Oregon HB 3546 (POWER Act): separate rate class and long contracts for large data-center users
Public Utility Commission of Oregon · No. HB 3546 (2025) · Updated Nov 23, 2026, 18:37 ETWhat the case is
Reskill Report summary · the commission lists the case as decided
Oregon's Legislature enacted a law directing the Public Utility Commission to create a separate service classification and tariff for large energy use facilities, meaning data centers using or able to use 20 megawatts or more. Utilities serving them must sign contracts of 10 years or longer with minimum payment obligations.
From the docket: “The Public Utility Commission shall provide for a classification of service under ORS”
Official title: Enrolled House Bill 3546 (HB 3546-B) - Relating to large energy use facilities; and declaring an emergency
What the commission decided
The Legislature enacted HB 3546, requiring the PUC to create a separate large energy use facility classification with its own tariff and to require contracts of 10 years or longer with a minimum payment obligation. · Jun 5, 2025
Terms for large users, as enacted in law
| Term | What it says | The document's words |
|---|---|---|
| Counts as a large user at | 20 MW | “means a facility that uses or is able to use 20 megawatts” Source |
| Minimum contract | 10 years | “Specify the duration of the contract and be for a duration for 10 years or longer” Source |
| Also | Customer must pay a minimum amount or percentage of projected usage, set by the commission. | “Obligate the retail electricity consumer to pay a minimum amount or percentage” Source |
Source
- This case was compiled from the Public Utility Commission of Oregon's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Statute (enrolled bill text): “The Public Utility Commission shall provide for a classification of service under ORS”
- Commission report to the legislature: “The POWER Act, HB 3546 (2025), directs the PUC to create a separate rate class for data”
- Commission report naming the implementing dockets: “UM 2377 for Portland General Electric and”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.