Mesquite H2 appeals ERCOT decisions; one of the "Batch Zero" large-load complaint dockets
Public Utility Commission of Texas · No. 60410 · Updated Nov 23, 2026, 17:44 ETWhat the case is
Reskill Report summary
Mesquite H2, LLC filed a complaint appealing unspecified ERCOT decisions and asked for expedited handling. South Texas Electric Cooperative moved to intervene, and Skybox Datacenters and a group called Joint Large Loads also filed. The commission paused the schedule; ERCOT and Joint Large Loads then filed lists of issues for the "Batch Zero" complaints.
From the docket: “JOINT LARGE LOADS’ COMMENTS ON PROCEDURAL ISSUES IN THE BATCH ZERO COMPLAINTS”
Official title: MESQUITE H2, LLC COMPLAINT AND APPEAL OF THE DECISIONS OF THE ELECTRIC RELIABILITY COUNCIL OF TEXAS, INC.
Who is taking part
MESQUITE H2, LLC; ERCOT; Joint Large Loads; SOUTH TEXAS ELECTRIC COOPERATIVE, INC.; Joint Large Load; Juan O Flores Norma L Flores; Marisol Saenz-Zambrano; SOUTH TEXAS ELECTRIC COOPERATIVE, INC; SKYBOX DATACENTERS, LLC.
Latest filings
The 34 filings the docket shows. The 7 in bold name data centers or large loads in their own description.A filing is one party's submission, not a decision.
Source
- The filings and the official title are the Public Utility Commission of Texas's own records, read from its docket system.
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.