Georgia Power 2023 resource plan update: added grid capacity; docket holds large-load reports

Georgia Public Service Commission · No. 55378 · Updated Nov 23, 2026, 18:37 ET
StateGeorgia
Kind of caseNew plants, lines or power purchases
OpenedSep 6, 2023
Latest filingn/a

What the case is

Reskill Report summary · the commission lists the case as decided

The Georgia Public Service Commission unanimously approved Georgia Power's interim Integrated Resource Plan in April 2024, which added extra capacity to the grid. The docket (55378) is still open, and Georgia Power has filed a Large Load Economic Development Report for Q3 2025 in it.

From the docket: “Georgia Power Company?s 2023 Integrated Resource Plan Update”

Official title: Georgia Power Company?s 2023 Integrated Resource Plan Update

What the commission decided

The commission unanimously approved Georgia Power's interim Integrated Resource Plan in April 2024, which added extra capacity to Georgia's power grid.

Who is taking part

Georgia Public Service Commission Public Interest Advocacy Staff; Southern Environmental Law Center; Georgia Interfaith Power & Light.

Source

  • This case was compiled from the Georgia Public Service Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
  • Docket page: “Georgia Power Company?s 2023 Integrated Resource Plan Update”
  • Docket page: “Large Load Economic Development Report for Q3 2025 PD”
  • Commission press release: “on the interim Integrated Resource Plan, unanimously approved by Commissioners in”
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
  • Nothing here says who is right or what the case will cost any customer.