NV Energy proposes Large Load Electric Service Agreement for data centers and other big users
Public Utilities Commission of Nevada · No. 26-05029 · Updated Nov 23, 2026, 18:37 ETStateNevada
Kind of caseContract with a large customer
Openedn/a
Latest filingn/a
What the case is
Reskill Report summary
NV Energy has proposed a Large Load Electric Service Agreement for customers, such as data centers, whose energy needs typically exceed 25 megawatts. Those customers must make long-term commitments, pay minimum usage levels and provide financial guarantees.
From the docket: “Large customers with energy needs that typically exceed”
Official title: Application of Nevada Power Company d/b/a NV Energy for approval of Large Load Electric Service Agreements with Novva Las Vegas, LLC and Proton NLV, LLC.
Who is taking part
Novva Las Vegas, LLC; Proton NLV, LLC.
Source
- This case was compiled from the Public Utilities Commission of Nevada's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
- Utility fact sheet: “Large customers with energy needs that typically exceed”
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.