Black Hills Energy (Cheyenne Light) asks Wyoming PSC for a large-customer transmission cost charge
Wyoming Public Service Commission · No. 20003-273-EM-26 · Updated Nov 23, 2026, 18:37 ETWhat the case is
Reskill Report summary · the commission lists the case as open
Cheyenne Light, Fuel and Power, doing business as Black Hills Energy, applied to the Wyoming Public Service Commission to implement a Large Customer Transmission Cost Adjustment Mechanism tariff. It also asks to change its Base TCAM, LPCS and BCIS tariffs.
From the docket: “requesting authority to implement a Large Customer Transmission Cost Adjustment Mechanism (LCTCAM) tariff and make changes to the Base TCAM, LPCS and BCIS tariffs.”
Official title: IN THE MATTER OF THE APPLICATION OF CHEYENNE LIGHT, FUEL AND POWER COMPANY d/b/a BLACK HILLS ENERGY TO ESTABLISH A LARGE CUSTOMER TRANSMISSION COST ADJUSTMENT MECHANISM AND TO AMEND ITS TRANSMISSION COST ADJUSTMENT MECHANISM TARIFF PROVISIONS, LARGE POWER CONTRACT SERVICE TARIFF, AND BLOCKCHAIN CUSTOMER INTERRUPTIBLE SERVICE TARIFF (SHEET NO. 33, 52, 53 & 55)
Terms for large users, as proposed
| Term | What it says | The document's words |
|---|---|---|
| Counts as a large user at | 5 MW | “interconnected with the Company’s system with expected capacity requirements of 5,000 kW or greater, in” Source |
| Also | LPCS customers must hold eligible capacity resources equal to 115% of their peak monthly load. | “to 115% of the Customer’s actual peak monthly load served under this Rate Schedule. The energy” Source |
Who is taking part
Wyoming Office of Consumer Advocate; Microsoft Corporation; Google LLC; Dyno Nobel, Inc.; Cheyenne Renewable Diesel Company LLC.
Source
- This case was compiled from the Wyoming Public Service Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Commission notice of application: “requesting authority to implement a Large Customer Transmission Cost Adjustment Mechanism (LCTCAM) tariff and make changes to the Base TCAM, LPCS and BCIS tariffs.”
- Commission notice of application: “20003-273-EM-26 (Record No. 18157)”
- Filed tariff (Wyo. P.S.C. Tariff No. 14, Rate Schedule LPCS): “This Rate Schedule is for large power users who are eligible for and are taking service under either the”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.