Reskill ReportTracking AI's effect on jobs, power and the law

Texas PUC petition to require data centers to report water use before grid connection (denied)

Public Utility Commission of Texas · No. 59824 · Updated Nov 23, 2026, 17:44 ET
StateTexas
Kind of caseCommission rules or inquiry
OpenedMay 29, 2026
Latest filingJul 30, 2026

What the case is

Reskill Report summary

Margaret Elizabeth Hill and the Texas Residents and Ratepayers petitioned the Texas commission to change a rule so large data centers disclose water demand before connecting to the grid. Many members of the public filed comments in support, and Oncor filed comments opposing a proposed 50-megawatt large load threshold. On July 30, 2026, the commission issued an order denying the petition.

From the docket: “requiring large data centers to file a Water-Reliability Impact Statement before grid connection”

Official title: PETITION OF MARGARET ELIZABETH HILL AND THE TEXAS RESIDENTS AND RATEPAYERS FOR RULEMAKING TO AMEND 16 TEXAS ADMINISTRATIVE CODE § 22.281

Who is taking part

MARGARET ELIZABETH HILL AND THE TEXAS RESIDENTS AND RATEPAYERS; JIM SCOGGINS; Kimberly Weiland; Timothy Weiland; ONCOR ELECTRIC DELIVERY COMPANY LLC; Rillera; Rikki Weaver; Rachel Streater; Susan Waldron; Chelsea Burns.

Latest filings

The 60 most recent of 66 filings the docket shows. The 10 in bold name data centers or large loads in their own description.A filing is one party's submission, not a decision.

FiledWho filedWhat was filed
Jul 30, 2026PUC OPDMORDER DENYING PETITION FOR RULEMAKING
Jul 24, 2026PUC RULES & PROJECTSOM Item No. 33 - (Staff Recommendation) Order Denying Petition For Rulemaking
Jul 14, 2026JIM SCOGGINSWaterfront property owner on Cedar Creek Lake in Trinidad, Texas. I'm writing in strong support of the petition in Project No. 59824, which would require large data centers to disclose their water demand before connecting to the grid.
Jul 14, 2026Jim ScogginsLetter
Jul 13, 2026ONCOR ELECTRIC DELIVERY COMPANY LLCONCOR ELECTRIC DELIVERY COMPANY'S COMMENTS OPPOSING PROPOSED 50-MEGAWATT LARGE LOAD ELIGIBILITY THRESHOLD
Jul 13, 2026RilleraI strongly support the petition in Project 59824. ECROT needs approval from the TWBD before a data center in Texas is established. A temporary infrastructure moratorium is needed in Texas counties until mandatory standards are law. Protect Texas.
Jul 9, 2026Rikki Weaversupport the petition in Project No. 59824 requiring large data centers to file a Water-Reliability Impact Statement before grid connection
Jul 8, 2026Rachel StreaterI strongly support the petition in Project No. 59824. Revealed in the June 23rd House hearing, over 80% of data centers operate in secrecy, refusing to report water metrics. Protect TX resources by requiring ERCOT to work with TWDB before approvals.
Jul 7, 2026Susan WaldronComment of support
Jul 4, 2026Chelsea BurnsComment of Support
Jul 1, 2026hallye StubblefieldComment of support
Jun 30, 2026Steven BradyPublic comment
Jun 30, 2026Stepheny IsbellComment of support
Jun 30, 2026Jenny InzerilloComment of support.
Jun 30, 2026HazikComment of support
Jun 30, 2026Kimberly GreenfieldComment
Jun 30, 2026Tonya KleuskensComment of Support
Jun 30, 2026Stacy CliftonComment of support
Jun 30, 2026Rebecca GibbsComment of support
Jun 29, 2026Cheryl ShaddenComments supporting
Jun 29, 2026Luis LaraComment of support.
Jun 29, 2026Gerald GalvinComment of support.
Jun 29, 2026Frank McClainComment of support
Jun 29, 2026Daniel S. CantuComment of Support
Jun 29, 2026Ashlyn MajorComment in support.
Jun 28, 2026Hamlet PegueroRequire Water Accountability Before Approving Data Center Growth
Jun 28, 2026MitchellComment of Support
Jun 28, 2026EileenNo New Water Hogging Datacenters AND Existing Datacenters Must Report Actual Water Usage on a Monthly Basis
Jun 28, 2026Steven GuessComments of support
Jun 27, 2026Shawna WhalenI strongly support the petition in Project No. 59824.
Jun 27, 2026Carole MannyComment of support.
Jun 27, 2026Suzanne GentlingComment of support
Jun 27, 2026Christina JettComment of support
Jun 27, 2026Horace JettComment of Support
Jun 26, 2026Tom BickComment of Support
Jun 26, 2026Kimberly WeilandComment of support
Jun 26, 2026Timothy WeilandComment of support
Jun 26, 2026Kimberly Weilandcomment of support
Jun 26, 2026Timothy Weilandcomment of support
Jun 26, 2026JlawlessNeed to regulate data centers and require water reporting to protect citizens and resources of Texas.
Jun 26, 2026BRIAN FLYNTProject No 59824 Comment of Support
Jun 26, 2026Amy FlyntProject NO 59824 Comment of Support
Jun 26, 2026CONCERNED CITIZENRegarding data centers be required to report all water usage
Jun 26, 2026Lisa LewisComment of support
Jun 26, 2026Amy ReidProject No. 59824 Comment of Support
Jun 26, 2026Samantha BozemanComment of support
Jun 26, 2026Max/Sandra ReedComment of Support
Jun 26, 2026Georgina HidalgoI strongly support petition Project No. 59824. As revealed in the June 23rd House hearing, 80%+ of data centers operate in total secrecy, refusing to report water metrics. The PUCT must stop letting ERCOT approve massive grid connections in isolation.
Jun 26, 2026Gilbert CumberledgeComment of support
Jun 26, 2026Lee Ann LynnI strongly support the petition in Project No. 59824.
Jun 25, 2026Miriam CobbLetter of Support
Jun 25, 2026Teresa DillonComment of support
Jun 25, 2026Dillard LeedsComment of support
Jun 25, 2026Taylor BallesterosComment of support
Jun 25, 2026Jamie StanfordComment of Support I strongly support the petition in Project No. 59824
Jun 25, 2026LAURA CRAWFORDComment in Support
Jun 25, 2026Brandy DebenportComment of support
Jun 25, 2026Chad WeltyComment of support
Jun 25, 2026Roger FrazierComments regarding water usage and data centers
Jun 25, 2026Alis StinsonComment of support for petition in Project No. 59824.

Source

  • The filings and the official title are the Public Utility Commission of Texas's own records, read from its docket system.
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
  • Nothing here says who is right or what the case will cost any customer.