Xcel Colorado asks approval of large-load tariff (Schedule TL) for new loads of 50 MW or more

Colorado Public Utilities Commission · No. 26AL-0137E · Updated Nov 23, 2026, 18:37 ET
StateColorado
Kind of caseRates and terms for large users
OpenedApr 2, 2026
Latest filingn/a

What the case is

Reskill Report summary · the commission lists the case as open

Public Service Company of Colorado filed Advice Letter 2018-Electric proposing Schedule TL, a transmission-level rate for new or expanded loads of 50 MW or more, plus line extension changes and an optional Clean Transition Tariff. The Commission suspended the tariff and set an en banc hearing; the docket status is Suspended.

From the docket: “Public Service Company - AL 2018 - Tariff 8 - Large Load”

Official title: Public Service Company - AL 2018 - Tariff 8 - Large Load

Terms for large users, as proposed

TermWhat it saysThe document's words
Counts as a large user at50 MW“reasonably forecast new incremental (expanded) Demands are 50 MW or more on or” Source
Must pay for at least80% of contracted demand“the greater of: Measured Demand used during the Month, or eighty percent (80%) of the” Source
Minimum contract15 years“All service under this schedule shall be for a minimum period of fifteen (15)” Source
Deposit or exit termsCustomer unable to give a guaranty must post credit support of 60 times the minimum monthly bill.“Agreement multiplied by sixty (60). Such credit support shall be in” Source
AlsoExit fee equals all minimum monthly bills remaining for the rest of the contract term.“Minimum Monthly Bills for each of the remaining months of the term of” Source

Who is taking part

Google LLC; Data Center Coalition; Office of Utility Consumer Advocate; Colorado Energy Consumers Group; Colorado Energy Office; Climax Molybdenum Company; United Power, Inc.; Western Resource Advocates.

Source

  • This case was compiled from the Colorado Public Utilities Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
  • Docket page: “Public Service Company - AL 2018 - Tariff 8 - Large Load”
  • Utility advice letter: “customers with 50 MW of new or new incremental (expanded) load.”
  • Commission order (Decision No. C26-0280): “is suspended for 120 days to August 31, 2026, or until further order of the Commission.”
  • Docket page: “Data Center Coalition's Statement of Position”
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
  • Nothing here says who is right or what the case will cost any customer.