Duke Energy Progress SC rate case: large load stipulation on new 50 MW+ customers approved

Public Service Commission of South Carolina · No. 2025-154-E · Updated Nov 23, 2026, 18:37 ET
StateSouth Carolina
Kind of caseGeneral rate case
OpenedMay 13, 2025
Latest filingn/a

What the case is

Reskill Report summary · the commission lists the case as decided

In Duke Energy Progress's South Carolina rate case, parties signed a Large Load Stipulation agreeing to petition for a generic docket on new large loads of 50 MW or greater. The Commission's order approved that stipulation in its entirety.

From the docket: “evaluating issues associated with new large load (50 MW or greater) additions including existing”

Official title: Application of Duke Energy Progress, LLC for Increase in Electric Rates, Adjustments in Electric Rate Schedules and Tariffs, and Request for an Accounting Order

What the commission decided

Order No. 2025-757 (December 12, 2025) found the Large Load Stipulation just and reasonable, in the public interest and lawful, and approved it in its entirety. · Dec 12, 2025

Terms for large users, as approved

TermWhat it saysThe document's words
Counts as a large user at50 MW“evaluating issues associated with new large load (50 MW or greater) additions including existing” Source
AlsoPetition to open the generic large load docket due no later than June 1, 2026“Petition to open this generic docket shall be filed no later than June 1, 2026.” Source

Who is taking part

South Carolina Department of Consumer Affairs; South Carolina Coastal Conservation League; Southern Alliance for Clean Energy; Upstate Forever; Vote Solar; Sierra Club; South Carolina Small Business Chamber of Commerce; South Carolina Office of Regulatory Staff.

Source

  • This case was compiled from the Public Service Commission of South Carolina's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
  • Utility application: “evaluating issues associated with new large load (50 MW or greater) additions including existing”
  • Commission order: “Accordingly, the Large Load Stipulation is approved in its entirety.”
  • Docket page: “Application of Duke Energy Progress, LLC for Increase in Electric Rates, Adjustments in Electric Rate Schedules and Tariffs, and Request for an Accounting Order”
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
  • Nothing here says who is right or what the case will cost any customer.