Rowan Stampede LLC complaint against ERCOT, one of the "Batch Zero" large-load complaints
Public Utility Commission of Texas · No. 60396 · Updated Nov 23, 2026, 17:44 ETWhat the case is
Reskill Report summary
Rowan Stampede LLC filed a complaint against ERCOT on 2026-10-14, asking for immediate suspension of conduct and expedited relief. ERCOT, Commission Staff, a group called Joint Large Loads and Skybox Datacenters, LLC have filed in the case. The case has been abated, and lists of issues were filed in November. An order on 2026-11-23 sets a deadline for a proposed schedule and a prehearing conference.
From the docket: “JOINT LARGE LOADS’ COMMENTS ON PROCEDURAL ISSUES IN THE BATCH ZERO COMPLAINTS AND REQUEST FOR COMMISSION-HELD HEARINGS”
Official title: COMPLAINT OF ROWAN STAMPEDE LLC AGAINST THE ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.
Who is taking part
Rowan Stampede LLC; ERCOT; Joint Large Loads; SKYBOX DATACENTERS, LLC.
Latest filings
The 35 filings the docket shows. The 5 in bold name data centers or large loads in their own description.A filing is one party's submission, not a decision.
Source
- The filings and the official title are the Public Utility Commission of Texas's own records, read from its docket system.
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.