Dominion Virginia asks approval of Rider T1 rate adjustment clause; data center issues argued
Virginia State Corporation Commission · No. PUR-2026-00056 · Updated Nov 23, 2026, 17:44 ETWhat the case is
Reskill Report summary · the commission lists the case as under appeal
Dominion asked the Virginia SCC to approve a rate adjustment clause, Rider T1. Microsoft, Amazon Data Services, Google, Commission Staff and others took part, and exhibits address data center projects. After a July hearing, the Commission issued a final order on 07/31/2026 and Dominion filed a revised tariff. Microsoft appealed, then withdrew the appeal on 11/17/2026.
From the docket: “Comparison of "But For" Data Center Projects”
Official title: Virginia Electric and Power Company - For approval of a rate adjustment clause Rider T 1 pursuant to § 56-585.1 A 4 of the Code of Virginia
Latest filings
The 60 most recent of 146 filings the docket shows. The 1 in bold name data centers or large loads in their own description.A filing is one party's submission, not a decision.
Source
- The filings and the official title are the Virginia State Corporation Commission's own records, read from its docket system.
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.