California Public Utilities Commission · No. R.26-04-009 · Updated Nov 23, 2026, 18:37 ETWhat the case is
Reskill Report summary · the commission lists the case as open
The California Public Utilities Commission opened a rulemaking on April 9, 2026 to consider advanced electric rate design. A Sept. 22, 2026 scoping memo sets Track 1 to ask whether to create data center rate design, including a separate customer class, new rates, exit fees, and protections against cost shifts and stranded costs.
From the docket: “Track 1: Data Center Tariffs and Customer Protections”
Official title: Order Instituting Rulemaking on California Advanced Electric Rate Design.
Who is taking part
Data Center Coalition; Google LLC; Equinix, Inc.; California Large Energy Consumers Association; California Coalition of Large Energy Users; Public Advocates Office at the California Public Utilities Commission; The Utility Reform Network; Industrious Labs.
Source
- This case was compiled from the California Public Utilities Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Commission order (Assigned Commissioner's Scoping Memo and Ruling, Sept. 22, 202: “Track 1: Data Center Tariffs and Customer Protections”
- Commission order (scoping memo, procedural background): “On April 9, 2026, the Commission opened this rulemaking (R.) 26-04-009 to”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.