Reskill ReportTracking AI's effect on jobs, power and the law

El Paso Electric economic development rates for a new El Paso data center

Public Utility Commission of Texas · No. 56903 · Updated Nov 23, 2026, 18:37 ET
StateTexas
Kind of caseRates and terms for large users
OpenedAug 1, 2024
Latest filingn/a

What the case is

Reskill Report summary · the commission lists the case as decided

El Paso Electric applied on August 1, 2024 for two new rates under its economic development tariff, Rate Schedule No. 33, for a new data center in El Paso. The data center is expected to have a peak demand of over 100 megawatts (MW). The commission approved the rates after the parties filed an agreement.

From the docket: “APPLICATION OF EL PASO ELECTRIC COMPANY FOR AN ECONOMIC DEVELOPMENT RATE RIDER FOR A NEW DATA CENTER TO BE LOCATED IN EL PASO TEXAS”

Official title: APPLICATION OF EL PASO ELECTRIC COMPANY FOR AN ECONOMIC DEVELOPMENT RATE RIDER FOR A NEW DATA CENTER TO BE LOCATED IN EL PASO TEXAS

What the commission decided

The Commission approved El Paso Electric's Rate Schedule No. 33A (large economic development rate) and No. 33B (medium economic development rate), as attached to the parties' agreement, effective the first billing cycle after the Order. · Jul 31, 2025

Terms for large users, as approved

TermWhat it saysThe document's words
AlsoService under Rate Schedules 33A and 33B is limited to five years from initiation unless extended and approved.“service under Rate Schedule Nos. 33A and 33B will not exceed five” Source

Who is taking part

City of El Paso; Texas Industrial Energy Consumers; State Office of Administrative Hearings.

Source

  • This case was compiled from the Public Utility Commission of Texas's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
  • Docket page: “APPLICATION OF EL PASO ELECTRIC COMPANY FOR AN ECONOMIC DEVELOPMENT RATE RIDER FOR A NEW DATA CENTER TO BE LOCATED IN EL PASO TEXAS”
  • Commission order: “The Commission approves El Paso Electric's Rate Schedule No. 33A, large economic”
  • Commission order: “service under Rate Schedule Nos. 33A and 33B will not exceed five”
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
  • Nothing here says who is right or what the case will cost any customer.