PG&E seeks Electric Rule 30 for large transmission-level customers; interim version partly approved

California Public Utilities Commission · No. A.24-11-007 · Updated Nov 23, 2026, 18:37 ET
StateCalifornia
Kind of caseConnecting to the grid
OpenedNov 21, 2024
Latest filingn/a

What the case is

Reskill Report summary · the commission lists the case as open

PG&E applied for Electric Rule 30, a tariff for large transmission-level customers (50-230 kilovolts) seeking retail service, and moved for interim implementation. The Commission partly granted that motion in Decision 25-07-039 and deferred refunds and cost allocation to the final decision.

From the docket: “Rule 30 tariff for large transmission-level customers (50-230 kilovolts) seeking”

Official title: Application of Pacific Gas and Electric Company (U39E) for Approval of Electric Rule No. 30 for Transmission-Level Retail Electric Service.

Terms for large users, as proposed

TermWhat it saysThe document's words
Deposit or exit termsCustomer prefunds 100 percent of Type 4 transmission network upgrade cost; repayment not guaranteed.“100 percent of the project cost as a pre-funded loan.” Source
AlsoInterim Rule 30 applies to large transmission-level retail customers served at 50 to 230 kilovolts.“Rule 30 tariff for large transmission-level customers (50-230 kilovolts) seeking” Source

Who is taking part

The Utility Reform Network; Public Advocates Office at the California Public Utilities Commission; Joint CCAs; Shell Energy.

Source

  • This case was compiled from the California Public Utilities Commission's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
  • Commission order (Decision 25-07-039): “Rule 30 tariff for large transmission-level customers (50-230 kilovolts) seeking”
  • Commission order (Decision 25-07-039, ordering paragraph 1.c): “100 percent of the project cost as a pre-funded loan.”
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
  • Nothing here says who is right or what the case will cost any customer.