Reskill ReportTracking AI's effect on jobs, power and the law

Alabama law on Public Service Commission review of large data center electric contracts (SB270)

Alabama Legislature · No. SB270 (2026 Regular Session) / Act No. 2026-610 · Updated Nov 23, 2026, 18:37 ET
StateAlabama
Kind of caseOther
OpenedFeb 5, 2026
Latest filingn/a

What the case is

Reskill Report summary · the commission lists the case as decided

Alabama's SB270 adds Section 37-4-22.1 to the state code, setting how the Public Service Commission reviews retail electric contracts with large load data center customers, defined as expected total peak demand of 150 megawatts or greater. A contract is in the public interest if it recovers incremental costs and promotes positive benefits to other customers.

From the docket: “an expected total peak demand of 150 megawatts or greater at”

Official title: Electric Utilities; review by Public Service Commission of certain contracts with large load data centers further provided for

What the commission decided

SB270 was enacted as Act No. 2026-610, adding Section 37-4-22.1 to the Code of Alabama, effective October 1, 2026. · Apr 17, 2026

Terms for large users, as enacted in law

TermWhat it saysThe document's words
Counts as a large user at150 MW“an expected total peak demand of 150 megawatts or greater at” Source
AlsoContract terms the Commission weighs include minimum contract length, upfront payments and collateral.“matters such as minimum term for contract length, upfront” Source

Source

  • This case was compiled from the Alabama Legislature's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
  • Statute: “an expected total peak demand of 150 megawatts or greater at”
  • Statute: “matters such as minimum term for contract length, upfront”
  • Statute: “Section 2. This act shall become effective on October”
  • Statute: “4/17/2026 - Senate Enacted - 2026-610”
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
  • Nothing here says who is right or what the case will cost any customer.