energy Progress SC rate case: large load stipulation on new 50 MW+ customers approved No. 2025-154-E · DecidedIn Duke Energy Progress's South Carolina rate case, parties signed a Large Load Stipulation agreeing to petition for a generic docket on new large loads of 50 MW or greater. The Commission's order approved that stipulation in its entirety.General rate caseMay 13, 2025n/a0
Santee Cooper experimental Large Load rate schedule L-25-LL for data centers and other big users No. Schedule L-25-LL · DecidedSantee Cooper adopted an experimental Large Load Service schedule, mandatory for data centers and other facilities over 50,000 kW. It requires a service term of at least 180 months, upfront payment of delivery point and transmission costs, and collateral equal to 180 months of Minimum Bills.Rates and terms for large usersApr 25, 2025n/a0

Arkansas

CaseWhat it isKindOpenedLatest filingFilings
Arkansas PSC opens docket on ratepayer affordability, including large load tariffs No. 26-042-U · OpenThe Arkansas Public Service Commission opened a docket to explore ways to make electric and natural gas bills more affordable, including large load tariffs, sleeve power purchase agreements and time-of-use rates. All jurisdictional electric and natural gas utilities are parties, and the docket page lists it as open.Commission rules or inquiryJun 3, 2026n/a0
Entergy Arkansas special rate contract with Attitude Capital (Google), approved by commission No. 25-055-P · DecidedEntergy Arkansas applied for approval of a special rate customer contract with Attitude Capital, LLC, called Google in the filing, and for other related approvals. In Order No. 9, dated 12/4/2025, the Arkansas Public Service Commission approved the agreement.Contract with a large customerAug 15, 2025n/a0
Arkansas Electric Cooperative's tariff for users over 50 MW to pay for transmission extensions No. 25-031-TF · DecidedArkansas Electric Cooperative Corporation filed a Transmission Extension of Facilities tariff on May 28, 2025. It covers users of more than 50 MW, who would pay for the transmission facilities built to serve them. An administrative law judge approved it in Order No. 6.Rates and terms for large usersMay 28, 2025n/a0
Arkansas Electric Cooperative asks approval of curtailable Demand Response tariff for 50 MW+ users No. 25-008-TF · OpenArkansas Electric Cooperative Corporation filed a Demand Response Service tariff for member cooperatives serving power-intensive retail consumers of 50 MW or greater whose load can be curtailed. The docket shows the tariff suspended and a joint motion to approve a unanimous settlement filed, and it is listed as open.Rates and terms for large usersJan 30, 2025n/a0
Entergy Arkansas large power high-load density (crypto mining) tariff, Rate Schedule 69 No. 22-032-TF · DecidedEntergy Arkansas applied for a Large Power High-Load Density Service tariff (Rate Schedule No. 69) for high-load customers. The Commission approved it in Order No. 7, required annual reporting, and in Order No. 8 found additional reporting on the tariff in the public interest.Rates and terms for large usersMay 23, 2022n/a0

Louisiana

CaseWhat it isKindOpenedLatest filingFilings
Cleco Power seeks approval of large-load customer contracts and grid/generation certification No. U-38035 · OpenCleco Power applied to the Louisiana Public Service Commission to authorize contracts, including a site specific contract, and certify transmission interconnection and new generation for a large load customer under the Lightning Initiative. A procedural order sets Commission consideration for the March 2027 session.Contract with a large customerJul 9, 2026n/a0
Louisiana PSC repository docket for non-binding guidelines on large load additions No. X-37921 · OpenThe Louisiana Public Service Commission opened a repository docket, published for information only, for its Large Load Additions Non-Binding Guidelines. The guidelines list areas a utility should address when serving a large new load, such as transmission costs, stranded assets, rates and curtailment.Commission rules or inquiryMay 6, 2026n/a0
Louisiana PSC proceeding on private use electrical networks to serve new large loads No. R-37905 · OpenThe Louisiana Public Service Commission opened an ex parte proceeding, docket R-37905, on determining and evaluating private use electrical networks so generation can serve new large loads locating in Louisiana. The docket is listed as open, with utilities, industrial companies and advocacy groups named as involved.Commission rules or inquiryApr 22, 2026n/a0
Louisiana PSC "Lightning" directive waiving General Order rules for capacity serving new large loads No. R-34247 · DecidedCommissioner Coussan's directive waives the requirements of General Order 10-14-2024 (R-34247) for a capacity addition serving a new or expanding load, if conditions including a signed electric service agreement of at least 15 years are proven in the certification proceeding. It passed 4:1 on December 17, 2025.OtherDec 17, 2025n/a0
Entergy Louisiana power plants and lines for Meta data center in Richland Parish No. U-37425 · DecidedEntergy Louisiana asked the Commission to approve generation and transmission resources, including a proposed rider, to serve a data center Meta Platforms is developing through its subsidiary Laidley LLC in Richland Parish. The Commission accepted a settlement approving the resources, subject to conditions.New plants, lines or power purchasesNov 4, 2024n/a0

Idaho

CaseWhat it isKindOpenedLatest filingFilings
Idaho Power annual update of marginal energy prices for large-load Schedules 20 and 34 No. IPC-E-26-08 · DecidedIdaho Power asked the Commission to acknowledge its updated marginal cost calculations and let it keep the current marginal energy price components of Schedule 20 (Speculative High-Density Load) and Schedule 34 (Lamb Weston Special Contract). The Commission granted this and directed a separate docket on the methodology.Rates and terms for large usersApr 1, 2026n/a0
Idaho Power seeks approval of special contract and Schedule 28 to serve Micron's memory fab No. IPC-E-24-44 · DecidedIdaho Power asked the Idaho Public Utilities Commission to approve a special electric service contract with Micron Idaho Semiconductor Manufacturing (Triton) LLC for its new memory fabrication complex, plus rates in tariff Schedule 28. The Commission approved it with modifications to the energy charge and minimum monthly billing demand terms.Contract with a large customerDec 6, 2024n/a0
Idaho law requiring commission approval of contracts for new large electricity loads (HB 911) No. Idaho Code 61-335 (House Bill 911, 2026) · DecidedIdaho Code 61-335 says a utility may serve a new load of 50 megawatts or more only under a commission-approved contract. The commission must approve or deny each contract within 270 days of filing and issue orders to implement the section.Othern/an/a0
Idaho Power asks to open a docket on cost-of-service methods and costs of new large-load customers No. IPC-E-26-07 · OpenIdaho Power asked the Idaho Public Utilities Commission to open a single-issue docket to evaluate its class cost-of-service methodology, four alternative methodologies, and cost considerations for new large-load customers such as data centers. The request is not for rate changes or approval of a specific methodology.OtherMar 31, 2026n/a0

Michigan

CaseWhat it isKindOpenedLatest filingFilings
DTE Electric's special contracts with Google for a Wayne County data center, approved with conditions No. U-22058 · DecidedDTE Electric asked the Michigan commission to approve two special contracts with Google: one setting electric service terms for a Van Buren Township data center, the other for new clean energy and storage paid for by Google. The commission approved both with conditions protecting other customers from costs.Contract with a large customerMar 17, 2026n/a0
Michigan approves Indiana Michigan Power's amended large load tariff for data centers No. U-21986 · DecidedThe Michigan commission let Indiana Michigan Power amend its large load tariff for customers drawing 50 megawatts (MW) or more, including data centers. Amendments include a 15-year contract term, early termination fees and a 90% monthly minimum billing demand; I&M must propose a standalone large load rate in its next general rate case.Rates and terms for large usersn/an/a0
DTE Electric special contracts for 1,383-MW Washtenaw County data center, approved with conditions No. U-21990 · DecidedDTE Electric applied for approval of special contracts to supply power to a 1,383-MW data center in Saline Township, Washtenaw County, run by Green Chile Ventures LLC, an Oracle subsidiary. The Michigan Public Service Commission conditionally approved them on December 18, 2025, adding safeguards for other customers.Contract with a large customern/an/a0
Michigan PSC approves Consumers Energy terms of service for data centers and other very large customers No. U-21859 · DecidedConsumers Energy applied to amend its Rate GPD general primary demand rate to add a data center provision. The Michigan Public Service Commission approved it on November 06, 2025, with protections against cross-subsidization and stranded costs.Rates and terms for large usersn/an/a0

California

CaseWhat it isKindOpenedLatest filingFilings
CPUC rulemaking on electric rate design, with a track on data center tariffs and customer protections No. R.26-04-009 · OpenThe California Public Utilities Commission opened a rulemaking on April 9, 2026 to consider advanced electric rate design. A Sept. 22, 2026 scoping memo sets Track 1 to ask whether to create data center rate design, including a separate customer class, new rates, exit fees, and protections against cost shifts and stranded costs.Commission rules or inquiryApr 9, 2026n/a0
PG&E asks CPUC to approve transmission agreements for Microsoft's 90 MW San Jose data center No. PG&E Advice Letter 7635-E / Resolution E-5439 · DecidedPG&E asked the California Public Utilities Commission to approve four agreements for new transmission facilities to energize a 90 megawatt (MW) Microsoft data center in San Jose. The Commission approved them with modifications, limiting refunds of Microsoft's energization costs to 75 percent of net revenues plus an ITCC adjustment.Contract with a large customerJul 1, 2025n/a0
PG&E seeks Electric Rule 30 for large transmission-level customers; interim version partly approved No. A.24-11-007 · OpenPG&E applied for Electric Rule 30, a tariff for large transmission-level customers (50-230 kilovolts) seeking retail service, and moved for interim implementation. The Commission partly granted that motion in Decision 25-07-039 and deferred refunds and cost allocation to the final decision.Connecting to the gridNov 21, 2024n/a0

Colorado

CaseWhat it isKindOpenedLatest filingFilings
Xcel Colorado asks approval of large-load tariff (Schedule TL) for new loads of 50 MW or more No. 26AL-0137E · OpenPublic Service Company of Colorado filed Advice Letter 2018-Electric proposing Schedule TL, a transmission-level rate for new or expanded loads of 50 MW or more, plus line extension changes and an optional Clean Transition Tariff. The Commission suspended the tariff and set an en banc hearing; the docket status is Suspended.Rates and terms for large usersApr 2, 2026n/a0
Xcel's Public Service Co. of Colorado asks for more time to file its large load tariff; approved No. 26V-0048E · DecidedPublic Service Company of Colorado asked the Commission for a variance from Ordering Paragraph 81 of Decision No. C25-0747 to extend the filing date for its Large Load Tariff. The Commission granted the petition, and the Colorado Energy Office intervened.OtherJan 26, 2026n/a0
Xcel Colorado 2024 Just Transition Solicitation: large load customer contract principles and tariff No. 24A-0442E · DecidedPublic Service Company of Colorado proposed nine commercial principles for new large load customers, including a 15-year minimum term and a 100 MW threshold. The Commission generally adopted them with changes, such as six months of security, and directed a large load tariff filing by January 31, 2026.New plants, lines or power purchasesOct 15, 2024n/a0

Nebraska

CaseWhat it isKindOpenedLatest filingFilings
Nebraska law limits eminent domain over private power plants serving huge industrial customers No. LB 1261 (2026) · DecidedNebraska's LB 1261, approved by the Governor April 14, 2026, bars consumer-owned utilities from using eminent domain to take a privately owned generation facility built for an industrial customer at a single site with new load greater than one thousand megawatts. It applies only with conditions, including co-location and Power Review Board approval.New plants, lines or power purchasesn/an/a0
Nebraska enacts Large Load Customer Regulation Act (LB 1010) for new loads over 20 MW No. LB 1010 (2026) · DecidedNebraska's Legislature passed LB 1010, which creates the Large Load Customer Regulation Act. It requires public power suppliers to set interconnection standards for customers whose site load would exceed twenty megawatts, and lets them negotiate rates and charges for those customers.Connecting to the gridn/an/a0
OPPD Rate 261M: market-priced power rate for very large high-voltage customers No. Rate 261M · DecidedOmaha Public Power District's Rate 261M serves large high-voltage transmission customers needing a minimum 20 megawatts (MW) of new load for 161 kilovolt (kV) service or 200 MW for 345 kV service. Customers must provide or acquire their own substation, and energy is priced hourly at a Southwest Power Pool market price.Rates and terms for large usersn/an/a0

Oregon

CaseWhat it isKindOpenedLatest filingFilings
Oregon PUC sets PGE data center rate class (Schedule 96) under the POWER Act No. UM 2377 · DecidedThe Commission investigated how Portland General Electric's tariff treats large loads and, in Order No. 26-154, implemented the POWER Act with a data center class, Schedule 96. PGE then filed Advice No. 26-24 to update its tariffs, and Staff recommends the Commission approve it.Rates and terms for large usersn/an/a0
Pacific Power Schedule 401 tariff for large data centers under Oregon's POWER Act No. UE 463 · DecidedPacifiCorp (Pacific Power) filed Advice No. 25-015 to create Schedule 401, a rate schedule for new large energy use facilities, in response to HB 3546, the POWER Act. The Oregon commission has adopted a stipulation assigning data center service costs directly to those customers.Rates and terms for large usersOct 2, 2025n/a0
Oregon HB 3546 (POWER Act): separate rate class and long contracts for large data-center users No. HB 3546 (2025) · DecidedOregon's Legislature enacted a law directing the Public Utility Commission to create a separate service classification and tariff for large energy use facilities, meaning data centers using or able to use 20 megawatts or more. Utilities serving them must sign contracts of 10 years or longer with minimum payment obligations.Othern/an/a0

Utah

CaseWhat it isKindOpenedLatest filingFilings
Rocky Mountain Power large-load service contract with unnamed customer approved by Utah PSC No. 26-035-05 · DecidedRocky Mountain Power asked the Utah PSC to approve a large-load service contract with an unnamed large-load customer. On April 10, 2026, the PSC approved the application, contract and a settlement among RMP, DPU and OCS, and denied the Utah Association of Energy Users' motion for access to restricted materials.Contract with a large customerFeb 10, 2026n/a0
Utah PSC rulemaking on large-load electric service rules under S.B. 132, Rule R746-318 No. 25-R318-01 · DecidedThe Utah Public Service Commission started this rulemaking, as S.B. 132 required, to set rules for electric service to large-scale loads of 100 megawatts or greater. It made Rule R746-318 effective January 1, 2026, and continued the rulemaking to consider amendments, consolidating it with a large load flexible tariff review.Commission rules or inquiryMay 9, 2025n/a0
Utah PSC consolidates Rocky Mountain Power large-load line extension probe with S.B. 132 rulemaking No. 24-035-43 · DecidedThe Division of Public Utilities asked the Utah PSC to open an investigation of Rocky Mountain Power's line extension policy for large loads. The PSC stayed it pending a rulemaking, then consolidated the two dockets to also consider a large load flexible tariff.Connecting to the gridAug 14, 2024n/a0

Alabama

CaseWhat it isKindOpenedLatest filingFilings
Alabama PSC sets process for reviewing Alabama Power contracts with large data center customers No. 33709 · DecidedThe Alabama Public Service Commission opened a generic proceeding on how it reviews electric service contracts between Alabama Power and large load data center customers under Act 2026-610. After 19 sets of initial comments and 10 sets of reply comments, it adopted a review process, with a vote and 90-day deemed-approval limit.Commission rules or inquiryn/an/a0
Alabama law on Public Service Commission review of large data center electric contracts (SB270) No. SB270 (2026 Regular Session) / Act No. 2026-610 · DecidedAlabama's SB270 adds Section 37-4-22.1 to the state code, setting how the Public Service Commission reviews retail electric contracts with large load data center customers, defined as expected total peak demand of 150 megawatts or greater. A contract is in the public interest if it recovers incremental costs and promotes positive benefits to other customers.OtherFeb 5, 2026n/a0

Georgia

CaseWhat it isKindOpenedLatest filingFilings
Georgia Power large-load contract filings and review within its 2022 rate case No. 44280 · OpenGeorgia Power has filed a series of large load contracts and a large load incremental revenue filing in its 2022 rate case docket. Commission Staff and the company issued a joint statement on a contract deemed filed for review on July 27, 2026. Environmental groups wrote about data center load growth and ratepayer protections, and a Hubbard motion on deposits and bills drew a company response.Contract with a large customerFeb 4, 2022Nov 20, 2026610
Georgia Power 2023 resource plan update: added grid capacity; docket holds large-load reports No. 55378 · DecidedThe Georgia Public Service Commission unanimously approved Georgia Power's interim Integrated Resource Plan in April 2024, which added extra capacity to the grid. The docket (55378) is still open, and Georgia Power has filed a Large Load Economic Development Report for Q3 2025 in it.New plants, lines or power purchasesSep 6, 2023n/a0

Indiana

CaseWhat it isKindOpenedLatest filingFilings
NIPSCO and GenCo special contract to serve Amazon data centers, approved by Indiana regulators No. Cause No. 46322 · DecidedNIPSCO and its affiliate NIPSCO Generation asked the Indiana commission to approve a special contract to serve Amazon data centers, plus a power purchase agreement between them. The commission approved the settlement, contract, agreement, alternative regulatory plans and depreciation rates.Contract with a large customerNov 7, 2025n/a0
Indiana Michigan Power large-load terms added to Industrial Power tariff, approved by IURC No. Cause No. 46097 · DecidedIndiana Michigan Power asked the Indiana commission to approve large-load terms in its Industrial Power tariff. A settlement set a 70 MW individual-site threshold (150 MW aggregated), a contract term of not less than 12 years, an 80 percent minimum billing demand and collateral requirements.Rates and terms for large usersJul 19, 2024n/a0

Kentucky

CaseWhat it isKindOpenedLatest filingFilings
East Kentucky Power Cooperative's Rate DCP data center tariff approved with changes No. 2025-00140 · DecidedEast Kentucky Power Cooperative filed Rate DCP, a tariff setting terms for serving data centers of 15,000 kW or greater with a 60 percent or greater load factor, each under a special contract approved by the Commission. The Commission approved the tariff as modified.Rates and terms for large usersApr 30, 2025n/a0
Kentucky Power tariff: long-term terms and safeguards for new customers of 150 MW or more No. 2024-00305 · DecidedKentucky Power asked to revise Tariff I.G.S. to require long-term commitments and financial safeguards from new large-load customers with contract demands of at least 150 MW. The Commission found the revisions reasonable and approved them with modifications limiting them to customers adding 150 MW or more of incremental load.Rates and terms for large usersAug 30, 2024n/a0

Maryland

CaseWhat it isKindOpenedLatest filingFilings
Maryland PSC opens rulemaking RM 93 on large load customer regulations and tariffs No. RM 93 · OpenCommission Technical Staff filed proposed regulations on large load customers, and the Maryland Public Service Commission opened RM 93 to consider them. The rules cover load study request deadlines, payment for load studies, contract terminations and adjustments, and forms of collateral.Commission rules or inquiryDec 9, 2025n/a0
Maryland PSC opens PC 72 work group on large load customer regulations and tariffs No. PC 72 · DecidedThe Maryland Public Service Commission opened Public Conference 72 and set up a work group to propose regulations for large load customers under the Next Generation Act. Each investor-owned electric company and cooperative must submit a large load rate schedule for approval.Commission rules or inquiryJun 25, 2025n/a0

Minnesota

CaseWhat it isKindOpenedLatest filingFilings
Minnesota law on electric service to very large customers (Minn. Stat. 216B.1622) No. Minn. Stat. § 216B.1622 (2025 1st Spec. Sess. ch. 12, § 9) · DecidedMinnesota's statute 216B.1622, enacted in 2025, requires the Public Utilities Commission to define a very large customer class or subclass for each electric utility by December 15, 2026. It lets the commission approve, modify or reject tariffs or service agreements with such customers, weighing required outcomes.Commission rules or inquiryn/an/a0
Minnesota PUC approves Xcel's very large customer tariff, with stronger cost protections No. 25-289 · DecidedXcel Energy proposed a tariff framework for serving very large electricity customers, as the Minnesota Legislature required. The commission adopted it but strengthened it, creating a standalone customer class and raising the minimum bill and exit fee to 80% of contracted capacity.Rates and terms for large usersn/an/a0

Missouri

CaseWhat it isKindOpenedLatest filingFilings
Ameren Missouri large load tariff: required rate for new or expanded customers of 75 MW or more No. ET-2025-0184 · DecidedAmeren Missouri filed a Large Load Customer Service rate that is required for new facilities or expansions of 75 MW or more, with billing demand of at least 80% of contract capacity and collateral of two years of minimum monthly bills. The commission's November 24, 2025 order authorized the tariff sheets, effective January 4, 2026.Rates and terms for large usersMay 14, 2025n/a0
Evergy Missouri Metro and West large load tariff (Schedule LLPS) for customers of 75 MW or more No. EO-2025-0154 · DecidedEvergy Missouri Metro and Evergy Missouri West asked the Missouri commission to approve new large load tariffs, Schedule LLPS, covering customers of 75 MW or more. The commission's Report and Order addressed a non-unanimous stipulation, to which Staff objected, and Evergy West later filed the tariff.Rates and terms for large usersn/an/a0

Montana

CaseWhat it isKindOpenedLatest filingFilings
NorthWestern Energy seeks approval of Rule No. 24, service terms for large new loads like data centers No. 2026.04.023 · OpenNorthWestern Energy applied on March 31, 2026 for approval of its Large New Load Service Tariff Rule, Rule No. 24, setting terms for data centers averaging at least five megawatts. Ratepayer advocates have moved to widen the case to a new customer class and cost allocation; NorthWestern opposes.Rates and terms for large usersMar 31, 2026n/a0
Ratepayer groups' complaint: NorthWestern Energy plans data center service without required review No. 2025.11.084Nine ratepayer and conservation groups filed a complaint against NorthWestern Energy over its plan to provide 1,400 megawatts of electricity supply service to three data center developers. They say the utility intends to do so without the Commission's required finding of no long-term adverse impact on other customers.DisputeNov 17, 2025n/a0

North Carolina

CaseWhat it isKindOpenedLatest filingFilings
Duke Energy Carolinas rate case: large load tariff for data centers over 50 MW approved No. E-7, Sub 1329 · DecidedAfter the Commission asked for comments on large-load tariffs, Duke Energy Carolinas and Duke Energy Progress settled with the Public Staff, Amazon, Google, Meta, Microsoft and others on a Large Load Tariff. Duke's press release says the Commission approved new rates and a new rate schedule for data centers above 50 megawatts.Rates and terms for large usersNov 20, 2025n/a0
Duke Energy Progress rate case: new large-load tariff for data centers over 50 MW approved No. E-2, Sub 1380 · DecidedDuke Energy Progress asked to adjust its North Carolina rates, and the Commission on August 14, 2026 requested comments on a model large load tariff for data centers. Settling parties proposed one Large Load Tariff for both Duke utilities, and the Commission has since approved a new data center rate schedule.Rates and terms for large usersNov 20, 2025n/a0

North Dakota

CaseWhat it isKindOpenedLatest filingFilings
Montana-Dakota seeks approval of Rate 45 power agreement with Applied Digital data center near Center, ND No. PU-26-235 · OpenMontana-Dakota Utilities filed an Electric Service Agreement with APLD BIS-01 LLC (Applied Digital) under its High Density Contracted Demand Response Rate 45 for approval. It also asks to waive select provisions of Rate 45's General Terms and Conditions for a new data center near Center, North Dakota.Contract with a large customerJun 26, 2026n/a0
Otter Tail Power asks ND regulators to create very large customer class and data center rate No. PU-26-215 · OpenOtter Tail Power Company asked the North Dakota Public Service Commission to approve a new class for very large customers and a new rate schedule for high power compute loads of at least 75 MW of firm load. It proposes an effective date of January 1, 2027.Rates and terms for large usersJun 18, 2026n/a0

New Mexico

CaseWhat it isKindOpenedLatest filingFilings
El Paso Electric seeks NM rate increase and new Large Load tariffs for big customers No. 25-00082-UT · OpenEl Paso Electric asked the New Mexico Public Regulation Commission for a net base rate increase of $70.5 million. Its amended application includes two new Large Load tariff schedules, and a public evidentiary hearing is scheduled for December 9 through December 22.General rate caseMar 27, 2026n/a0
PNM seeks approval of amended data center power contract with Greater Kudu, plus three power deals No. 25-00048-UT · DecidedPNM asked the New Mexico commission to approve an amended special service contract with Greater Kudu LLC, three purchased power agreements and three energy storage agreements to serve an expanding data center, along with amended Rate 36B and Riders 47 and 49. The case was on the commission's December 18, 2025 consent agenda.Contract with a large customern/an/a0

Nevada

CaseWhat it isKindOpenedLatest filingFilings
NV Energy proposes Large Load Electric Service Agreement for data centers and other big users No. 26-05029NV Energy has proposed a Large Load Electric Service Agreement for customers, such as data centers, whose energy needs typically exceed 25 megawatts. Those customers must make long-term commitments, pay minimum usage levels and provide financial guarantees.Contract with a large customern/an/a0
NV Energy asks Nevada PUC to approve standard large-load electric service agreement in its resource plan No. 26-05007 · OpenNevada Power and Sierra Pacific (NV Energy) ask the Nevada commission to approve a form Large Load Electric Service Agreement for customers with at least 25 MW, and to approve Exemplar Clean Transition Tariffs pricing models. The agreement sets minimum billing, termination and security terms meant to protect existing customers.Rates and terms for large usersn/an/a0

Ohio

CaseWhat it isKindOpenedLatest filingFilings
PUCO orders AEP Ohio to procure separate default-service energy for data centers returning to SSO No. 26-113-EL-ATA · DecidedThe Public Utilities Commission of Ohio issued an order directing AEP Ohio to protect other customers from data center effects on energy prices. Data centers must give 180-day notice before returning to the Standard Service Offer, and their energy will be bought separately, with the entire cost assigned to them.Rates and terms for large usersn/an/a0
PUCO orders AEP Ohio to file a data center tariff, adopting the utility's settlement No. 24-508-EL-ATA · DecidedAEP Ohio applied on May 14, 2024 for new tariffs for data center customers. The Public Utilities Commission of Ohio adopted the settlement signed by AEP Ohio, staff, Ohio Consumers' Counsel and others, and ordered AEP Ohio to file updated tariffs.Rates and terms for large usersMay 14, 2024n/a0

Oklahoma

CaseWhat it isKindOpenedLatest filingFilings
OG&E asks Oklahoma regulators to approve new Extra Large Power and Light tariff for large-load customers No. PUD2026-000046 · OpenOklahoma Gas and Electric applied for a new Extra Large Power and Light tariff and service terms for customers of 75 MW or more, plus a regulatory asset for portfolio optimization software. Its testimony proposes a 15-year minimum service term, billing minimums and a Customer Affordability Charge.Rates and terms for large usersJun 17, 2026n/a0
PSO rate case: large load tariff for customers over 75 MW, utility plan vs. stipulation No. PUD 2025-000075Public Service Company of Oklahoma proposed a Large Load Power tariff for customers of 75 MW or more. A non-unanimous stipulation filed June 26, 2026 by commission staff, Google and others proposes a separate large load tariff for demand over 75 MW, which PSO opposed.General rate casen/an/a0

Pennsylvania

CaseWhat it isKindOpenedLatest filingFilings
Pennsylvania PUC technical conference on cost allocation for large computational loads No. M-2026-3065062 · OpenVice Chair Barrow moved on 9/10/26 for the Pennsylvania PUC to host a technical conference on large computational load cost allocation. The docket will take initial and reply comments after the conference; a secretarial letter postponing the conference was posted 10/28/2026.OtherSep 10, 2026n/a0
Pennsylvania PUC adopts model tariff for customers with large loads of 50 MW or more No. M-2025-3054271 · DecidedThe Pennsylvania Public Utility Commission adopted a model tariff for customers with load at or over 50 MW individually or 100 MW in the aggregate. It covers contract terms, minimum demand charges and collateral, and applies to new large load interconnections.Commission rules or inquiryApr 12, 2025n/a0

Wisconsin

CaseWhat it isKindOpenedLatest filingFilings
Alliant Energy data center service agreement in Beaver Dam; PSC modifies it, orders large load tariff No. 6680-TE-115 · DecidedAlliant Energy applied in April 2025 for approval of an Electric Service Agreement to serve one data center in Beaver Dam under its Individual Contract Rate tariff. The Commission modified the agreement and ordered Alliant to file a stand-alone large load tariff for future data center customers.Contract with a large customern/an/a0
We Energies' very large customer tariff for data centers: Wisconsin PSC modifies and decides No. 6630-TE-113 · DecidedWe Energies applied in March 2025 for Very Large Customer and Bespoke Resources Tariffs after large data center customers entered its service territory. At its April 24, 2026 open meeting, the commission issued a decision making major modifications to the tariff; the final order was not yet posted.Rates and terms for large usersn/an/a0

Delaware

CaseWhat it isKindOpenedLatest filingFilings
Delmarva Power large load tariff for customers using 25 MW or more, ordered by Delaware PSC No. 25-0826 · OpenCommission Staff and the Division of the Public Advocate asked for a docket on a large load tariff for customers using a monthly maximum demand of 25 MW or greater. Delmarva filed a proposed tariff on December 19, 2025; a hearing examiner is gathering the record, and the Commission may approve or reject it.Rates and terms for large usersn/an/a0

Iowa

CaseWhat it isKindOpenedLatest filingFilings
MidAmerican Energy proposes Iowa Large Load Service Schedule and Rider IRR tariffs No. TF-2026-0091 · OpenMidAmerican Energy has a pending Iowa electric tariff filing to implement new tariffs for a Large Load Service Schedule and Rider IRR – Incremental Resources Recovery. The utility's list shows a proposed effective date of 02/01/2027.Rates and terms for large usersn/an/a0

Kansas

CaseWhat it isKindOpenedLatest filingFilings
Evergy Kansas large load (75 MW+) power service tariff approved by KCC via settlement No. 25-EKME-315-TAR · DecidedEvergy filed on February 11, 2025 for a Large Load Power Service rate plan for customers of 75 MW or more, including data centers. The parties filed a unanimous settlement, and the Kansas Corporation Commission approved it on November 6, 2025.Rates and terms for large usersFeb 11, 2025n/a0

Mississippi

CaseWhat it isKindOpenedLatest filingFilings
Mississippi Legislature: large customer electric agreements need no Public Service Commission approval No. SB 2001 (2024 Second Extraordinary Session), Section 22Section 22 of the Mississippi act lets a public utility sign a "large customer supply and service agreement" with a customer that has a qualifying project. It says the commission need not approve the agreement and cannot alter or cancel its pricing or charges during its term.Othern/an/a0

New Jersey

CaseWhat it isKindOpenedLatest filingFilings
NJ BPU seeks input on rules for large data center electricity tariffs under Data Center Fair Share Act No. EO26080463 · OpenNew Jersey Board of Public Utilities staff issued a request for information and a November 4, 2026 stakeholder meeting on requirements for utilities to file tariffs for large data center customers. The Data Center Fair Share Act requires the Board to set standards within 12 months, then each utility must petition for a rate class.Commission rules or inquiryn/an/a0

New York

CaseWhat it isKindOpenedLatest filingFilings
NY PSC opens proceeding on grid connection rules and costs for large loads like data centers No. 26-E-0045 · OpenOn February 12, 2026, the New York Public Service Commission opened a proceeding on its own motion to address interconnection reforms for large loads such as data centers. The order follows the Governor's Energize NY Development initiative and asks for comments.Connecting to the gridFeb 12, 2026n/a0

South Dakota

CaseWhat it isKindOpenedLatest filingFilings
Otter Tail Power asks SD PUC to create very large customer class and data center rate schedule No. EL26-021 · OpenOtter Tail Power Company asked the South Dakota Public Utilities Commission to divide its Large General Service class into tiers and add a Tier III High Power Compute rate schedule for customers with at least 75 MW of firm load. The commission's docket page lists the case as pending.Rates and terms for large usersJul 27, 2026n/a0

Washington

CaseWhat it isKindOpenedLatest filingFilings
Washington UTC policy statement on how electric utilities serve large loads like data centers No. UE-260162 · OpenThe Washington commission opened a docket in April 2026 to develop a policy statement on how investor-owned electric utilities connect large loads, including data centers. A draft policy statement says utilities should create a separate large load customer class, using a 50 MW threshold.Commission rules or inquiryMar 16, 2026n/a0

West Virginia

CaseWhat it isKindOpenedLatest filingFilings
Appalachian Power and Wheeling Power large-load tariff terms for 100 MW+ customers approved No. 24-0611-E-T-PW · DecidedAppalachian Power and Wheeling Power asked to add special terms for very large customers to their Schedules LCP and IP, first applying to customers over 200 MW. A settlement lowered the threshold to 100 MW at one site or 150 MW aggregated and set a mandatory contract term of not less than 12 years.Rates and terms for large usersJul 18, 2024n/a0

Wyoming

CaseWhat it isKindOpenedLatest filingFilings
Black Hills Energy (Cheyenne Light) asks Wyoming PSC for a large-customer transmission cost charge No. 20003-273-EM-26 · OpenCheyenne Light, Fuel and Power, doing business as Black Hills Energy, applied to the Wyoming Public Service Commission to implement a Large Customer Transmission Cost Adjustment Mechanism tariff. It also asks to change its Base TCAM, LPCS and BCIS tariffs.Rates and terms for large usersn/an/a0

Latest filings

FiledWho filedWhat was filed, and in which case
Nov 23, 2026PUC LEGALCOMMISSION STAFF’S RECOMMENDATION ON SUFFICIENCY OF NOTICE AND PROPOSED PROCEDURAL SCHEDULETexas · Southwestern Public Service Co. asks Texas PUC to approve large load customer tariff provisions
Nov 23, 2026PUC OPDMORDER NO. 6 - ESTABLISHING DEADLINE FOR PROPOSED PROCEDURAL SCHEDULE AND DISCOVERY PARAMETERS AND SCHEDULING PREHEARING CONFERENCETexas · Medina County Power appeals ERCOT decisions in "Batch Zero" large-load complaint cases
Nov 23, 2026PUC OPDMORDER NO. 5 - ESTABLISHING DEADLINE FOR PROPOSED PROCEDURAL SCHEDULE AND DISCOVERY PARAMETERS AND SCHEDULING PREHEARING CONFERENCETexas · Rowan Stampede LLC complaint against ERCOT, one of the "Batch Zero" large-load complaints
Nov 23, 2026PUC OPDMORDER NO. 3 - ESTABLISHING DEADLINE FOR PROPOSED PROCEDURAL SCHEDULE AND DISCOVERY PARAMETERS AND SCHEDULING PREHEARING CONFERENCETexas · Skybox Datacenters complaint against ERCOT over reclassification of its large-load project BZ-465
Nov 20, 2026SOUTHWESTERN PUBLIC SERVICE COMPANYSouthwestern Public Service Company’s First Supplemental Response to Texas Industrial Energy Consumers’ First Request for Information Question No. 1-5 and 1-27(A)Texas · Southwestern Public Service Co. asks Texas PUC to approve large load customer tariff provisions
Nov 20, 2026Sulphur Springs Valley Electric Cooperative, Inc. and 5 othersDocument FiledArizona · Six Arizona co-ops seek streamlined process for large-load electric service agreements
Nov 20, 2026Georgia Power CompanyDKT 44280 STF-PIA-48 Data Request ResponsesGeorgia · Georgia Power large-load contract filings and review within its 2022 rate case
Nov 19, 2026ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S LIST OF ISSUES FOR BATCH ZERO COMPLAINTSTexas · Medina County Power appeals ERCOT decisions in "Batch Zero" large-load complaint cases
Nov 19, 2026PUC MARKET ANALYSISCommission Staff's List of IssuesTexas · Medina County Power appeals ERCOT decisions in "Batch Zero" large-load complaint cases
Nov 19, 2026ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S LIST OF ISSUES FOR BATCH ZERO COMPLAINTSTexas · Rowan Stampede LLC complaint against ERCOT, one of the "Batch Zero" large-load complaints
Nov 19, 2026PUC MARKET ANALYSISCommission Staff's List of IssuesTexas · Rowan Stampede LLC complaint against ERCOT, one of the "Batch Zero" large-load complaints
Nov 19, 2026ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S LIST OF ISSUES FOR BATCH ZERO COMPLAINTSTexas · Mesquite H2 appeals ERCOT decisions; one of the "Batch Zero" large-load complaint dockets

Filings whose own description or filer names data centers or large loads, plus every filing in cases that are wholly about them. A filing is one party's submission, not a decision.

How we track them

  • Cases come from two places. In Texas, Virginia, Arizona and Georgia we read the commission's docket system through the day, so those cases show their latest filings. In other states, cases were compiled from the commission's and the utility's own documents and are checked again from time to time; they show no filing list. The list is not complete.
  • Every term in the comparison table is copied from an order, a tariff, an application or a statute, and a program confirmed the quoted words are in that document before the figure was listed. Hover over a figure to see the words; the link goes to the document.
  • A case is listed when a filing in it names data centers or large loads and the case, or a distinct part of it, is about very large electricity users: their rates and terms, a contract with one, how they connect to the grid, or the plants and lines built to serve them.
  • The plain title and summary of each case are written by an AI model from the docket's own title and list of filings. Code confirms a quoted clause against that list, and a second model checks the entry. We do not read every document in a case.
  • A filing is one party's submission. It shows what was asked for or argued, not what the commission decided. Nothing here says who is right or what any case will cost a customer.
  • A general rate case can run to hundreds of filings, most of them about other things. For those we list the case and point to the filings that name large loads.
  • Documents are on each commission's own system; every filing links there.
Full methodology