Rocky Mountain Power large-load service contract with unnamed customer approved by Utah PSC
Public Service Commission of Utah · No. 26-035-05 · Updated Nov 23, 2026, 18:37 ETWhat the case is
Reskill Report summary · the commission lists the case as decided
Rocky Mountain Power asked the Utah PSC to approve a large-load service contract with an unnamed large-load customer. On April 10, 2026, the PSC approved the application, contract and a settlement among RMP, DPU and OCS, and denied the Utah Association of Energy Users' motion for access to restricted materials.
From the docket: “Application of Rocky Mountain Power for Approval of a Large-Load Service Contract between PacifiCorp and a Large-Load Customer”
Official title: Application of Rocky Mountain Power for Approval of a Large-Load Service Contract between PacifiCorp and a Large-Load Customer
What the commission decided
The PSC approved the Application, the large-load service contract and the Settlement, finding the Customer will bear all just and reasonable incremental costs, and denied UAE's motion for access to "regulator access only" materials. · Apr 10, 2026
Terms for large users, as approved
| Term | What it says | The document's words |
|---|---|---|
| Counts as a large user at | 100 MW | “new electric service that is expected to reach a cumulative demand of 100 megawatts” Source |
| Also | Statute gives the commission 60 days to approve or disapprove a large-load contract. | “The Act requires the PSC to issue an order on such requests within 60” Source |
Who is taking part
Division of Public Utilities; Office of Consumer Services; Utah Association of Energy Users; Utah Clean Energy.
Source
- This case was compiled from the Public Service Commission of Utah's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Docket page: “Application of Rocky Mountain Power for Approval of a Large-Load Service Contract between PacifiCorp and a Large-Load Customer”
- Commission order: “For the foregoing reasons, the LLSC and the Settlement are approved.”
- Commission order: “Based on the foregoing findings and conclusions, the PSC approves the”
- Utility application: “approving the large-load service contract between Rocky Mountain Power and a”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.