Dominion Energy Virginia seeks approval of its queue process for connecting large loads
Virginia State Corporation Commission · No. PUR-2026-00011 · Updated Nov 23, 2026, 17:44 ETWhat the case is
Reskill Report summary · the commission lists the case as pending
Virginia Electric and Power Company (Dominion) asked the State Corporation Commission to approve its large-load connection queue process. Data center and tech companies, including Amazon, Google, Microsoft, STACK and Verrus, the Data Center Coalition and the Piedmont Environmental Council took part. Hearings were held April 28–30, 2026, post-hearing briefs were filed June 30, and the Commission issued an order on October 23, 2026.
From the docket: “Virginia Electric and Power Company - For approval of its large-load connection queue process”
Official title: Virginia Electric and Power Company - For approval of its large-load connection queue process
Latest filings
The 60 most recent of 128 filings the docket shows. The 3 in bold name data centers or large loads in their own description.A filing is one party's submission, not a decision.
Source
- The filings and the official title are the Virginia State Corporation Commission's own records, read from its docket system.
- The plain title and summary are ours, written from the docket's title and filing list and checked against them. We have not read every document in the case.
- Nothing here says who is right or what the case will cost any customer.