Arkansas Electric Cooperative asks approval of curtailable Demand Response tariff for 50 MW+ users
Arkansas Public Service Commission · No. 25-008-TF · Updated Nov 23, 2026, 18:37 ETStateArkansas
Kind of caseRates and terms for large users
OpenedJan 30, 2025
Latest filingn/a
What the case is
Reskill Report summary · the commission lists the case as open
Arkansas Electric Cooperative Corporation filed a Demand Response Service tariff for member cooperatives serving power-intensive retail consumers of 50 MW or greater whose load can be curtailed. The docket shows the tariff suspended and a joint motion to approve a unanimous settlement filed, and it is listed as open.
From the docket: “a service option for power intensive retail members whose load may need to be subject to curtailment”
Official title: IN THE MATTER OF THE APPLICATION OF ARKANSAS ELECTRIC COOPERATIVE CORPORATION FOR APPROVAL OF ITS DEMAND RESPONSE SERVICE TARIFF
Terms for large users, as proposed
| Term | What it says | The document's words |
|---|---|---|
| Counts as a large user at | 50 MW | “The DRS is available only to loads 50 MW or greater.” Source |
Who is taking part
APSC General Staff.
Source
- This case was compiled from the Arkansas Public Service Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Docket page: “a service option for power intensive retail members whose load may need to be subject to curtailment”
- Filed tariff: “The DRS is available only to loads 50 MW or greater.”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.