APS rate case: changes to Extra High Load Factor rate, requiring data centers to use it
Arizona Corporation Commission · No. E-01345A-25-0105 · Updated Nov 23, 2026, 18:37 ETWhat the case is
Reskill Report summary · the commission lists the case as open
In its general rate case, Arizona Public Service proposes changing its cost allocation and XHLF rate schedule so data centers must take XHLF service, with revised minimum bill and eligibility terms. The hearing ran May 18 to July 7, 2026; the judge's recommended order was expected by late November 2026.
From the docket: “to its cost allocation and XHLF Rate Schedule to ensure that the costs of”
Official title: In the matter of the application of Arizona Public Service Company for a hearing to determine the fair value of the utility property of the company for ratemaking purposes, to fix a just and reasonable rate of return thereon, and to approve rate schedules designed to develop such return.
Terms for large users, as proposed
| Term | What it says | The document's words |
|---|---|---|
| Counts as a large user at | 5 MW | “demand of 5,000 kW or more, and a load factor of 92% or more, for a minimum of” Source |
| Also | Data centers taking service after January 2024 would be required to take service on the XHLF tariff | “must take service on the XHLF tariff” Source |
Who is taking part
Residential Utility Consumer Office; Arizona Attorney General; Data Center Coalition.
Source
- This case was compiled from the Arizona Corporation Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Utility application: “to its cost allocation and XHLF Rate Schedule to ensure that the costs of”
- Commission press release: “Extra High Load Factor (which applies to large load users, such as manufacturing companies and data centers)”
- Utility direct testimony filed in the rate case: “This includes changes to the minimum bill requirements and eligibility”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.