Texas PUC petition to require data centers to report water use before grid connection (denied)
Public Utility Commission of Texas · No. 59824 · Updated Nov 23, 2026, 17:44 ETWhat the case is
Reskill Report summary
Margaret Elizabeth Hill and the Texas Residents and Ratepayers petitioned the Texas commission to change a rule so large data centers disclose water demand before connecting to the grid. Many members of the public filed comments in support, and Oncor filed comments opposing a proposed 50-megawatt large load threshold. On July 30, 2026, the commission issued an order denying the petition.
From the docket: “requiring large data centers to file a Water-Reliability Impact Statement before grid connection”
Official title: PETITION OF MARGARET ELIZABETH HILL AND THE TEXAS RESIDENTS AND RATEPAYERS FOR RULEMAKING TO AMEND 16 TEXAS ADMINISTRATIVE CODE § 22.281
Who is taking part
MARGARET ELIZABETH HILL AND THE TEXAS RESIDENTS AND RATEPAYERS; JIM SCOGGINS; Kimberly Weiland; Timothy Weiland; ONCOR ELECTRIC DELIVERY COMPANY LLC; Rillera; Rikki Weaver; Rachel Streater; Susan Waldron; Chelsea Burns.
Latest filings
The 60 most recent of 66 filings the docket shows. The 10 in bold name data centers or large loads in their own description.A filing is one party's submission, not a decision.
Source
- The filings and the official title are the Public Utility Commission of Texas's own records, read from its docket system.
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.