Idaho Power annual update of marginal energy prices for large-load Schedules 20 and 34
Idaho Public Utilities Commission · No. IPC-E-26-08 · Updated Nov 23, 2026, 18:37 ETWhat the case is
Reskill Report summary · the commission lists the case as decided
Idaho Power asked the Commission to acknowledge its updated marginal cost calculations and let it keep the current marginal energy price components of Schedule 20 (Speculative High-Density Load) and Schedule 34 (Lamb Weston Special Contract). The Commission granted this and directed a separate docket on the methodology.
From the docket: “Speculative High-Density Load”
Official title: IN THE MATTER OF IDAHO POWER COMPANY'S APPLICATION FOR ITS ANNUAL UPDATE TO MARGINAL PRICING USED IN CERTAIN SCHEDULES
What the commission decided
In Order No. 37125 the Commission acknowledged the marginal cost calculations as correctly quantified, found the Company complied with Order No. 36619, authorized keeping the current Schedule 20 and 34 marginal energy price components, and directed a separate docket to reevaluate the methodology. · Aug 11, 2026
Who is taking part
Micron Technology, Inc.; Idaho Irrigation Pumpers Association, Inc..
Source
- This case was compiled from the Idaho Public Utilities Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Commission order (Order No. 37125): “Speculative High-Density Load”
- Commission order stating what was authorized: “marginal energy price components of Schedule 20 and Schedule 34”
- Commission order directing a follow-on docket: “open a separate docket to reevaluate the methodology for determining marginal cost rates.”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.