Duke Energy asks SC regulators to open a comment docket on large load additions of 50 MW or more

Public Service Commission of South Carolina · No. 2026-138-E · Updated Nov 23, 2026, 18:37 ET
StateSouth Carolina
Kind of caseCommission rules or inquiry
OpenedMay 27, 2026
Latest filingn/a

What the case is

Reskill Report summary · the commission lists the case as open

Duke Energy Carolinas and Duke Energy Progress petitioned the South Carolina commission to open a generic docket for comments on new large loads (50 megawatts or greater), including rate schedules, line extension policies and interconnection rules. The docket is open, and Order No. 2026-362 clarified the procedural schedule.

From the docket: “On June 17th, the Public Service Commission issued Order No. 2026-362, which clarifies the procedural”

Official title: Petition to Establish a Generic Docket for the Purpose of Receiving Comments Addressing Large Load Additions

Terms for large users, as proposed

TermWhat it saysThe document's words
Counts as a large user at50 MW“with new large load (50 megawatts or greater) additions, including existing rate schedules, service regulations,” Source

Who is taking part

South Carolina Office of Regulatory Staff; Sierra Club; Nucor Steel - South Carolina; Google, LLC; Dominion Energy South Carolina, Inc.; South Carolina Coastal Conservation League, Southern Alliance for Clean Energy, and Vote Solar; Carolinas Clean Energy Business Association; South Carolina Department of Consumer Affairs.

Source

  • This case was compiled from the Public Service Commission of South Carolina's and the utility's own documents, not from a docket system we read daily, so it shows no filing list and may lag. The case's own page.
  • Commission press release: “On June 17th, the Public Service Commission issued Order No. 2026-362, which clarifies the procedural”
  • Docket page: “Petition to Establish a Generic Docket for the Purpose of Receiving Comments Addressing Large Load Additions”
  • The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
  • Nothing here says who is right or what the case will cost any customer.