Santee Cooper experimental Large Load rate schedule L-25-LL for data centers and other big users

South Carolina Public Service Authority (Santee Cooper) Board of Directors · No. Schedule L-25-LL · Updated Nov 23, 2026, 18:37 ET
StateSouth Carolina
Kind of caseRates and terms for large users
OpenedApr 25, 2025
Latest filingn/a

What the case is

Reskill Report summary · the commission lists the case as decided

Santee Cooper adopted an experimental Large Load Service schedule, mandatory for data centers and other facilities over 50,000 kW. It requires a service term of at least 180 months, upfront payment of delivery point and transmission costs, and collateral equal to 180 months of Minimum Bills.

From the docket: “aggregate monthly maximum demand of greater than 50,000 kW”

Official title: LARGE LIGHT AND POWER EXPERIMENTAL LARGE LOAD SERVICE SCHEDULE L-25-LL

What the commission decided

Santee Cooper adopted Schedule L-25-LL on April 25, 2025, effective for bills rendered on and after that date, and available through no later than April 24, 2029. · Apr 25, 2025

Terms for large users, as approved

TermWhat it saysThe document's words
Counts as a large user at50 MW“aggregate monthly maximum demand of greater than 50,000 kW” Source
Deposit or exit termsCollateral equal to 180 months of minimum bills; at least 12 months as a cash deposit.“At least twelve (12) months of Minimum Bills shall be in the form of a” Source
AlsoExperimental; service available only through April 24, 2029, with no guarantee of renewal.“Expires no later than April 24, 2029” Source

Source

  • This case was compiled from the South Carolina Public Service Authority (Santee Cooper) Board of Directors's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
  • Filed tariff: “aggregate monthly maximum demand of greater than 50,000 kW”
  • Utility press release: “Revised industrial customer rates also include a High Impact Load Rate, which builds on and transitions the 2025 Experimental Large Load Rate Santee Cooper into a standard offering.”
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
  • Nothing here says who is right or what the case will cost any customer.