Alliant Energy data center service agreement in Beaver Dam; PSC modifies it, orders large load tariff
Public Service Commission of Wisconsin · No. 6680-TE-115 · Updated Nov 23, 2026, 18:37 ETStateWisconsin
Kind of caseContract with a large customer
Openedn/a
Latest filingn/a
What the case is
Reskill Report summary · the commission lists the case as decided
Alliant Energy applied in April 2025 for approval of an Electric Service Agreement to serve one data center in Beaver Dam under its Individual Contract Rate tariff. The Commission modified the agreement and ordered Alliant to file a stand-alone large load tariff for future data center customers.
From the docket: “Background on Docket 6680-TE-115”
Official title: 6680-TE-115
What the commission decided
The Commission modified the Electric Service Agreement, strengthening the termination charge and adding reporting and financial safeguards, and ordered Alliant to file a stand-alone large load tariff for future data center customers. · May 7, 2026
Terms for large users, as approved
| Term | What it says | The document's words |
|---|---|---|
| Also | Alliant must file a stand-alone large load tariff that future data centers must take. | “the Commission ordered the utility to file a stand-alone large load tariff” Source |
Source
- This case was compiled from the Public Service Commission of Wisconsin's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Commission press release: “Background on Docket 6680-TE-115”
- Commission press release: “In April 2025, Alliant Energy submitted an application seeking approval of an Electric”
- Commission press release: “the Commission ordered the utility to file a stand-alone large load tariff”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.