APS asks Arizona regulators to approve 25-year direct pricing contract for TSMC Arizona

Arizona Corporation Commission · No. E-01345A-26-0454 · Updated Nov 23, 2026, 18:37 ET
StateArizona
Kind of caseContract with a large customer
OpenedNov 6, 2026
Latest filingn/a

What the case is

Reskill Report summary · the commission lists the case as open

Arizona Public Service asked the Arizona Corporation Commission to approve a 25-year Direct Pricing Contract with TSMC Arizona Corporation, plus related accounting orders and resource findings. The contract contemplates ramping to approximately 1.88 GW and includes fixed capacity charges, exit fees and collateral obligations.

From the docket: “requests that the Arizona Corporation Commission (Commission or ACC) approve the”

Official title: In the matter of the application of Arizona Public Service Company for approval of direct pricing contract with TSMC Arizona Corporation and associated accounting orders and regulatory findings.

Terms for large users, as proposed

TermWhat it saysThe document's words
Minimum contract25 years“The DPC formalizes a 25-year commitment by TSMC to take firm service under” Source
Deposit or exit termsRisk-based collateral (cash, surety bonds or letters of credit) covering three years of fixed capacity payments“three years of coverage for all fixed contract capacity payments.” Source
AlsoCustomer must give at least five years' notice before the contract ends or pay a resource value reconciliation“provide at least five-years' notice prior to the end of the DPC” Source

Who is taking part

TSMC Arizona Corporation.

Source

  • This case was compiled from the Arizona Corporation Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
  • Utility application: “requests that the Arizona Corporation Commission (Commission or ACC) approve the”
  • Utility application: “The DPC formalizes a 25-year commitment by TSMC to take firm service under”
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
  • Nothing here says who is right or what the case will cost any customer.