Texas PUC rule on large loads net metering with existing power plants (new 16 TAC §25.205)

Public Utility Commission of Texas · No. 58479 · Updated Nov 23, 2026, 17:44 ET
StateTexas
Kind of caseCommission rules or inquiry
OpenedJul 31, 2025
Latest filingMar 26, 2026

What the case is

Reskill Report summary

The Public Utility Commission of Texas is writing a rule on net metering arrangements where a large load, such as a data center, is co-located with an existing power plant. Utilities, ERCOT, the Data Center Coalition, CyrusOne, Crusoe, Vistra, Calpine, Sierra Club and the Office of Public Utility Counsel filed comments. On 2026-03-26 the commission issued an order adopting new 16 TAC §25.205.

From the docket: “RULEMAKING FOR NET METERING ARRANGEMENTS INVOLVING A LARGE LOAD CO-LOCATED WITH AN EXISTING GENERATION RESOURCE UNDER PURA § 39.169”

Official title: RULEMAKING FOR NET METERING ARRANGEMENTS INVOLVING A LARGE LOAD CO-LOCATED WITH AN EXISTING GENERATION RESOURCE UNDER PURA § 39.169

Who is taking part

ERCOT; TCPA; OPUC; VISTRA CORP.; ONCOR ELECTRIC DELIVERY COMPANY LLC; RULES & PROJECTS; Conservative Texans for Energy Innovation; TPPA; CENTERPOINT ENERGY HOUSTON ELECTRIC; SIERRA CLUB.

Latest filings

The 60 most recent of 67 filings the docket shows. The 4 in bold name data centers or large loads in their own description.A filing is one party's submission, not a decision.

FiledWho filedWhat was filed
Mar 26, 2026PUC OPDMORDER ADOPTING NEW 16 TAC §25.205
Mar 26, 2026RULES & PROJECTSTexas Register Acknowledgement of Receipt-Proposal for Adoption
Mar 20, 2026VISTRA CORP.Vistra Corp.'s Comments on Planning Guide Revision Request 145
Mar 11, 2026PUC OPDMCHAIRMAN GLEESON MEMORANDUM
Mar 5, 2026PUC RULES & PROJECTSOM Item No. 43 - Staff Memo with Proposed Redline Changes
Feb 13, 2026PUC RULES & PROJECTSOM Item No. 26 - (Staff Recommendation) Order Adopting New §25.205
Oct 31, 2025TCPATCPA Reply Comments
Oct 31, 2025Conservative Texans for Energy InnovationCTEI Reply Comments on Proposed 16 TAC 25.505
Oct 31, 2025TPPATexas Public Power Association (TPPA) Reply Comments
Oct 31, 2025CENTERPOINT ENERGY HOUSTON ELECTRICREPLY COMMENTS OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC
Oct 31, 2025ONCOR ELECTRIC DELIVERY COMPANY LLCONCOR ELECTRIC DELIVERY’S REPLY COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205 AND ACCOMPANYING QUESTIONS
Oct 31, 2025VISTRA CORP.Vistra Reply Comments
Oct 31, 2025SIERRA CLUBReply Comments on Co-Location of Large Loads (58479)
Oct 31, 2025TEXAS ELECTRIC COOPERATIVES, INC.Comments of Texas Electric Cooperatives, Inc.
Oct 31, 2025Texas Solar+Storage AssociationReply Comments of TSSA
Oct 31, 2025TIECTEXAS INDUSTRIAL ENERGY CONSUMERS’ REPLY COMMENTS
Oct 31, 2025CALPINE CORPORATIONCALPINE CORPORATION’S REPLY COMMENTS ON COMMISSION STAFF’S PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.205
Oct 31, 2025TEXAS ADVANCED ENERGY BUSINESS ALLIANCETAEBA Project No. 58479 Reply Comments
Oct 31, 2025CRUSOE ENERGY SYSTEMS LLCCRUSOE ENERGY SYSTEMS LLC REPLY COMMENTS
Oct 31, 2025ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S REPLY COMMENTS REGARDING PROPOSED 16 TAC § 25.205
Oct 31, 2025TEXAS NEW MEXICO POWER COMPANYTexas-New Mexico Power Company’s Reply Comments Regarding Proposal for Publication
Oct 31, 2025OPUCOPUC’S REPLY COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205
Oct 31, 2025ENCHANTED ROCK, LLCENCHANTED ROCK, LLC REPLY COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205
Oct 31, 2025EOLIAN, L.P.Eolian's Reply Comments on Proposal for Publication
Oct 31, 2025Data Center Coalition (DCC)Data Center Coalition's Reply Comments
Oct 31, 2025CyrusOneCyrusOne Reply Comments on Project No 58479. RULEMAKING FOR NET METERING ARRANGEMENT INVOLVING A LARGE LOAD CO-LOCATED WITH AN EXISTING GENERATION RESOURCE UNDER PURA § 39.169
Oct 17, 2025SIERRA CLUBComments and responses to questions from the Sierra Club in Project 58479
Oct 17, 2025Splight Inc.SPLIGHT COMMENTS ON STAFF'S DRAFT DISCUSSION RULE § 25.205
Oct 17, 2025TPPATexas Public Power Association (TPPA) Comments on PFP
Oct 17, 2025Conservative Texans for Energy InnovationCTEI Initial Comments on Proposed 25 TAC 25.205
Oct 17, 2025TCPAVOID SEE ITEM 35
Oct 17, 2025TEXAS ADVANCED ENERGY BUSINESS ALLIANCEInitial Comments of the Texas Advanced Energy Business Alliance on Commission Staff's Draft Rule §25.205
Oct 17, 2025TIECTEXAS INDUSTRIAL ENERGY CONSUMERS’ PROPOSED COMMENTS TO DRAFT RULE 25.504
Oct 17, 2025SATOSHI ENERGY CORP.SATOSHI'S COMMENTS ON STAFF'S PROPOSAL FOR PUBLICATION
Oct 17, 2025EdgeConneXEDGECONNEX COMMENTS ON COMMISSION STAFF'S DRAFT RULE 16 TAC § 25.205
Oct 17, 2025CALPINE CORPORATIONCALPINE CORPORATION’S COMMENTS ON COMMISSION STAFF’S PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.205
Oct 17, 2025ONCOR ELECTRIC DELIVERY COMPANY LLCONCOR ELECTRIC DELIVERY’S COMMENTS ON THE PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205 AND ACCOMPANYING QUESTIONS
Oct 17, 2025OPUCOFFICE OF PUBLIC UTILITY COUNSEL’S INITIAL COMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205
Oct 17, 2025Texas Electric Cooperatives, Inc.Comments of Texas Electric Cooperatives, Inc.
Oct 17, 2025LOWER COLORADO RIVER AUTHORITY AND LCRA TRANSMISSION SERVICES CORPORATIONLCRA RESPONSE TO PFP
Oct 17, 2025VISTRA CORP.Vistra Corp.'s Comments
Oct 17, 2025TCPACORRECTION: RESPONSE TO STAFF QUESTIONS & RECOMMENDATIONS FOR PFP
Oct 17, 2025ELECTRIC TRANSMISSION TEXAS, LLCCOMMENTS ON PROPOSAL FOR PUBLICATION OF NEW 16 TAC § 25.505
Oct 17, 2025CENTERPOINT ENERGY HOUSTON ELECTRICCOMMENTS OF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC
Oct 17, 2025AEP TEXAS INC.AEP TEXAS’ COMMENTS ON PROPOSAL FOR PUBLICATION
Oct 17, 2025TCPAREQUEST TO VOID ITEM 20, FILED IN ERROR
Oct 17, 2025ERCOTELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.’S RESPONSES TO COMMISSION QUESTIONS AND COMMENTS REGARDING PROPOSED 16 TAC § 25.205
Oct 17, 2025EOLIAN, L.P.Eolian, L.P.'s Comments on the Proposal for Publication and Request for Hearing
Oct 17, 2025Data Center CoalitionData Center Coalition's Comments
Oct 17, 2025TEXAS- NEW MEXICO POWER COMPANYTexas-New Mexico Power Company’s Comments to Commission Staff’s Questions and Comments on Proposal For Publication
Oct 17, 2025Texas Solar+Storage AssociationComments of TSSA on Project 58479
Oct 17, 2025Onward Energy Holdings, LLCComments attached for Project 58497, Net Metering Arrangements
Sep 19, 2025RULES & PROJECTSTexas Register Acknowledgement of Receipt-Comments Due October 17, 2025
Sep 19, 2025ERCOTERCOT LETTER RE STAND-ALONE GENERATION RESOURCE LIST UPDATE
Sep 18, 2025ERCOTLETTER & PRESENTATION REGARDING ERCOT STUDIES OF PROPOSED NET METERING ARRANGEMENTS
Sep 18, 2025PUC OPDMPROPOSAL FOR PUBLICATION OF NEW 16 TAC §25.205
Sep 12, 2025PUC RULES & PROJECTSOM Item No. 9 - Staff Memo & PFP w/Oct. 17 Comment Deadline
Sep 10, 2025SATOSHI ENERGY CORP.SATOSHI ENERGY COMMENTS ON STAFF’S DRAFT DISCUSSION RULE § 25.205
Sep 5, 2025Crusoe Energy Systems, Inc.Crusoe's Comments on Staff's Draft Discussion Rule § 25.205
Sep 4, 2025ONCOR ELECTRIC DELIVERY COMPANY LLCONCOR'S COMMENTS ON STRANDED/UNDERUTILIZED ASSET COST TREATMENT

Source

  • The filings and the official title are the Public Utility Commission of Texas's own records, read from its docket system.
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
  • Nothing here says who is right or what the case will cost any customer.