Xcel's Public Service Co. of Colorado asks for more time to file its large load tariff; approved
Colorado Public Utilities Commission · No. 26V-0048E · Updated Nov 23, 2026, 18:37 ETStateColorado
Kind of caseOther
OpenedJan 26, 2026
Latest filingn/a
What the case is
Reskill Report summary · the commission lists the case as decided
Public Service Company of Colorado asked the Commission for a variance from Ordering Paragraph 81 of Decision No. C25-0747 to extend the filing date for its Large Load Tariff. The Commission granted the petition, and the Colorado Energy Office intervened.
From the docket: “Public Service Company -Petition re Large Load Tariff filing”
Official title: Public Service Company -Petition re Large Load Tariff filing
What the commission decided
The Commission granted Public Service's Verified Petition for a Variance from Ordering Paragraph 81 of Decision No. C25-0747 and acknowledged the Colorado Energy Office's notice of intervention. · Mar 11, 2026
Who is taking part
Colorado Energy Office.
Source
- This case was compiled from the Colorado Public Utilities Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Docket page: “Public Service Company -Petition re Large Load Tariff filing”
- Utility petition: “extending the filing date for the Large Load Tariff (“LLT”) to provide additional time for the”
- Commission order (Decision No. C26-0155): “The Verified Petition for a Variance from Ordering Paragraph 81 of Decision No. C25-0747, filed on January 26, 2026, by Public Service Company of Colorado (“Public Service”) is granted.”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.