NJ BPU seeks input on rules for large data center electricity tariffs under Data Center Fair Share Act

New Jersey Board of Public Utilities · No. EO26080463 · Updated Nov 23, 2026, 18:37 ET
StateNew Jersey
Kind of caseCommission rules or inquiry
Openedn/a
Latest filingn/a

What the case is

Reskill Report summary · the commission lists the case as open

New Jersey Board of Public Utilities staff issued a request for information and a November 4, 2026 stakeholder meeting on requirements for utilities to file tariffs for large data center customers. The Data Center Fair Share Act requires the Board to set standards within 12 months, then each utility must petition for a rate class.

From the docket: “IN THE MATTER OF THE IMPLEMENTATION OF THE DATA CENTER FAIR SHARE ACT”

Official title: In the Matter of the Implementation of the Data Center Fair Share Act

Terms for large users, as proposed

TermWhat it saysThe document's words
Counts as a large user at50 MW“megawatt size designation, which shall not be greater than 50 megawatts. For the purpose of” Source
Must pay for at least85% of contracted demand“it will pay for at least 85 percent of the electricity supply it requests for a period of 10 years” Source
Minimum contract10 years“it will pay for at least 85 percent of the electricity supply it requests for a period of 10 years” Source
Deposit or exit termsDeposits, financial security or, for highly rated customers, financial commitments, plus a class-only stranded cost mechanism.“(2) provide for the posting of deposits, financial security, or, for large data center customers” Source
AlsoUtilities must file their rate class and tariff petitions within 180 days of the Board's standards order.“c. No later than 180 days after the board issues an order establishing standards for the” Source

Source

  • This case was compiled from the New Jersey Board of Public Utilities's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
  • Docket page: “IN THE MATTER OF THE IMPLEMENTATION OF THE DATA CENTER FAIR SHARE ACT”
  • Docket page: “The deadline for responses on this matter is 5 p.m. on November 13, 2026.”
  • Statute: “each electric public utility shall file a petition with the board for approval of a rate class and”
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
  • Nothing here says who is right or what the case will cost any customer.