East Kentucky Power Cooperative's Rate DCP data center tariff approved with changes

Kentucky Public Service Commission · No. 2025-00140 · Updated Nov 23, 2026, 18:37 ET
StateKentucky
Kind of caseRates and terms for large users
OpenedApr 30, 2025
Latest filingn/a

What the case is

Reskill Report summary · the commission lists the case as decided

East Kentucky Power Cooperative filed Rate DCP, a tariff setting terms for serving data centers of 15,000 kW or greater with a 60 percent or greater load factor, each under a special contract approved by the Commission. The Commission approved the tariff as modified.

From the docket: “EKPC’s Rate DCP tariff is approved, as modified in this Order”

Official title: ELECTRONIC TARIFF FILING OF EAST KENTUCKY POWER COOPERATIVE, INC. TO ESTABLISH A NEW TARIFF FOR DATA CENTER POWER

What the commission decided

The Commission approved EKPC's Rate DCP tariff as modified in the order, effective for service on and after the order date, required revised tariff sheets within 20 days, and closed the case.

Terms for large users, as approved

TermWhat it saysThe document's words
Counts as a large user at15 MW“15,000 kW or greater; (Load size test)” Source
Deposit or exit termsPrepayment deposit equal to a rolling two months of expected maximum monthly bills.“a rolling two-month period of expected maximum monthly bills” Source
AlsoLoads above 250 MW must be served with dedicated resources under a rider.“exceeding 250 MWs, one or more dedicated resources will be required as part of the” Source

Who is taking part

Nucor Steel Gallatin; Kentucky Attorney General, Office of Rate Intervention.

Source

  • This case was compiled from the Kentucky Public Service Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
  • Commission order: “EKPC’s Rate DCP tariff is approved, as modified in this Order”
  • Commission order: “15,000 kW or greater; (Load size test)”
  • Commission order: “a rolling two-month period of expected maximum monthly bills”
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.