Texas Senate Bill 6: rules for large electricity users (large loads) in ERCOT
Texas Legislature · No. S.B. No. 6 (89th Legislature, Regular Session, 2025) · Updated Nov 23, 2026, 18:37 ETWhat the case is
Reskill Report summary · the commission lists the case as decided
Texas Senate Bill 6 directs the Public Utility Commission to set interconnection standards for large load customers in ERCOT, with a 75 megawatt demand threshold, and to make them contribute to interconnection costs. The bill passed both houses, and the commission has adopted a rule under it, 16 TAC §25.194.
From the docket: “demand threshold of 75 megawatts unless the commission determines”
Official title: An Act relating to the allocation of costs and the regulation of large loads in the ERCOT power region
What the commission decided
The Legislature passed S.B. 6 in 2025, and the Public Utility Commission adopted new 16 TAC §25.194 in Project No. 58481, implementing the large load interconnection standards of PURA §37.0561. · May 29, 2025
Terms for large users, as enacted in law
| Term | What it says | The document's words |
|---|---|---|
| Counts as a large user at | 75 MW | “demand threshold of 75 megawatts unless the commission determines” Source |
Source
- This case was compiled from the Texas Legislature's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Statute: “demand threshold of 75 megawatts unless the commission determines”
- Commission order: “rule implements Public Utility Regulatory Act (PURA) §37.0561 as enacted by Senate Bill (SB)”
- Statute: “the Senate concurred in House amendments on May 29, 2025”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.