Dominion Virginia asks approval of Rider T1 rate adjustment clause; data center issues argued

Virginia State Corporation Commission · No. PUR-2026-00056 · Updated Nov 23, 2026, 17:44 ET
StateVirginia
Kind of caseRates and terms for large users
OpenedJul 9, 2026
Latest filingNov 17, 2026

What the case is

Reskill Report summary · the commission lists the case as under appeal

Dominion asked the Virginia SCC to approve a rate adjustment clause, Rider T1. Microsoft, Amazon Data Services, Google, Commission Staff and others took part, and exhibits address data center projects. After a July hearing, the Commission issued a final order on 07/31/2026 and Dominion filed a revised tariff. Microsoft appealed, then withdrew the appeal on 11/17/2026.

From the docket: “Comparison of "But For" Data Center Projects”

Official title: Virginia Electric and Power Company - For approval of a rate adjustment clause Rider T 1 pursuant to § 56-585.1 A 4 of the Code of Virginia

Latest filings

The 60 most recent of 146 filings the docket shows. The 1 in bold name data centers or large loads in their own description.A filing is one party's submission, not a decision.

FiledWho filedWhat was filed
Nov 17, 2026not statedMicrosoft Corporation - Withdrawal of Notice of Appeal
Oct 22, 2026not statedVirginia Electric and Power Company - Response to the Motion of Old Dominion Electric Cooperative
Oct 14, 2026not statedTheresa Ghiorzi - Notice of Withdrawal of Federico J. Zablah as counsel
Oct 1, 2026not statedOld Dominion Electric Cooperative - Motion to be Named a Party to Coordinated Efforts Directed in Final Order with Request for Expedited Treatment
Aug 28, 2026not statedMicrosoft Corporation - Notice of Appeal
Aug 26, 2026not statedMicrosoft Corporation - Notice of Withdrawal of Catherine L. Chapman as Counsel
Aug 25, 2026not statedVirginia Committee For Fair Utility Rates - Notice of Withdrawal of Shianne R. Randolph as Counsel.
Aug 12, 2026not statedVirginia Electric and Power Company - Staff letter acknowledging receipt of Company's Revised Rider T1 tariff, filed 07/31/2026 effective for usage on and after 09/01/2026.
Aug 11, 2026not statedVirginia Electric and Power Company - Rider T1 tariff sheet and supporting workpapers effective for usage on and after 09/01/2026
Jul 31, 2026not statedVirginia Electric and Power Company - Final Order - 07/31/2026.
Jul 29, 2026not statedVirginia Electric and Power Company - Min-u-script of Hearing - Day 3 - 07/16/2026 from 10:00 A.M. to 4:29 P.M. (Part 2 of 2)
Jul 29, 2026not statedVirginia Electric and Power Company - Transcript and Word Index of Hearing - Day 3 - 07/16/2026 from 10:00 A.M. to 4:29 P.M. (Part 1 of 2)
Jul 28, 2026not statedVirginia Electric and Power Company - Memorandum attaching a letter submitted to the Commission for consideration by Delegate Garrette McGuire.
Jul 27, 2026not statedVirginia Electric and Power Company - Min-u-script of Hearing - Day 2 - 07/15/2026 from 10:00 A.M. to 5:17 P.M. (Part 2 of 2)
Jul 27, 2026not statedVirginia Electric and Power Company - Transcript and Word Index of Hearing - Day 2 - 07/15/2026 from 10:00 A.M. to 5:17 P.M. (Part 1 of 2)
Jul 24, 2026not statedVirginia Electric and Power Company - Case heard on 07/14/2026-07/16/2026 before the Honorable Commissioner Kelsey A. Bagot, Chairman, PRESIDING; Appearances: J. K. Reid, III, J.D. Ray, B. M. Jackson, and D. J, DePippo, Counsel for
Jul 22, 2026not statedVirginia Electric and Power Company - Min-u-script of Hearing - Day 1 - 07/14/2026 from 10:00 A.M. to 5:21 P.M. (Part 2 of 2)
Jul 22, 2026not statedVirginia Electric and Power Company - Transcript and Word Index of Hearing - Day 1 - 07/14/2026 from 10:00 A.M. to 5:21 P.M. (Part 1 of 2)
Jul 20, 2026not statedAppalachian Voices - Letter in lieu of post-hearing brief in response to Commissioner Bagot's Request.
Jul 20, 2026not statedMicrosoft - Response to Judge Bagot's questions.
Jul 20, 2026not statedOld Dominion Electric Cooperative - Post-Hearing Brief.
Jul 20, 2026not statedVirginia Electric and Power Company - Post-Hearing Brief.
Jul 20, 2026not statedAmazon Data Services, Inc. - Letter in response to Commissioner Bagot's Request.
Jul 20, 2026not statedPiedmont Environmental Council - Letter in response to Commissioner Bagot's Request.
Jul 20, 2026not statedVirginia Committee for Fair Utility Rates - Letter in response to Commissioner Bagot's Request.
Jul 17, 2026not statedVirginia Electric and Power Company - Exhibit 29 – Late Filed Exhibit: 2021 Typical Bill for a Residential Customer using 1,000 kWh per month.
Jul 16, 2026not statedVirginia Electric and Power Company - Exhibit 28 – Rebuttal Testimony of William J. Caffall on behalf of Virginia Electric and Power Company, filed with the Commission on 06/30/2026.
Jul 16, 2026not statedVirginia Electric and Power Company - Exhibit 27 – Rebuttal Testimony of Robert E. Miller on behalf of Virginia Electric and Power Company, filed with the Commission on 06/30/2026.
Jul 16, 2026not statedVirginia Electric and Power Company - Exhibit 26 – Rebuttal Testimony of Ryen N. Lawson on behalf of Virginia Electric and Power Company, filed with the Commission on 06/30/2026.
Jul 16, 2026not statedVirginia Electric and Power Company - Exhibit 25 – Rebuttal Testimony of M. Robert Hines on behalf of Virginia Electric and Power Company, filed with the Commission on 06/30/2026.
Jul 16, 2026not statedVirginia Electric and Power Company - Memorandum attaching a letter submitted to the Commission for consideration by numerous members of the Virginia General Assembly.
Jul 15, 2026not statedVirginia Electric and Power Company - Exhibit 24 – Prefiled Testimony of Brian S. Pratt on behalf of Commission Staff, filed with the Commission on 06/16/2026.
Jul 15, 2026not statedVirginia Electric and Power Company - Exhibit 23 – Comparison of "But For" Data Center Projects.
Jul 15, 2026not statedVirginia Electric and Power Company - Exhibit 22 – Dominion Cases since 2021 Table.
Jul 15, 2026not statedVirginia Electric and Power Company - Exhibit 21 – Prefiled Testimony of Neil Joshipura on behalf of Commission Staff, filed with the Commission on 06/16/2026.
Jul 15, 2026not statedVirginia Electric and Power Company - Exhibit 20 – Prefiled Testimony of Gabriel N. Knight on behalf of Commission Staff, filed with the Commission on 06/16/2026.
Jul 15, 2026not statedVirginia Electric and Power Company - Exhibit 19 – Prefiled Testimony of Patrick W. Carr on behalf of Commission Staff, filed with the Commission on 06/16/2026.
Jul 15, 2026not statedVirginia Electric and Power Company - Exhibit 18 – Direct Testimony of Carolyn A. Berry, Ph.D. on behalf of Google, LLC, filed with the Commission on 06/11/2026.
Jul 15, 2026not statedVirginia Electric and Power Company - Exhibit 17 – Direct Testimony of Ron Nelson on behalf of the Sierra Club and the Natural Resources Defense Council, filed with the Commission on 06/11/2026.
Jul 15, 2026not statedVirginia Electric and Power Company - Exhibit 16 – Proposed Gross Revenue MDO Comparison Spreadsheet.
Jul 15, 2026not statedVirginia Electric and Power Company - Exhibit 15 – Direct Testimony of Cameron Brooks on behalf of Amazon Data Services, Inc., filed with the Commission on 06/11/2026.
Jul 14, 2026not statedVirginia Electric and Power Company - Exhibit 4 – Direct Testimony of David M. Wilkinson on behalf of Virginia Electric and Power Company, filed with the Commission on 05/01/2026.
Jul 14, 2026not statedVirginia Electric and Power Company - Exhibit 14 – Direct Testimony of Gregory Abbott on behalf of Piedmont Environmental Council, filed with the Commission on 06/11/2026.
Jul 14, 2026not statedVirginia Electric and Power Company - Exhibit 13 – Direct Testimony of Kevin C. Miller on behalf of Old Dominion Electric Cooperative, filed with the Commission on 06/11/2026.
Jul 14, 2026not statedVirginia Electric and Power Company - Exhibit 12 – Direct Testimony of Kevin J. Mara on behalf of Old Dominion Electric Cooperative, filed with the Commission on 06/11/2026.
Jul 14, 2026not statedVirginia Electric and Power Company - Exhibit 11 – Direct Testimony of Eric R. Dembek on behalf of Old Dominion Electric Cooperative, filed with the Commission on 06/11/2026, errata filed 07/09/2026.
Jul 14, 2026not statedVirginia Electric and Power Company - Exhibit 10 – Direct Testimony of Michael Goggin on behalf of Appalachian Voices, filed with the Commission on 06/11/2026.
Jul 14, 2026not statedVirginia Electric and Power Company - Exhibit 9 – Direct Testimony of Brian C. Collins on behalf of the Virginia Committee for Fair Utility Rates, filed with the Commission on 06/11/2026.
Jul 14, 2026not statedVirginia Electric and Power Company - Exhibit 8 – Direct Testimony of Robert E. Miller in Docket No. E-22, Sub 765.
Jul 14, 2026not statedVirginia Electric and Power Company - Exhibit 7 – Direct Testimony of Robert E. Miller on behalf of Virginia Electric and Power Company, filed with the Commission on 05/01/2026.
Jul 14, 2026not statedVirginia Electric and Power Company - Exhibit 6 – Direct Testimony of William J. Caffall on behalf of Virginia Electric and Power Company, filed with the Commission on 05/01/2026.
Jul 14, 2026not statedVirginia Electric and Power Company - Exhibit 5 – Direct Testimony of Ryen N. Lawson on behalf of Virginia Electric and Power Company, filed with the Commission on 05/01/2026, as corrected during Proceeding.
Jul 14, 2026not statedVirginia Electric and Power Company - Exhibit 3 – Direct Testimony of M. Robert Hines on behalf of Virginia Electric and Power Company, filed with the Commission on 05/01/2026.
Jul 14, 2026not statedVirginia Electric and Power Company - Exhibit 2 – Application and Filing Schedules 46A, 46B, and 46C of Virginia Electric and Power Company, filed with the Commission on 05/01/2026.
Jul 14, 2026not statedVirginia Electric and Power Company - Exhibit 1 – Proof of Notice and Service, filed with the Commission on 06/03/2026.
Jul 13, 2026not statedVirginia Electric and Power Company - Memorandum attaching a comment submitted to the Commission for consideration by Josephus Allmond, Chief Energy Officer, Office of the Governor of Virginia.
Jul 10, 2026not statedVirginia Electric and Power Company - Memorandum attaching 47 comments submitted to the Commission for consideration by Lisa Taylor, Rafael Scharan, Pamela Foltz, et al.
Jul 10, 2026not statedVirginia Electric and Power Company - Memorandum attaching a comment submitted to the Commission for consideration by Donald Matlock and Jeremy Mauck.
Jul 10, 2026not statedVirginia Electric and Power Company - Order on Motion - 07/10/2026.
Jul 9, 2026not statedVirginia Electric and Power Company - Memorandum attaching 29 comments submitted to the Commission for consideration by Fauquier County, Lisa Raper, Marcia Fuqua, et al.

Source

  • The filings and the official title are the Virginia State Corporation Commission's own records, read from its docket system.
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
  • Nothing here says who is right or what the case will cost any customer.