PSO rate case: large load tariff for customers over 75 MW, utility plan vs. stipulation
Oklahoma Corporation Commission · No. PUD 2025-000075 · Updated Nov 23, 2026, 18:37 ETWhat the case is
Reskill Report summary
Public Service Company of Oklahoma proposed a Large Load Power tariff for customers of 75 MW or more. A non-unanimous stipulation filed June 26, 2026 by commission staff, Google and others proposes a separate large load tariff for demand over 75 MW, which PSO opposed.
From the docket: “LPL tariff, eligible for customers with contract demand exceeding 75 MW at a single”
Official title: APPLICATION OF PUBLIC SERVICE COMPANY OF OKLAHOMA, AN OKLAHOMA CORPORATION, FOR AN ADJUSTMENT IN ITS RATES AND CHARGES AND THE ELECTRIC SERVICE RULES, REGULATIONS AND CONDITIONS OF SERVICE FOR ELECTRIC SERVICE IN THE STATE OF OKLAHOMA AND TO APPROVE VARIOUS COST RECOVERY MECHANISMS AND TARIFFS
Terms for large users, as proposed
Who is taking part
Public Utility Division, Oklahoma Corporation Commission; Oklahoma Attorney General; AARP; Oklahoma Industrial Energy Consumers; Walmart Inc.; The Petroleum Alliance of Oklahoma; Data Center Coalition; Google LLC.
Source
- This case was compiled from the Oklahoma Corporation Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Utility application: “LPL tariff, eligible for customers with contract demand exceeding 75 MW at a single”
- Utility application: “or greater than 75MW shall have an initial contract term of not less than ten (10) years”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.