Oregon PUC sets PGE data center rate class (Schedule 96) under the POWER Act
Public Utility Commission of Oregon · No. UM 2377 · Updated Nov 23, 2026, 18:37 ETWhat the case is
Reskill Report summary · the commission lists the case as decided
The Commission investigated how Portland General Electric's tariff treats large loads and, in Order No. 26-154, implemented the POWER Act with a data center class, Schedule 96. PGE then filed Advice No. 26-24 to update its tariffs, and Staff recommends the Commission approve it.
From the docket: “Creates Schedule 96, Data Center Standard Service as well as all Direct Access”
Official title: In the Matter of PUBLIC UTILITY COMMISSION OF OREGON, Investigation into Marginal Cost Study Treatment of Costs for Large Customers and Further Modifications to Portland General Electric Company's Rule C and Rule I.
What the commission decided
Order No. 26-154 adopted Schedule 96 with modifications, ordered revisions to Schedules 89 and 90 and to Rules C and I, and adopted the first partial stipulation. · May 7, 2026
Terms for large users, as approved
| Term | What it says | The document's words |
|---|---|---|
| Counts as a large user at | 20 MW | “a facility that uses or is able to use 20 megawatts or more and is primarily engaged in” Source |
| Must pay for at least | 90% of contracted demand | “transmission and generation demand provisions of 90 percent of contracted capacity, and” Source |
| Minimum contract | 10 years | “We are persuaded that the proposals to have a minimum contract term of 10 years that” Source |
Who is taking part
Staff of the Public Utility Commission of Oregon; Alliance of Western Energy Consumers (AWEC); Amazon; Data Center Coalition; Oregon Citizens' Utility Board (CUB); Northwest & Intermountain Power Producers Coalition; Verrus; Columbia River Inter-Tribal Fish Commission (CRITFC).
Source
- This case was compiled from the Public Utility Commission of Oregon's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Commission order (Order No. 26-239, compliance filing): “Creates Schedule 96, Data Center Standard Service as well as all Direct Access”
- Commission order (Order No. 26-154): “transmission and generation demand provisions of 90 percent of contracted capacity, and”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.