Michigan approves Indiana Michigan Power's amended large load tariff for data centers
Michigan Public Service Commission · No. U-21986 · Updated Nov 23, 2026, 18:37 ETWhat the case is
Reskill Report summary · the commission lists the case as decided
The Michigan commission let Indiana Michigan Power amend its large load tariff for customers drawing 50 megawatts (MW) or more, including data centers. Amendments include a 15-year contract term, early termination fees and a 90% monthly minimum billing demand; I&M must propose a standalone large load rate in its next general rate case.
From the docket: “Case No. U-21986”
Official title: U-21986
What the commission decided
The commission approved the Tariff LP amendments and required I&M to propose a standalone large load rate, modeling six cost allocation and rate design models, in its next general rate case, plus an ex parte compliance filing before each new customer. · Aug 27, 2026
Terms for large users, as approved
| Term | What it says | The document's words |
|---|---|---|
| Counts as a large user at | 50 MW | “allow for large load customers drawing 50 megawatts (MW) or more of electricity” Source |
| Must pay for at least | 90% of contracted demand | “a 90% monthly minimum billing demand and 65% monthly minimum energy requirement” Source |
| Minimum contract | 15 years | “requiring a contract term of 15 years with a maximum 5-year period to ramp up to its full load” Source |
| Also | Four years' notice needed to cut contract capacity by more than 10 percent. | “requiring 4 years of notice if the customer plans to reduce capacity more than 10%” Source |
Who is taking part
Michigan Department of Attorney General; Association of Businesses Advocating Tariff Equity; Ecology Center.
Source
- This case was compiled from the Michigan Public Service Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Commission press release: “Case No. U-21986”
- Commission press release: “allow for large load customers drawing 50 megawatts (MW) or more of electricity”
- Commission press release: “a 90% monthly minimum billing demand and 65% monthly minimum energy requirement”